Question

In: Finance

The cash flows for three independent projects are found below. Year 0 (Initial investment) Project A...

The cash flows for three independent projects are found below.

Year 0 (Initial investment) Project A $(45,000) Project B $(120,000) Project C $(460,000)

Year 1 $12,000    $ 30,000 $ 220,000

Year 2 $14,000 $ 30,000 $ 220,000

Year 3 $ 19,000 $ 30,000 $   220,000

Year 4 $ 27,000 $ 30,000 -

Year 5   

a. Calculate the IRR for each of the projects. b. If the discount rate for all the three projects is 16 percent, which projects or projects would you want to undertake? c. What is the net present value of each projects where the appropriate discount rate is 16 percent? a. The IRR of project A is.

Solutions

Expert Solution

IRR is the internal rate of return such that the Net Present Value of a set of cashflows from an investment/project will equal to its initial investment.

initial investment = CF1/(1+r) +CF2/(1+r)2 + CF3/(1+r)3 +CF4/(1+r)4 +.....+ CFn/(1+r)n

In the example, we will calculate IRR using Excel IRR method which takes in the set of cash flows and NPV by discounting each cash flow by 16%. This is copied in the table below:

r 0.16
Year Project A Project B Project C PV (Project A) PV (Project B) PV (Project C)
0 ($45,000) ($120,000) ($460,000) ($45,000.00) ($120,000.00) ($460,000.00)
1 $12,000 $30,000 $220,000 $10,344.83 $25,862.07 $189,655.17
2 $14,000 $30,000 $220,000 $10,404.28 $22,294.89 $163,495.84
3 $19,000 $30,000 $220,000 $12,172.50 $19,219.73 $140,944.69
4 $27,000 $30,000 $14,911.86 $16,568.73 $0.00
5
IRR 18.707% 0.000% 20.475% NPV $2,833.46 ($36,054.58) $34,095.70


Copying the formula sheet below:

r 0.16
Year Project A Project B Project C PV (Project A) PV (Project B) PV (Project C)
0 -45000 -120000 -460000 =B4/(1+$B$1)^$A4 =C4/(1+$B$1)^$A4 =D4/(1+$B$1)^$A4
1 12000 30000 220000 =B5/(1+$B$1)^$A5 =C5/(1+$B$1)^$A5 =D5/(1+$B$1)^$A5
2 14000 30000 220000 =B6/(1+$B$1)^$A6 =C6/(1+$B$1)^$A6 =D6/(1+$B$1)^$A6
3 19000 30000 220000 =B7/(1+$B$1)^$A7 =C7/(1+$B$1)^$A7 =D7/(1+$B$1)^$A7
4 27000 30000 =B8/(1+$B$1)^$A8 =C8/(1+$B$1)^$A8 =D8/(1+$B$1)^$A8
5
IRR =IRR(B4:B8) =IRR(C4:C8) =IRR(D4:D8) NPV =SUM(F4:F8) =SUM(G4:G8) =SUM(H4:H8)

Sub part a:

IRR for project A = 18.707%

IRR for project B = 0

IRR for project C = 20.475%

Sub part b:

If discount rate is 16 %, then the NPV of project C ($34,095.70) is the highest

Sub part b:

If discount rate is 16 %, then the NPV of project C ($34,095.70) is the highest

NPV for project A = $2,833.46

NPV for project B = - $36,054.58

NPV for project C = $34,095.70


Related Solutions

The cash flows for three independent projects are found​ below:   Year 0 ​ (Initial investment) ​$(70,000​)...
The cash flows for three independent projects are found​ below:   Year 0 ​ (Initial investment) ​$(70,000​) ​$(110,000​) ​$(420,000​) Year 1 ​$11,000 ​$28,000 ​$220,000 Year 2 17,000 28,000 220,000 Year 3 21,000 28,000 220,000 Year 4 26,000 28,000 — Year 5 33,000 28,000 — . a. Calculate the IRR for each of the projects. b. If the discount rate for all three projects is 13 percent​, which project or projects would you want to​ undertake? c. What is the net present...
Projects A B Cost (initial investment) 40000 250000 Year Cash flows of A Cash flows of...
Projects A B Cost (initial investment) 40000 250000 Year Cash flows of A Cash flows of B 1 10000 40000 2 10000 120000 3 10000 200000 4 10000 200000 5 10000 200000 6 10000 200000 What are the Payback Periods of Projects A, and B? Assume all cash flows are evenly spread throughout the year and already discounted. If the cut-off period ( الفتره المقبوله) is three years, which projects do you accept?
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 380 ?$ 380 1 210 280 2 210 280 3 210 280 4 210 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 280 ?$ 280 1 160 180 2 160 180 3 160 180 4 160 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project A Profitability Index Project B
The following are the cash flows of two projects: Year Project A Project B 0 −$...
The following are the cash flows of two projects: Year Project A Project B 0 −$ 290 −$ 290 1 170 190 2 170 190 3 170 190 4 170 If the opportunity cost of capital is 11%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330) $ (330) 1 160 230 2 160 230 3 160 230 4 160 If the opportunity cost of capital is 12%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.) Project Profitability Index: A B
The following are the cash flows of two projects: Year Project A Project B 0 ?$...
The following are the cash flows of two projects: Year Project A Project B 0 ?$ 220 ?$ 220 1 100 120 2 100 120 3 100 120 4 100 If the opportunity cost of capital is 10%, what is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 4 decimal places.)
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (260 ) $ (260 ) 1 140 160 2 140 160 3 140 160 4 140 a. Calculate the NPV for both projects if the opportunity cost of capital is 16%. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Project A Project B b. Suppose that you can choose only one of these projects. Which would you choose? Project A...
The following are the cash flows of two projects: Year Project A Project B 0 $...
The following are the cash flows of two projects: Year Project A Project B 0 $ (330 ) $ (330 ) 1 160 230 2 160 230 3 160 230 4 160 a. If the opportunity cost of capital is 12%, calculate the NPV for both projects. (Do not round intermediate calculations. Round your answers to 2 decimal places.) b. Which of these projects is worth pursuing? ****NOTE**** You are finding the NPV, NOT the Profitability index!
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year...
The cash flows for the two projects are as follows? ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A - $ 100 $26 $28 $42 $52 B -$ 100    $52 $42 $28    $18 a. What is the IRR of each? project? b. What is the NPV of each project at your cost of? capital? c. At what cost of capital are you indifferent between the two? projects? d. What should you? do?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT