Question

In: Accounting

In early 2019, Bridge Company entered into a long term contract to construct a bridge for...

In early 2019, Bridge Company entered into a long term contract to construct a bridge for Greensville County for $10 million. The bridge will take three years to complete. In 2019, Bridge spent $2.8 million on the project, recognized $3.5 million in revenue and $.7 million in profit. In 2020, Bridge spent $4.2 million on the project, recognized $3.8 million in revenue and a $.4 million loss. Bridge billed Greensville $3.0 million in 2019 and $4.5 million in 2020. Greensville paid Bridge $2.6 million in 2019 and $4.3 million in 2020. Bridge Company recognizes revenue on all contracts over time, as the project is being completed by using the cost to cost approach. When preparing the December 31, 2019 and the December 31, 2020 balance sheets what would Bridge report in regards to this contract?

Solutions

Expert Solution

Contract Price          10,000,000
In 2019 Billed
Revenue Recognized            3,500,000
Less: Cost incurred            2,800,000
Profit booked                700,000
Billed            3,000,000
Less: Collected            2,600,000
               400,000
In 2020
Revenue Recognized            3,800,000
Less: Cost incurred            4,200,000
Profit booked              (400,000)
Billed            4,500,000
Less: Collected            4,300,000
               200,000
In 2019
Contract asset (Revenue recognised-billed)                500,000 (3.5m-3m)
Accounts Receivable(Billed-collected)                400,000 (3m-2.6m)
In 2020
Contract Liability (billed till date -Revenue recognised till date)                200,000 (3m+4.5m-3.5m-3.8m)
Accounts Receivable(Billed till date -collected till date)-contract liability if any                400,000 (3m+4.5m-2.6-4.3-.2m)

Related Solutions

In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year    $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $5,600,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year    $2,600,000 $3,900,000    $5,100,000 a. Westgate recognizes revenue over time according to percentage of completion....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000....
In 2021, the Westgate Construction Company entered into a contract to construct a bridge for $12,000,000. The bridge was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year    $1,840,000 $3,760,000 $4,500,000 Estimated costs to complete as of year-end $6,160,000 $5,600,000 $0 Billings during the year $3,000,000 $4,000,000 $5,000,000 Cash collections during thee year    $2,600,000 $3,900,000    $5,100,000 a. Westgate recognizes revenue over time according to percentage of completion....
On January 1 2019 Areej entered into a contract with a customer to construct a stadium...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium for consideration of $ 200 million. The contract was expected to take 2 years to complete. At 31 December 2019 Areej had incurred costs of $ 55 million, Costs to complete are estimated at $ 50 million. In addition to these costs, Amir purchased plant to be used on the contract at a cost of $ 30 million. This plant was purchased on 1...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
In 2013, the Plumbing Company entered into a contract to construct a road for San Diego...
In 2013, the Plumbing Company entered into a contract to construct a road for San Diego County for $12,000,000. The road was completed in 2015. Information related to the contract is as follows: 2013 2014 2015 Cost incurred during the year $3,000,000 $3,800,000 $2,700,000 Estimated costs to complete as of year-end 6,300,000 2,400,000 0 Billings during the year 3,700,000 4,000,000 4,300,000 Cash collections during the year 2,800,000 4,800,000 4,400,000 Calculate the amount of revenue and gross profit to be recognized...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,100,000 $ 3,150,000 $ 2,475,000 Estimated costs to complete as of year-end 5,400,000 2,250,000 0 Billings during the year 2,150,000 3,100,000 4,750,000 Cash collections during the year 1,875,000 3,100,000 5,025,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 3,471,000 $ 4,005,000 $ 1,566,400 Estimated costs to complete as of year-end 5,429,000 1,424,000 0 Billings during the year 2,900,000 4,576,000 2,524,000 Cash collections during the year 2,700,000 4,500,000 2,800,000 Assume that Westgate Construction’s contract with Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows. 2018 2019 2020 Cost incurred during the year $ 2,044,000 $ 2,628,000 $ 2,890,800 Estimated costs to complete as of year-end 5,256,000 2,628,000 0 Billings during the year 2,170,000 2,502,000 5,328,000 Cash collections during the year 1,885,000 2,600,000 5,515,000 5. Calculate the amount of revenue and...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate Construction uses the completed contract method...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT