In: Operations Management
ICON Motors has the following demand to meet for custom manufactured parts.
The holding cost for that item is $1 per week and each setup costs $500.
Lead time is 2 weeks.
Calculate the planned order releases using: the POQ techniques.
POQ technique
POQ Interval = |
Answer |
Month |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
|
Gross requirements |
0 |
200 |
250 |
0 |
300 |
100 |
200 |
||
Projected on hand |
300 |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
|
Net Requirement |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
||
Planned Receipt |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
||
Planned Order |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
Answer |
Set Up cost |
Answer |
Holding Cost |
Answer |
Total |
Answer |
Please answer all parts of the question.
Average weekly demand (after subtracting initial inventory), D = (0+200+250+0+300+100+200-300)/7
= 107
(in the table, time unit is month, lead time and holding cost is in weeks. So, assuming time unit is weeks for all purposes)
Setup cost, S = $ 500
Holding cost, H = $ 1 per unit per week
EOQ = sqrt(2DS/H)
= sqrt(2*107*500/1)
= 327
POQ interval = Q/D
= 327/107
= 3 weeks (rounded-off)
Using POQ policy, order is released at an interval of 3 weeks and order quantity is equal to the net requirement of 3 weeks
Resulting MRP is following:
Set up cost = Number of planned order * S = 2*500 = $ 1,000
Holding cost = SUM of projected on hand * H = (300+100+300+300+0+200+0)*1 = $ 1,200
Total cost = 1000+1200 = $ 2,200