Question

In: Operations Management

1) Clancy's Motors has the following demand to meet for custom manufactured fuel injector parts. The...

1) Clancy's Motors has the following demand to meet for custom manufactured fuel injector parts. The holding cost for that item is $2 per month and each setup costs $80. Lead time is 0 months. Calculate the planned order releases using: (a) the EOQ technique, and (b) the POQ technique. And What are the costs of each plan, including the holding cost of any inventory left over after month 7? What technique performance is better.

Month

1

2

3

4

5

6

7

Requirement

400

150

200

150

100

150

250

Answer (Show all mathematical work):

(a) The monthly holding cost = $2/month

Average monthly demand = ??? units

The EOQ = ??? units

Total inventory held = ??? units

Setup costs = $???

Holding cost = $????

Total cost = $????

(b) POQ Interval = ?.??, round to # month.

Total inventory held = ? units

Setup costs = $???

Holding cost = $?

Total cost = $???

Solutions

Expert Solution

(a)

As given, holding cost for that item is $2 per month and each setup costs $80.

Average monthly demand = (Total demand)/ (number of months) = (400+150+200+150+100+150+250)/ (7) = 1400/ 7= 200

Total project annual demand is 200*12=2400.

EOQ = square root (2*D*S/H)

where D is annual demand, S is ordering cost, H is holding cost per year

EOQ = square root (2*2400*80/ (2*12)) = 126.49 ~127 (rounded)

Planned order release plan

Month

1

2

3

4

5

6

7

Requirement

400

150

200

150

100

150

250

Planned order receipt 508 127 127 254 254 254
Planned order release 508 127 127 254 254 254
Balance inventory available 508-400=108 127+108-150=85 127+85-200=12 254+12-150=116 116-100=16 254+16-150=120 254+120-250=124

Total inventory held = 124 units (at the end of Month 7)

Total Setup cost = (Number of planned order releases)*Setup cost = (12)*80 = $960 (rounded)

Total Holding cost = (Total inventory carried forward from one month to another)*(holding cost per month) = (108+85+12+116+16+120+124)*$2 = $1162

Total cost = Total Setup cost + Total Holding cost = $960 + $1162 = $2122

(b)

POQ uses EOQ to calculate fixed number of period requirements to include in each order

EOQ= 127

Average monthly demand = 200

POQ = EOQ/ Average monthly demand= 127/ 200 = 0.635 ~ 1 month

POQ Interval = 1 month

Month

1

2

3

4

5

6

7

Requirement

400

150

200

150

100

150

250

Planned order receipt 400 150 200 150 100 150 250
Planned order release 400 150 200 150 100 150 250
Balance inventory available 0 0 0 0 0 0 0

Total inventory held = 0 units

Setup costs = (number of setup)* cost per setup = (7)*$80 =$560

Holding cost = $0

Total cost = $560

Hence, POQ is a better cost effective option for order release plan


Please give thumbs up/ likes if you consider my answer useful. Thank you!


Related Solutions

ICON Motors has the following demand to meet for custom manufactured parts. The holding cost for...
ICON Motors has the following demand to meet for custom manufactured parts. The holding cost for that item is $1 per week and each setup costs $500. Lead time is 2 weeks. Calculate the planned order releases using: the POQ techniques. POQ technique POQ Interval = Answer Month 1 2 3 4 5 6 7 8 Gross requirements 0 200 250 0 300 100 200 Projected on hand 300 Answer Answer Answer Answer Answer Answer Answer Net Requirement Answer Answer...
The following table contains the measurements of the key length dimension from a fuel injector. These...
The following table contains the measurements of the key length dimension from a fuel injector. These samples were taken at one-hour intervals. Construct a three-sigma X ̅-chart and R-chart for the length of the fuel injector. What can you say about this process? Sample Number Observations 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 1 0.57 0.70 0.61 0.67 0.20 0.51 0.95 0.23 0.24 0.59 0.70 0.04 0.05...
The following table contains the measurements of the key length dimension from a fuel injector. These...
The following table contains the measurements of the key length dimension from a fuel injector. These samples of size five were taken at one-hour intervals. Use three-sigma control limits. Use Exhibit 10.13. OBSERVATIONS SAMPLE NUMBER 1 2 3 4 5 1 0.488 0.485 0.482 0.508 0.485 2 0.501 0.504 0.518 0.491 0.526 3 0.498 0.481 0.513 0.483 0.515 4 0.497 0.504 0.482 0.485 0.486 5 0.474 0.498 0.524 0.460 0.486 6 0.475 0.485 0.505 0.482 0.497 7 0.497 0.512 0.485...
The following table contains the measurements of the key length dimension from a fuel injector. These...
The following table contains the measurements of the key length dimension from a fuel injector. These samples of size five were taken at one-hour intervals. Use three-sigma control limits. Use Exhibit 10.13. OBSERVATIONS SAMPLE NUMBER 1 2 3 4 5 1 0.465 0.494 0.493 0.511 0.472 2 0.471 0.501 0.505 0.484 0.515 3 0.472 0.493 0.516 0.493 0.528 4 0.475 0.501 0.495 0.494 0.492 5 0.481 0.498 0.523 0.457 0.485 6 0.472 0.496 0.502 0.495 0.505 7 0.494 0.502 0.494...
The following table contains the measurements of the key length dimension from a fuel injector. These...
The following table contains the measurements of the key length dimension from a fuel injector. These samples of size five were taken at one-hour intervals. Use three-sigma control limits. Use Exhibit 10.13. OBSERVATIONS SAMPLE NUMBER 1 2 3 4 5 1 0.486 0.499 0.493 0.511 0.481 2 0.499 0.506 0.516 0.494 0.529 3 0.496 0.500 0.515 0.488 0.521 4 0.495 0.506 0.483 0.487 0.489 5 0.472 0.502 0.526 0.469 0.481 6 0.473 0.495 0.507 0.493 0.506 7 0.495 0.512 0.490...
A production manager needs to develop a production schedule to meet the following demand: Period 1...
A production manager needs to develop a production schedule to meet the following demand: Period 1 2 3 4 5 6 Demand 600 600 800 1000 1200 600 Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time: $5 per unit. (c) subcontract: $7 per unit. (d) Inventory carrying cost = $2 per unit per period (e) Back-order costs = $5 per unit per period. Suppose some workers have retired, and the regular production rate can be...
Gibson Corporation makes custom-order furniture to meet the needs of persons with disabilities. On January 1,...
Gibson Corporation makes custom-order furniture to meet the needs of persons with disabilities. On January 1, 2018, the company had the following account balances: $88,000 for both cash and common stock. In 2018, Gibson worked on three jobs. The relevant direct operating costs follow: Direct Labor Direct Materials Job 1 $ 4,300 $ 5,300 Job 2 2,100 2,200 Job 3 8,400 3,700 Total $ 14,800 $ 11,200 Gibson’s predetermined manufacturing overhead rate was $.40 per direct labor dollar. Actual manufacturing...
4/ A quality control inspector has determined that 0.25% of all parts manufactured by a particular...
4/ A quality control inspector has determined that 0.25% of all parts manufactured by a particular machine are defective. If 50 parts are randomly selected, find the probability that there will be at most one defective part. 5/ A fair die is rolled 10 times. Compute the probability that a “one” appears exactly once. 6/ If two dice are tossed six times, find the probability of obtaining a sum of 7 two or three times. 7/ A machine produces parts...
Custom Auto Parts started this year with the following balances:       Cash: $60,000       Merchandise Inventory:...
Custom Auto Parts started this year with the following balances:       Cash: $60,000       Merchandise Inventory: $8,000       Land: $12,000       Accounts Payable: $0       Common Stock: $50,000       Retained Earnings: $30,000 During the year they had the following transactions: Purchase $60,000 of merchandise inventory on account, terms 2/10,n/30. The goods delivered in Event 1 were delivered FOB shipping point. Freight costs of $1,500 were paid in cash by the responsible party Returned $3,000 of goods purchased in Event 1...
1. When identical parts are being manufactured. They vary from one another. If the variation is...
1. When identical parts are being manufactured. They vary from one another. If the variation is normally distributed if: a) is natural and is to be expected b) indicates the parts do not meet quality standards c) indicates an unstable process is developing 2. Probability tells us: a) how often something actually occurs b) how often something is expected to occur c) the number of random samples it takes for an event to occur 3. Unnatural variation is normally the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT