In: Operations Management
Question 5 (1 point)
Process control is about using the data generated by the execution of a business process in order to extract insights about the actual performance of the process and conforming appropriately.
True | |
False |
Question 8 (1 point)
Within conformance control flow, the ordering constraint indicates two or more tasks can't co-occur in the same case.
True | |
False |
Question 9 (1 point)
Which of the following types of information are primary in providing business insights from BPMS data?
A. Operational information |
|
B. Structured information |
|
C. Historic information |
|
D. A and B |
|
E. A and C |
Question 11 (1 point)
Which advantage category applies to the following incentive to introduce BPMS in the organization?:
The clients of a company complain that they can only get very shallow updates on the progress of the orders they make. The IT manager of that organization looks into the use of a BPMS to capture and provide status information on all these orders.
Transparency |
|
Enforcement |
|
Flexibility |
|
Quality |
Answer-5): False.
Within conformance control flow, the ordering constraint indicates two or more tasks can't co-occur in the same case
Answer-8): True.
As explained by Marlon Dumas, Marcello La Rosa, Jan Mendling in their book "Fundamentals of Business Process Management", an ordering constraint states that two tasks should occur in a given order and cannot co-occur at same time in order to reduce wasteful efforts.
Answer-9) Option E
Explanation: From a Business process management system, the information required for providing business insights are Operational and Historical Information.
Answer-11): Option A
Explanation: When the problem lies in the updating of knowledge pertaining to the progress of the project, it is the advantage category of Transparency. Using the BPMS, the transparency of the project can be increased with regular updates. This will infuse efficiency in the system.
If it's helpfull, a thumbs up, pls