Question

In: Accounting

You are considering an investment for which you require a 13.5 percent rate of return. The...

You are considering an investment for which you require a 13.5 percent rate of return. The investment costs $58,900 and will produce cash inflows of $25,000 for 3 years. Should you accept this project based on its internal rate of return? Why or why not?


A. Yes; because the IRR is 13.13 percent
B. Yes; because the IRR is 13.65 percent
C. Yes; because the IRR is 13.67 percent
D. No; because the IRR is 13.13 percent
E. No; because the IRR is 13.65 percent

F. There is no IRR for the project

Solutions

Expert Solution

Answer)

Calculation of Internal rate of return

Internal rate of return is the rate at which the present value of cash inflows will be equal to the Initial cash outflow.

Initial investment = Annual cash inflows X Present value of annuity of $ 1 at Internal rate of return for 3 years

Present value of annuity of $ 1 at Internal rate of return for 3 years = Initial investment/ Annual cash inflows

                                                                                                              = $ 58,900/ $ 25,000

                                                                                                              = 2.356               

The present value of annuity factor against 3 years row corresponding to 13% rate is 2.36115 and to 14% rate is 2.32163. Therefore internal rate of return can be calculated by interpolating between these two rates.

Internal rate of return = 13% + [(2.36115 – 2.356)/ (2.36115 -2.32163)]

                                        = 13% + (0.00515/ 0.03952)

                                        = 13.13%

Therefore internal rate of return on investment is 13.13%.

Decision: Since the internal rate of return on investment (i.e. 13.13%) is less than the required rate of return (i.e. 13.5%), the project should not be accepted.

Final answer: (D) No; because the IRR is 13.13 percent.

           


Related Solutions

6. You require a 14 percent rate of return from an investment. The investment costs $58,000...
6. You require a 14 percent rate of return from an investment. The investment costs $58,000 and will produce cash inflows of $25,000 for 3 years. Should you accept this project based on its internal rate of return? Why or why not? A. Yes; because the IRR is 14.04 percent B. Yes; because the IRR is 14.65 percent C. Yes; because the IRR is 14.67 percent D. No; because the IRR is 13.04 percent E. None of the above 7....
An investment offers a total return of 13.5 percent over the coming year. Janice Yellen thinks...
An investment offers a total return of 13.5 percent over the coming year. Janice Yellen thinks the total real return on this investment will be only 5.5 percent. What does Janice believe the inflation rate will be over the next year?
Consider the following two mutually exclusive projects, you require a 11 percent return on your investment:...
Consider the following two mutually exclusive projects, you require a 11 percent return on your investment: Year Cash Flow (A) Cash Flow (B) 0           -17,000                 -17,000 1             8,000                     2,000 2             7,000                     5000 3              5,000.                   9,000 4              3,000                    9,500 Required: a) What is the IRR for each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? (1 mark) b) What is the NPV for each of these projects? (1...
You are considering an investment which has the following cash flows. If you require a 5        year...
You are considering an investment which has the following cash flows. If you require a 5        year payback, should you take the investment?             Year                   0               1               2                3                4               5                6             Cash flow    -$30,000    $10,000     $5,000       $5,000       $7,500    $10,000      $20,000 please show steps in excel
You are considering two independent projects. The required rate of return is 13.75 percent for Project...
You are considering two independent projects. The required rate of return is 13.75 percent for Project A and 14.25 percent for Project B. Project A has an initial cost of $51,400 and cash inflows of $21,400, $24,900, and $22,200 for Years 1 to 3, respectively. Project B has an initial cost of $38,300 and cash inflows of $23,000 a year for 2 years. Which project(s), if either, should you accept? Accept both A and B Reject both A and B...
MFI Inc. has a beta of 1.51. If the expected market return is 13.5 percent and...
MFI Inc. has a beta of 1.51. If the expected market return is 13.5 percent and the​ risk-free rate is 5.0 percent, what is the appropriate required return of MFI​ (using the​ CAPM)?
A firm is considering an investment in a risky project that offers a 10 percent rate...
A firm is considering an investment in a risky project that offers a 10 percent rate of return. Alternative investments with the same level of risk offer a 15% rate of return. If the company makes the investment, their value will: Options increase. increase, and then decrease. stay the same. It cannot be determined what will happen to the firm value. decrease.
1....Putters and Drivers, Inc. is considering making an investment in Project A, which will require an...
1....Putters and Drivers, Inc. is considering making an investment in Project A, which will require an initial cash outlay of $20,000. Project A is expected to generate cash inflows of $6,000 for year 1, $8,000 for year 2, $10,000 for year 3, and $7,000 for year 4. The firm's hurdle rate is 11%. What is the net present value for Project A? Select one: A. $3,301 B. $4,529 C. $3,821 D. None of the above 2.....Unlike the internal rate of...
A company is considering an investment in a new project which would require $39,000 worth of...
A company is considering an investment in a new project which would require $39,000 worth of capital expenditures and an increase of $45,000 in net working capital that will be recovered at the end of the project. Each year, starting at the end of the first year, the operating cash flows of the project will be $32,000 for 3 years. The project is so risky and so crazy its WACC is 16%. What is the net present value of the...
You are considering a project which has been assigned a discount rate of 9 percent. If...
You are considering a project which has been assigned a discount rate of 9 percent. If you start the project today, you will incur an initial cost of $4,000 and will receive cash inflows of $2,800 a year for 2 years. If you wait one year to start the project, the initial cost will rise to $4,220 and the cash flows will increase to $3,157 a year for 2 years. What is the value of the option to wait? (Do...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT