In: Operations Management
Case: Titan Electric Company
The Titan Electric Company (TEC) manufactures and distributes electronic transformers used to distribute electric power throughout the US. The company started with a small manufacturing plant in Reno and gradually built a customer base throughout the Southwest. A distribution center was established in Denver, and later, as business expanded, their second and third distribution centers were established in Tucson and Sacramento. To date, the company operates two plants, three distribution centers and nine warehouse locations. Manufacturing costs differ between the company’s production plants. The cost of each transformer produced at the Reno plant is $1200. The newer Las Vegas plant utilizes more efficient equipment; as a result, manufacturing costs $1050 per transformer.
The cost of shipping a transformer from each of the two plants to each of the three distribution centers is shown in Table 1, below. Note that due to lack of Interstate highways, no shipments are allowed from Reno plant to the Tucson distribution center. The annual production capacity is 30,000 transformers at the Reno plant and 20,000 at the Las Vegas plant.
Table 1. Shipping Costs to Distribution Centers |
|||
Distribution Center |
|||
Plants |
Sacramento |
Denver |
Tucson |
Reno |
23.50 |
38.20 |
-- |
Las Vegas |
38.00 |
32.00 |
33.00 |
The company serves their nine warehouses from the three
distribution centers. The forecast of the number of meters needed
in each warehouse for the next quarter is shown in Table 2,
below.
Table 2. Demand Forecast |
|
Warehouse |
Demand |
Albuquerque |
6300 |
Dallas |
4900 |
Los Angeles |
2100 |
Omaha |
1200 |
Phoenix |
6100 |
Salt Lake City |
4800 |
San Francisco |
2800 |
Seattle |
8600 |
Wichita |
4500 |
The cost per unit of shipping from each distribution center to each
warehouse is given in Table 3, below. Note that some distribution
centers cannot serve certain warehouses. These are indicated by a
dash, “—”. Titan is interested in developing manufacturing plans
for its plants, and shipping plans for its distribution centers
that result in the lowest overall costs.
Table 3. Shipment Costs to Customer Zones |
|||
Distribution Center |
|||
Customer Zone |
Sacramento |
Denver |
Tucson |
Albuquerque |
-- |
27.00 |
27.50 |
Dallas |
-- |
30.00 |
29.00 |
Los Angeles |
24.50 |
32.00 |
27.00 |
Omaha |
-- |
26.00 |
32.00 |
Phoenix |
32.55 |
25.75 |
18.50 |
Salt Lake City |
31.50 |
27.50 |
-- |
San Francisco |
19.75 |
47.50 |
-- |
Seattle |
28.00 |
38.80 |
-- |
Wichita |
-- |
22.00 |
-- |
Assignment Questions
6.Titan is considering a proposal to ship up to 2000 transformers directly from its Las Vegas plant to the Salt Lake City warehouse. The cost of shipping directly is estimated to be $50 per transformer, with no change in manufacturing costs. Under this new plan, what are the new manufacturing and shipping plans? How much would Titan save?
The formulation of LP and the constrains
The solution for all the mentioned are
Reno
is full.