In: Finance
Consider a project to supply Detroit with 40,000 tons of machine screws annually for automobile production. You will need an initial $5,400,000 investment in threading equipment to get the project started; the project will last for 5 years. The accounting department estimates that annual fixed costs will be $850,000 and that variable costs should be $440 per ton; accounting will depreciate the initial fixed asset investment straight-line to zero over the 5-year project life. It also estimates a salvage value of $380,000 after dismantling costs. The marketing department estimates that the automakers will let the contract at a selling price of $560 per ton. The engineering department estimates you will need an initial net working capital investment of $540,000. You require a return of 12 percent and face a marginal tax rate of 23 percent on this project.
a-1
What is the estimated OCF for this project? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)
a-2
What is the estimated NPV for this project? (Do not round intermediate calculations and enter your answer in dollars, not millions of dollars, rounded to 2 decimal places, e.g., 1,234,567.89.)
b.
Suppose you believe that the accounting department’s initial cost and salvage value projections are accurate only to within ±15 percent; the marketing department’s price estimate is accurate only to within ±10 percent; and the engineering department’s net working capital estimate is accurate only to within ±5 percent. What is the worst-case NPV for this project? The best-case NPV?
Answer a-1:
Contribution per ton = sales price - variable cost = $560 - $440 = $120
Operating cash flow = (Contribution per ton * Tons sold - Fixed cost) * (1 - Tax rate) + Depreciation tax shield
= (120 * 40000 -850000) * (1 - 23%) + (5400000 / 5) * 23%
= $3,289,900
Operating cash flow = $3,289,900
Answer a-2:
NPV = $6,391,792.83
Working:
The above excel with 'show formula' is follows:
Answer b:
Worst case NPV = ($537,994.04)
Worst case NPV will be when:
Initial cost increases by 15% to $6210000
Salvage value decreases by 15% to $323,000
Price decreases by 10% to $504
Working capital increases by 5% to $567,000
Working:
Best case NPV = $13,321,580.70
Best case NPV will be when:
Initial cost decreases by 15% to $4,590,000
Salvage value increases by 15% to $437,000
Price increases by 10% to $616
Working capital decreases by 5% to $513,000
Working: