In: Computer Science
Determine a suitable process model for the following projects. Also, you are required to provide a short justification along with the necessary assumptions
d) An enterprise software system where the stakeholders do not
well understand requirements. Thus, requirements are expected to be
extremely changeable due to external changes, changing
expectations, changes in the budget and the rapid change in
technology.
e) Children learning mobile application. The stakeholders are
concerned about the user interface more than the functionality of
the application.
d) An enterprise software system where the stakeholders
do not well understand requirements. Thus, requirements are
expected to be extremely changeable due to external changes,
changing expectations, changes in the budget and the rapid change
in technology. (1 Marks)
Ans: Iterative model is the best fit model for the given scenario
where stakeholders do not well understand requirements. It is
complex in nature and it has the tendency to broadening the set of
features until the target system is complete. It has the ability to
manage extreme changes in the budget and in technology aspects.
e) Children learning mobile application. The stakeholders are concerned about the user interface more than the functionality of the application.
Ans: Agile model is best fit for such scenarios if the developers are more concerned about the user interface of mobile applications. This model is based on the values and principles expressed in the Agile Manifesto that is a way of thinking that enables teams and businesses to innovate, quickly response to the given requirements and demands by clients/ users and by mitigating risk.
If you like my answer, kindly upvote. And if you have any doubts, feel free to ask