Question

In: Finance

You are considering a project which has been assigned a discount rate of 9 percent. If...

You are considering a project which has been assigned a discount rate of 9 percent. If you start the project today, you will incur an initial cost of $4,000 and will receive cash inflows of $2,800 a year for 2 years. If you wait one year to start the project, the initial cost will rise to $4,220 and the cash flows will increase to $3,157 a year for 2 years. What is the value of the option to wait? (Do not round intermediate calculations.)

$297.90

$2,556.92

$628.93

$408.00

$484.42

Solutions

Expert Solution

Please upvote if the ans is helpful. In case of doubt,do comment.Thanks.


Related Solutions

You are considering a project that has been assigned a discount rate of 12 percent. If...
You are considering a project that has been assigned a discount rate of 12 percent. If you start the project today, you will incur an initial cost of $280 and will receive cash inflows of $350 a year for 3 years. If you wait 1 year to start the project, the initial cost will rise to $420 and the cash flows will increase to $385 a year for 3 years. What is the value of the option to wait? O...
You are considering a project that has been assigned a discount rate of 8 percent. If...
You are considering a project that has been assigned a discount rate of 8 percent. If you start the project today (t=0), you will incur an initial cost of $980 and will receive cash inflows of $475 a year for three years. If you wait one year to start the project, the initial cost will rise to $1,000 (at t=1) and the cash flows will increase to $515 a year for three years (starting from year t=2). Should you wait...
Perini Corp is considering a project that has been assigned a discount rate of 14 percent....
Perini Corp is considering a project that has been assigned a discount rate of 14 percent. If the company starts the project today, it will incur an initial cost of $860,000 and will receive cash inflows of $287,000 a year for five years. If the company waits one year to start the project, the initial cost will rise to $988,000 and the cash flows will increase to $341,000 a year for five years. What is the value of the option...
PLEASE SHOW CALCULATOR INPUTS A project has been assigned a discount rate of 12 percent. If...
PLEASE SHOW CALCULATOR INPUTS A project has been assigned a discount rate of 12 percent. If the project starts immediately, it will have an initial cost of $480 and cash inflows of $350 a year for three years. If the start is delayed one year, the initial cost will rise to $520 and the cash flows will increase to $385 a year for three years. What is the value of the option to wait?
Lowell Flooring has assigned a discount rate of 15.2 percent to a new project that has...
Lowell Flooring has assigned a discount rate of 15.2 percent to a new project that has an initial cost of $285,400 and cash flows of $87,400, $98,300, and $131,700 for Years 1 to 3, respectively. What is the net present value of this project?
Calculate the project's MIRR, given a discount rate of 9 percent. The MIRR of the project with a discount rate of 9% is...
Emily's Soccer Mania is considering building a new plant. This project would require an initial cash outlay of $8.5 million and would generate annual cash inflows of $3.5 million per year for years one through four. In year five the project will require an investment outlay of $5.5 million. During years 6 through 10 the project will provide cash inflows of $5.5 million per year.Question:Calculate the project's MIRR, given a discount rate of 9 percent. The MIRR of the project...
Your firm is considering a project with a discount rate of 10%. If you start the...
Your firm is considering a project with a discount rate of 10%. If you start the project today, your firm will incur an initial cost of $480 and will receive cash inflows of $300 per year for 3 years with the first cashflow occurring one year from today. If you instead wait one year to start the project, the initial cost will rise to $520 and the cash flows will increase to $350 a year for the following 3 years...
An investment will pay you $20,000 in 7 years. The appropriate discount rate is 9 percent...
An investment will pay you $20,000 in 7 years. The appropriate discount rate is 9 percent compounded daily. What is the present value? Multiple Choice $10,652.66 $10,972.24 $11,185.30 $10,120.03 $10,940.68
JJ's is reviewing a project with a required discount rate of 15.2 percent and an initial...
JJ's is reviewing a project with a required discount rate of 15.2 percent and an initial cost of $309,000. The cash inflows are $47,000, $198,000, and $226,000 for Years 2 to 4, respectively. Should the project be accepted based on discounted payback if the required payback period is 2.5 years?
You are a project manager who has been assigned to a new project that would require  “Porting...
You are a project manager who has been assigned to a new project that would require  “Porting of the existing backend server code-base that currently runs on the OS platform ABC to another OS platform XYZ so that the backend sever code-base would run on XYZ OS platform as well the OS platform ABC, when finished”.  Both of the OS platforms are used heavily by the company and are well understood by the technical staff. The functionalities would remain the same and...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT