Question

In: Accounting

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows:

January 1, 2018 - $ 1,360,000

March 1, 2018 - 810,000

June 30, 2018 - 160,000

October 1, 2018 - 670,000

January 31, 2019 - 585,000

April 30, 2019 - 900,000

August 31, 2019 - 1,530,000

On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest rate. The loan was outstanding all of 2018 and 2019. The company’s other interest-bearing debt included two long-term notes of $4,700,000 and $6,700,000 with interest rates of 7% and 9%, respectively. Both notes were outstanding during all of 2018 and 2019. Interest is paid annually on all debt. The company’s fiscal year-end is December 31.

Required:

1. Calculate the amount of interest that Mason should capitalize in 2018 and 2019 using the weighted-average method.

2. What is the total cost of the building?

3. Calculate the amount of interest expense that will appear in the 2018 and 2019 income statements.

Solutions

Expert Solution

Solution:

Average interest rate = (4.7 x 7% + 6.7x 9%) / (4.7+ 6.7)

= 93.2 % / 11.4

= 8.17%

Average expenditure during 2018

Jan 1 $1,360,000 x 12/12 = $1,360,000

Mar 1 $810,000 x 10/12 = $675,000

June 30 $160,000 x 6/12 = $80,000

Oct 1 $670,000 x 3/12 = $167,500

  Total    = $2,282,500

Average expenditure during 2019

$3,000,000 x 12/12 = $3,000,000

Jan 31 $585,000 x 11/12 = $536,250

Apr 30 $900,000 x 8/12 = $600,000

Aug 31 $1,530,000 x 4/12 = $510,000

Total = $4,646,250

(1) capitalize in 2018

weighted-average expenditure Interest rate Interest capitalized
$2.282,500 10% $228,250

capitalize in 2019

weighted-average expenditur interest rate interest
$3,000,000 10% $300,000
$646,250 8.17% $52,799
$352,799

(2) total cost of the building = total expenditure + interest capitalized

= $6,015,000 + $228,250+ $352,799

= $6,596,049

(3) Total interest = $3,000,000 x 10% + $4,700,000 x 7% + $6,700,000 x 9%

= $300,000 + $329,000 + $603,000

= $1,232,000

2018 2019
Total interest $1,232,000 $1,232,000
Less: Interest Capitalized $228,250 $352,799
interest expense that will appear in income statements $1,003,750 $879,201

Related Solutions

On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 660,000 June 30, 2018 520,000 October 1, 2018 620,000 January 31, 2019 360,000 April 30, 2019 675,000 August 31, 2019 1,080,000 On January 1, 2018, the company obtained a $3 million construction loan with a 11% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,940,000 March 1, 2018 1,680,000 June 30, 2018 1,880,000 October 1, 2018 1,680,000 January 31, 2019 432,000 April 30, 2019 765,000 August 31, 2019 1,062,000 On January 1, 2018, the company obtained a $4,800,000 construction loan with a 14% interest rate....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT