Question

In: Accounting

2. On January 1, 2018, Kendall Inc. began construction of an automated cattle feeder system. The...

2. On January 1, 2018, Kendall Inc. began construction of an automated cattle feeder system. The system was finished and ready for use on September 30, 2019. Expenditures on the project were as follows:

January 1, 2018

$

200,000

July 1, 2018

$

300,000

December 1, 2018

$

600,000

March 31, 2019

$

300,000

September 30, 2019

$

200,000

Kendall borrowed $600,000 on a construction loan at 8% interest on January 1, 2018. This loan was outstanding throughout the construction period. The company had $2,000,000 in 5% bonds payable outstanding in 2018 and 2019. Kendall used the specific interest method.

Interest capitalized for 2018 was:

a. 48,000

b. 40,000

c. 32,000

d. 30,000

3. Pam & Co. exchanged land and $9,000 cash for equipment. The book value and the fair value of the land were $90,000 and $106,000, respectively.

Assuming that the exchange has commercial substance, Lowell would record equipment and a gain/(loss) of:

a. Equipment: 90,000

Gain/loss: (25,000)

b. Equipment: 99,000

Gain/loss: (16,000)

c. Equipment: 106,000

gain/loss: 25,000

d. Equipment: 115,000

gain/loss: 16,000

Solutions

Expert Solution

2)
Date Amount Capitalization period Weighted Average Accumulated Expenditures
January 1, 2018 $ 200,000 12 /12 $ 200,000
July 1, 2018 $ 300,000 6 /12 $ 150,000
December 1, 2018 $ 600,000 1 /12 $ 50,000
Total $ 1,100,000 $ 400,000
Interest capitalized in 2018
   = Weighted Avg. Exp. X Interest Rate
$ 400,000 x 8% = $ 32,000 Option ( C ) is Correct
3)
Accounts titles and Explanation Debit ( In $ ) Credit ( In $ )
Equipment    - Bal. Fig.
( $ 106,000 + $ 9,000)
$ 115,000
        Gain $ 16,000
        Cash $ 9,000
         Land $ 90,000
Option (d) is Correct
Gain
   = Fair Value (-) Book value
   = $ 106,000 (-) $ 90,000
    = $ 16,000 (Gain)

Related Solutions

On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated...
On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 604000 September 1, 2020 1809600 December 31, 2020 1809600 March 31, 2021 1809600 September 30, 2021 1196000 Crane Company borrowed $3240000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
On January 1, 2018, Star Inc. began construction of a new warehouse for its own use....
On January 1, 2018, Star Inc. began construction of a new warehouse for its own use. The warehouse was completed in 2019. Expenditures on the project in 2018 were as follows:             January 1, 2018           $310,000             March 31, 2018           $600,000             September 1, 2018      $720,000 Star borrowed $600,000 on a construction loan at 6% interest rate on January 1, 2018. The loan was outstanding throughout the construction period. During 2018, the company had $300,000 in 4% bonds and $700,000 in 8% notes outstanding. Star’s capitalized...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 2,020,000 March 1, 2018 1,740,000 June 30, 2018 1,940,000 October 1, 2018 1,740,000 January 31, 2019 441,000 April 30, 2019 774,000 August 31, 2019 1,071,000 On January 1, 2018, the company obtained a $4,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,710,000 March 1, 2018 1,320,000 June 30, 2018 1,520,000 October 1, 2018 1,320,000 January 31, 2019 378,000 April 30, 2019 711,000 August 31, 2019 1,008,000 On January 1, 2018, the company obtained a $4,200,000 construction loan with a 16% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,180,000 March 1, 2018 660,000 June 30, 2018 860,000 October 1, 2018 660,000 January 31, 2019 279,000 April 30, 2019 612,000 August 31, 2019 909,000 On January 1, 2018, the company obtained a $3,100,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,050,000 March 1, 2018 870,000 June 30, 2018 390,000 October 1, 2018 690,000 January 31, 2019 675,000 April 30, 2019 990,000 August 31, 2019 1,710,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,200,000 March 1, 2018 900,000 June 30, 2018 1,100,000 October 1, 2018 900,000 January 31, 2019 315,000 April 30, 2019 648,000 August 31, 2019 945,000 On January 1, 2018, the company obtained a $3,500,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,420,000 March 1, 2018 1,140,000 June 30, 2018 1,340,000 October 1, 2018 1,140,000 January 31, 2019 351,000 April 30, 2019 684,000 August 31, 2019 981,000 On January 1, 2018, the company obtained a $3,900,000 construction loan with a 12% interest rate....
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,070,000 March 1, 2018 840,000 June 30, 2018 380,000 October 1, 2018 710,000 January 31, 2019 1,170,000 April 30, 2019 1,485,000 August 31, 2019 2,700,000 On January 1, 2018, the company obtained a $3 million construction loan with a 14% interest...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used...
On January 1, 2018, the Mason Manufacturing Company began construction of a building to be used as its office headquarters. The building was completed on September 30, 2019. Expenditures on the project were as follows: January 1, 2018 $ 1,300,000 March 1, 2018 720,000 June 30, 2018 340,000 October 1, 2018 640,000 January 31, 2019 450,000 April 30, 2019 765,000 August 31, 2019 1,260,000 On January 1, 2018, the company obtained a $3 million construction loan with a 10% interest...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT