Question

In: Finance

You are considering three independent projects: A, B, and C. Given the following free cash flow...

  1. You are considering three independent projects: A, B, and C. Given the following free cash flow information, calculate the payback period for each. Required rate of return is 9%. (1 Mark)

If you require a 3-year payback before an investment can be accepted, which project(s) would be accepted? (0.5 Mark)

Year

Project A

Project B

Project C

0

(1,000)

(9,000)

(4,000)

1

300

4,000

1,100

2

400

2,000

1,800

3

250

2,000

2,200

4

125

3,000

2,800

5

125

5,000

3,200

Solutions

Expert Solution

Payback Period = ( Last Year with a Negative Cash Flow ) + [( Absolute Value of negative Cash Flow in that year)/ Total Cash Flow in the following year)]

Project A :

Payback Period = 2 + ( 300 / 250)

= 3.20 Years

Hence the correct answer is 3.20 Years

Note:

Year Investment Cash Inflow Net Cash Flow
0 -1,000 -    -1,000 (Investment + Cash Inflow)
1 -    300 -700 (Net Cash Flow + Cash Inflow)
2 -    400 -300 (Net Cash Flow + Cash Inflow)
3 -    250 -50 (Net Cash Flow + Cash Inflow)
4 -    125 75 (Net Cash Flow + Cash Inflow)
5 -    125 200 (Net Cash Flow + Cash Inflow)

Project B :

Payback Period = 3 + ( 1000 / 3000)

= 3.33 Years

Hence the correct answer is 3.33 Years

Note:

Year Investment Cash Inflow Net Cash Flow
0 -9,000 -    -9,000 (Investment + Cash Inflow)
1 -    4,000 -5,000 (Net Cash Flow + Cash Inflow)
2 -    2,000 -3,000 (Net Cash Flow + Cash Inflow)
3 -    2,000 -1,000 (Net Cash Flow + Cash Inflow)
4 -    3,000 2,000 (Net Cash Flow + Cash Inflow)
5 -    5,000 7,000 (Net Cash Flow + Cash Inflow)

Project C :

Payback Period = 2 + (1100 / 2200)

= 2.5 Years

Hence the correct answer is 2.50 Years

Note:

Year Investment Cash Inflow Net Cash Flow
0 -4,000 -    -4,000 (Investment + Cash Inflow)
1 -    1,100 -2,900 (Net Cash Flow + Cash Inflow)
2 -    1,800 -1,100 (Net Cash Flow + Cash Inflow)
3 -    2,200 1,100 (Net Cash Flow + Cash Inflow)
4 -    2,800 3,900 (Net Cash Flow + Cash Inflow)
5 -    3,200 7,100 (Net Cash Flow + Cash Inflow)

-------------------

If the required payback is 3-year payback before an investment can be accepted, project C would be accepted

Hence the correct answer is project C


Related Solutions

Your company is considering three independent projects. Given the following cash flow information, calculate the payback...
Your company is considering three independent projects. Given the following cash flow information, calculate the payback period for each. If your company requires a three-year payback before an investment can be accepted, which project(s) would be accepted? Project D Project E Project F Cost 205,000.00 179,000.00 110,000.00 Inflow year 1 53,000.00 51,000.00 25,000.00 Inflow year 2 50,000.00 87,000.00 55,000.00 Inflow year 3 48,000.00 41,000.00 21,000.00 Inflow year 4 30,000.00 52,000.00 9,000.00 Inflow year 5 24,000.00 40,000.00 35,000.00 Payback Period EXACT...
​(Payback period calculations​) You are considering three independent​ projects: project​ A, project​ B, and project C....
​(Payback period calculations​) You are considering three independent​ projects: project​ A, project​ B, and project C. Given the free cash flow information in the popup​ window, calculate the payback period for each. If you require a​ 3-year payback before an investment can be​ accepted, which​ project(s) would be​ accepted? Initial Outlay   -900   -10,000   -6,500 Inflow year 1   700   6,000   2,000 Inflow year 2   400   4,000   2,000 Inflow year 3   200   4,000   4,000 Inflow year 4   100   4,000   4,000 Inflow year...
​(Payback period calculations​) You are considering three independent​ projects: project​ A, project​ B, and project C....
​(Payback period calculations​) You are considering three independent​ projects: project​ A, project​ B, and project C. Given the cash flow information in the popup​ window,calculate the payback period for each. If you require a​ 3-year payback before an investment can be​ accepted, which​ project(s) would be​ accepted? Initial Outlay   -950   -9000   -6500 Inflow year 1   700   4000   2000 Inflow year 2   200   3000   2000 Inflow year 3   100   3000   3000 Inflow year 4   300   3000   3000 Inflow year 5   500  ...
You are considering the following three projects. A & B are mutually exclusive while C is...
You are considering the following three projects. A & B are mutually exclusive while C is independent. Question: On one graph, plot the NPV profile for Both projects, A&B. please show how on excel Following are their expected cash flows year project A Project B Project C 0 -60,000.00 -40,000.00 -20,000.00 1 0 40,000.00 35,000.00 2                    82,000.00                    40,000.00                     30,000.00 3                    60,000.00                    20,000.00                        2,000.00 4 20,000.00 10,000.00 -40,000.00
Question 5 Given the following cash flows, for the two independent projects A and B, calculate...
Question 5 Given the following cash flows, for the two independent projects A and B, calculate Payback Period                                                                Accounting rate of return                                                Net Present Value                                                          Profitability index                                                           And recommend acceptance or rejection of projects considering individual techniques of capital budgeting. A rate of 10 % has been selected for the NPV analysis. Project A Project B Initial outlay $50,000 $100,000 Cash inflows Year 1 $10,000 $ 25,000 Year 2 15,000 25,000 Year 3 20,000 25,000 Year 4...
Intro WH Smith Company is evaluating three projects: A, B, C, with cash flows as given...
Intro WH Smith Company is evaluating three projects: A, B, C, with cash flows as given in the table. Each project requires an initial investment of $96,000 and has a required return of 6%. Year A B C 1 50,000 0 20,000 2 40,000 50,000 40,000 3 20,000 50,000 40,000 4 10,000 40,000 40,000    Attempt 3/10 for 8 pts. Part 1 What is the payback period for project A (in years)? Submit    Attempt 1/10 for 10 pts. Part 2 What...
Given the following information: Year 1 free cash flow: 40 million Year 2 free cash flow...
Given the following information: Year 1 free cash flow: 40 million Year 2 free cash flow 90 million Year 3 free cash flow 100 million After year 3, expected FCF growth is expected to be 4% The cost of capital is 9% Short term investments is 50 million Debt is currently 25 million Preferred shock is 5 million There are 20 million outstanding stock shares. 1. Calculate the intrinsic stock price . If the current stock price was $100.00, would...
Given the following information: Year 1 Free cash flow: 40 million Year 2 Free cash flow...
Given the following information: Year 1 Free cash flow: 40 million Year 2 Free cash flow 90 m Year 3 Free cash flow 100 m After year 3, expected FCF growth is expected to be 4% The cost of capital is 9% Short term investments = 50 million Debt is currently 25 million Preferred stock = 5 million There are 20 million outstanding stock shares. 1. Calculate the intrinsic stock price. 2. If the current stock price was $100.00, would...
Given the following information: Year 1 Free cash flow: 40 million Year 2 Free cash flow...
Given the following information: Year 1 Free cash flow: 40 million Year 2 Free cash flow 90 m Year 3 Free cash flow 100 m After year 3, expected FCF growth is expected to be 4% The cost of capital is 9% Short term investments = 50 million Debt is currently 25 million Preferred stock = 5 million There are 20 million outstanding stock shares. 1. Calculate the intrinsic stock price. 2. If the current stock price was $100.00, would...
You are considering two independent projects with the following cash flows. The required return for both...
You are considering two independent projects with the following cash flows. The required return for both projects is 10%. Given this information, which one of the following is correct? Year Project A Project B 0 -$950,000 -$125,000 1 $330,000    $   55,000 2 $400,000    $   50,000 3 $450,000    $ 50,000 A. You should accept project B since it has the higher IRR and reject project A because you cannot accept both projects. B. You should accept project A because it has...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT