In: Finance
Consider the following two mutually exclusive projects: |
Year |
Cash Flow (A) |
Cash Flow (B) |
|||||
0 |
–$ |
315,500 |
– |
40,300 |
|||
1 |
42,000 |
21,500 |
|||||
2 |
63,000 |
19,000 |
|||||
3 |
68,000 |
16,500 |
|||||
4 |
415,000 |
14,600 |
|||||
Whichever project you choose, if any, you require a 12 percent return on your investment. When evaluating projects solely on the basis of payback, the firm payback requirement for projects is 2.3 years. You do not need to show each calculator keystroke but you do need to describe how you calculated each answer. (Round your answers to 2 decimal places) |
a) |
What is the payback period for each project? Indicate the best project you would accept, if either, based on this criteria. |
b) |
What is the discounted payback period for each project? Indicate the best project you would accept, if either, based on this criteria. |
c) |
What is the NPV for each project? Indicate the best project you would accept, if either, based on this criteria. |
d) What is the IRR for each project? Indicate the best project you would accept, if either, based on this criteria.
e) |
What is the profitability index for each project? Indicate the best project you would accept, if either, based on this criteria. |
f) Based on your analysis above, which project will you finally choose, and why?
A) Payback period
Project A
project A | ||
year | cash flow | cumulative cashflow |
1 | 42000 | 42000 |
2 | 63000 | 105000 |
3 | 48000 | 153000 |
4 | 415000 | 568000 |
Pay back period= 3 years +[ (315500-153000)/ (568000-153000) ] * 12
3 years + (162500/415000) * 12
3 years + 0.3916* 12
3 years and 4.7 months
Payback period = 3.47
Project B
project B | ||
year | cash flow | cumulative cashflow |
1 | 21500 | 21500 |
2 | 19000 | 40500 |
3 | 16500 | 57000 |
4 | 14600 | 71600 |
Pay back period= 1 year +[ (40300-21500)/ (40500-21500) ] * 12
1 year + (18800/19000) * 12
1 year + 0.9895* 12
1 year and 11.8 months
Payback period = 1.12
Project B have a less pay back period. It is better to select project B on the basis of payback period and also it is less than the firms payback requirements.
B) Discounted Payback period
Project A
project A | ||||
year | cash flow | pvf @ 12% | pv of cashflow | cumulative cashflow |
1 | 42000 | 0.892857 | 37500 | 37500 |
2 | 63000 | 0.797194 | 50223.214 | 87723.214 |
3 | 48000 | 0.71178 | 34165.452 | 121888.67 |
4 | 415000 | 0.635518 | 263740 | 385628.67 |
Discounted Pay back period= 3 years +[ (315500-121888.67)/ (385628.67-121888.67) ] * 12
3 years + (193611.33/363740) * 12
3 years + 0.5323* 12
3 years and 6.38 months
Discounted Payback period = 3.64
Project B
project B | ||||
year | cash flow | pvf @ 12% | pv of cashflow | cumulative cashflow |
1 | 21500 | 0.892857 | 19196.4286 | 19196.429 |
2 | 19000 | 0.797194 | 15146.6837 | 34343.112 |
3 | 16500 | 0.71178 | 11744.3741 | 46087.486 |
4 | 14600 | 0.635518 | 9278.56394 | 55366.05 |
Discounted Pay back period= 2 years +[ (40300-34343.112)/ (46087.486-34343.112) ] * 12
2 year + (5956.888/11744.374) * 12
2 years + 0.5072* 12
2 years and 6.09 months
Discounted Payback period = 2.61
Project B have a less discounted pay back period. It is better to select project B on the basis of discounted payback period
C) Net Present Value (NPV)
NPV = Present value of cash inflow – Initial investment
project A | |||
year | cash flow | pvf @ 12% | pv of cashflow |
1 | 42000 | 0.892857 | 37500 |
2 | 63000 | 0.797194 | 50223.214 |
3 | 48000 | 0.71178 | 34165.452 |
4 | 415000 | 0.635518 | 263740 |
Total present value | 385628.67 | ||
(less) cash outflow | -315500.00 | ||
Net Present Value (NPV) | 70128.67 |
project B | |||
year | cash flow | pvf @ 12% | pv of cashflow |
1 | 21500 | 0.892857 | 19196.4286 |
2 | 19000 | 0.797194 | 15146.6837 |
3 | 16500 | 0.71178 | 11744.3741 |
4 | 14600 | 0.635518 | 9278.56394 |
Total present value | 55366.05 | ||
(less) cash outflow | -40300.00 | ||
Net Present Value (NPV) | 15066.05 |
Considering NPV both projects showing a positive value, project A is more profitable. Firm can go with project A (Accept project A)
D) Internal Rate of Return (IRR)
IRR = Lowest rate + [(NPV at lowest rate)/(NPV at lowest rate –NPV at highest rate)] * difference in rate
Project A
project A | |||
year | cash flow | pvf @ 12% | pv of cashflow |
1 | 42000 | 0.892857 | 37500 |
2 | 63000 | 0.797194 | 50223.214 |
3 | 48000 | 0.71178 | 34165.452 |
4 | 415000 | 0.635518 | 263740 |
Total present value | 385628.67 | ||
(less) cash outflow | -315500.00 | ||
Net Present Value (NPV) | 70128.67 | ||
project A | |||
year | cash flow | pvf @ 20% | pv of cashflow |
1 | 42000 | 0.833333 | 35000 |
2 | 63000 | 0.694444 | 43750 |
3 | 48000 | 0.578704 | 27777.778 |
4 | 415000 | 0.482253 | 200135.03 |
Total present value | 306662.81 | ||
(less) cash outflow | -315500.00 | ||
Net Present Value (NPV) | -8837.19 |
= 12+(70128.67)/( 70128.67-(-8837.19))]*20-12
= 12+[70128.67/78965.86]*8
= 12+ 7
IRR for the project A = 19%
Project B
project B | project B | |||||||
year | cash flow | pvf @ 20% | pv of cashflow | year | cash flow | pvf @ 32% | pv of cashflow | |
1 | 21500 | 0.833333 | 17916.6667 | 1 | 21500 | 0.757576 | 16287.879 | |
2 | 19000 | 0.694444 | 13194.4444 | 2 | 19000 | 0.573921 | 10904.5 | |
3 | 16500 | 0.578704 | 9548.61111 | 3 | 16500 | 0.434789 | 7174.0129 | |
4 | 14600 | 0.482253 | 7040.89506 | 4 | 14600 | 0.329385 | 4809.0261 | |
Total present value | 47700.62 | Total present value | 39175.42 | |||||
(less) cash outflow | -40300.00 | (less) cash outflow | -40300.00 | |||||
Net Present Value (NPV) | 7400.62 | Net Present Value (NPV) | -1124.58 |
= 20+(7400.62)/( 7400.62-(-1124.58))]*32-20
= 20+[7400.62/8525.2]*12
= 20+ 10.4
IRR for the project B = 30.4%
IRR in case of project B is higher than Project A, Hence project B is preferable.
E) Profitability index
Profitability index = Total present value of inflow/ Total present value of outflow
Project A
Profitability index = 385628.67/315500
Profitability index = 1.22
Project B
Profitability index = 55366.05/40300
Profitability index = 1.37
Project B is acceptable, it showing a higher PI
F)
Project B is preferable, all the evaluation technique except NPV suggest project B. when we look in to the NPV value Project A showing high but when we deeply examine the NPV percent is less when compared to its cash inflow. So, it’s better to select Project B.