Question

In: Finance

Which of the following statement regarding Profitability Index (PI) is correct? you should accept a project...

Which of the following statement regarding Profitability Index (PI) is correct? you should accept a project if PI is greater than 0 you should use PI to compare and select mutually exclusive projects you should accept a project if PI is greater than 1

Solutions

Expert Solution

Option a is incorrect since the profitability index of a project needs to be greater than 1 to accept the project.

Option b is incorrect since the net present value is the capital budgeting method that is used to select mutually exclusive projects.

Option c is correct a profitability index greater than 1 indicates that the project is profitable.

Hence, option c.


Related Solutions

As a general rule, if using the Profitability Index as a guide to accept/reject a project,...
As a general rule, if using the Profitability Index as a guide to accept/reject a project, you should accept the project if the Profitability Index is             a equal to 0             b greater than 0             c greater than 1             d greater than the IRR
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
Which of the following statements is most correct? A. Profitability Index decision rule adjust for the...
Which of the following statements is most correct? A. Profitability Index decision rule adjust for the time value of money B. Payback period decision rule provides information on whether the project is creating value for the firm C. NPV decision rule cannot be used to evaluate mutually exclusive projects D. IRR decision rule is the best method of analyzing mutually exclusive projects Which of the following statements is NOT correct? A. Capital asset pricing model explains the relationship between the...
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each...
For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years. Risk free rate = 1.10%, MRP = 9.5%, Required return = 14.40% Yes excel is fine Expected cash flows for the four potential projects that Avalon is...
1. Based on the profitability index rule, should a project with the following cash flows be...
1. Based on the profitability index rule, should a project with the following cash flows be accepted if the discount rate is 12 percent? Why or why not? Year Year Cash Flow 0 $-26,200 1 $11,800 2 $0 3 $24,900
You have to choose between two options using   PI (profitability index) as your project evaluation tool....
You have to choose between two options using   PI (profitability index) as your project evaluation tool. The company use a 15% discount rate The project “A” needs $25,000 for initial investment and will produce in 3 years $18,000 per year. The project “B” needs $50,000 for initial investment and will produce in 3 years $35,000 per year
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown as follows if the appropriate cost of capital is 10%. Time 0 1 2 3 4 5 Cash Flow -250 75 0 100 75 50 a) 2.41, accept b) 0.023, reject c) 0.90, reject d) 1.97, accept
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 8 percent. Time: 0, 1, 2, 3, 4, 5 Cash Flow: -82, -82, 0, 117, 92, 67 Time: 0 1 2 3 4 5 Cash flow: -82 -82 0 117 92 67 Multiple Choice 48.17 percent, reject 8.00 percent, accept 58.74 percent, accept 47.21 percent, reject All information is...
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -75 -75 0 100 75 50
Compute the PI statistic for Project X and note whether the firm should accept or reject...
Compute the PI statistic for Project X and note whether the firm should accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.   Time: 0 1 2 3 4 5   Cash flow: -80 -80 0 115 90 65   
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT