In: Operations Management
Plan
E:
Keep the current workforce, which is producing
1 comma 6001,600
units per month, and subcontract to meet the rest of the demand. Subcontract cost is
$7575
per unit. Subcontracting capacity is limited to
500500
units per month. The warehouse and overtime constraints from Plan D do not apply to this plan.
Plan E |
|||||||
Month |
Demand |
Production (Units) |
Subcontract (Units) |
Ending Inventory |
|||
0 |
December |
200200 |
|||||
1 |
January |
1 comma 4501,450 |
1 comma 6001,600 |
nothing |
nothing |
||
2 |
February |
1 comma 6001,600 |
1 comma 6001,600 |
nothing |
nothing |
||
3 |
March |
1 comma 7001,700 |
1 comma 6001,600 |
nothing |
nothing |
||
4 |
April |
1 comma 7001,700 |
1 comma 6001,600 |
nothing |
nothing |
||
5 |
May |
2 comma 1002,100 |
1 comma 6001,600 |
nothing |
nothing |
||
6 |
June |
2 comma 1002,100 |
1 comma 6001,600 |
nothing |
nothing |
||
7 |
July |
1 comma 9001,900 |
1 comma 6001,600 |
nothing |
nothing |
||
8 |
August |
1 comma 3001,300 |
1 comma 6001,600 |
nothing |
nothing |
The total subcontracting cost= $nothing (Enter your response as a whole number)
The total inventory holding cost for January through August = $nothing
The total cost excluding normal time labour costs, Plan E= $nothing
Below is the screenshot of the formula applied -
Below is the screenshot of the result -
Subcontract Cost = 86250
Holding cost = 28000
Total Cost = 114250