Question

In: Finance

Intro WH Smith Company is evaluating three projects: A, B, C, with cash flows as given...

Intro

WH Smith Company is evaluating three projects: A, B, C, with cash flows as given in the table. Each project requires an initial investment of $96,000 and has a required return of 6%.

Year A B C
1 50,000 0 20,000
2 40,000 50,000 40,000
3 20,000 50,000 40,000
4 10,000 40,000 40,000

   Attempt 3/10 for 8 pts.

Part 1

What is the payback period for project A (in years)?

Submit

   Attempt 1/10 for 10 pts.

Part 2

What is the payback period for project B (in years)?

Submit

   Attempt 1/10 for 10 pts.

Part 3

What is the payback period for project C (in years)?

Submit

   Attempt 1/5 for 10 pts.

Part 4

Which project is best based on the payback rule?

Project A

Project C

Project B

Submit

   Attempt 1/10 for 10 pts.

Part 5

What is the NPV of project A?

Submit

   Attempt 1/10 for 10 pts.

Part 6

What is the NPV of project B?

Submit

   Attempt 1/10 for 10 pts.

Part 7

What is the NPV of project C?

Submit

   Attempt 1/5 for 10 pts.

Part 8

Which project is best based on the NPV rule?

Project C

Project B

Project A

Can you answer all questions?

Solutions

Expert Solution

Based on the given data, pls find below steps, workings and the answers:

Part 1

What is the payback period for project A (in years)? Answer 2.30 Years

Part 2

What is the payback period for project B (in years)? Answer 2.92 Years

Part 3

What is the payback period for project C (in years)? Answer 2.90 Years

Part 4

Which project is best based on the payback rule? Answer : Based on the Payback rule, the Proejct with shorter Payback period is considered as best and in this case, Proejct A has the lower Payback period and is considered best, based on Payback rule;

Part 5

What is the NPV of project A? Answer : NPV = $ 11482.99

Part 6

What is the NPV of project B? Answer : NPV = $ 22164.53

Part 7

What is the NPV of project C? Answer : NPV = $ 23736.30

Part 8

Which project is best based on the NPV rule? Answer : Based on the Net Present Value, the Project with higher value of NPV is considered as the best Project; In this case, Project C has the highest NPV and hence Project C is considered as best Project, based on NPV criteria

Computation of Net Present Value (NPV) based on the Discounted Cash flows; The Discounting factor is computed based on the formula: For year 0, the discounting factor is 1; For Year 1, it is computed as = Year 0 factor /(1+discounting factor%) ; Year 2 = Year 1 factor/(1+discounting factor %) and so on;

Next, the cashflows need to be multiplied with the respective years' discounting factor, to arrive at the discounting cash flows;

The total of all the discounted cash flows is equal to its respective Project NPV of the Cash Flows;

Computation of Pay Back Period: Here, the period is computed for each project, based on cumulative cash flows: If the cumulative value is less than or equal to zero, the period is considered as 12 months (it means that the net cumulative cash flow has not yet paid back the initial investment); Once the value turns positive in a particular year, the period for such year is observed at a proportion of actual discounted cash flow to the cumulative CF; This gives the period less than 12 months in such year; Once this is computed, total of all the years is taken and divided by 12, to arrive at the Payback period in no.of years.


Related Solutions

A company is evaluating two possible projects with the following cash flows. Suppose that the projects...
A company is evaluating two possible projects with the following cash flows. Suppose that the projects are contingent. Which answer describes the correct decision if the firm's required rate of return is 15%? Year 0 1 2 3 4 Project 1 -$50 $10 $15 $10 $20 Project 2 -$30 $20 $15 $30 $10 Question 16 options: Accept both projects. Accept project 1 and reject project 2. Accept project 2 and reject project 1. Reject both projects.
A company is evaluating two possible projects with the following cash flows. Suppose that the projects...
A company is evaluating two possible projects with the following cash flows. Suppose that the projects are contingent. Which answer describes the correct decision if the firm's required rate of return is 12%? Year 0 1 2 3 4 Project 1 -$50 $15 $15 $5 $5 Project 2 -$30 $20 $10 $10 $10
Suppose you are given the following two projects A and B with the cash flows below,...
Suppose you are given the following two projects A and B with the cash flows below, if the cost of capital is 10%, what is the Profitability Index (PI) of projects A and B? Year Project A Project B 0 -5000 -6000 1 1500 1500 2 2000 2500 3 3000 4000 4 3500 4000
Question 5 Given the following cash flows, for the two independent projects A and B, calculate...
Question 5 Given the following cash flows, for the two independent projects A and B, calculate Payback Period                                                                Accounting rate of return                                                Net Present Value                                                          Profitability index                                                           And recommend acceptance or rejection of projects considering individual techniques of capital budgeting. A rate of 10 % has been selected for the NPV analysis. Project A Project B Initial outlay $50,000 $100,000 Cash inflows Year 1 $10,000 $ 25,000 Year 2 15,000 25,000 Year 3 20,000 25,000 Year 4...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $22 $17 B −$100 $22 $41 $48 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$52 $27 $19 $18 $17 B −$101 $19 $40 $51 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$ 49 $ 24 $ 19 $ 20 $ 13 B -$ 100 $ 18 $ 39 $ 48 $ 59 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.5 % what are the NPVs of the two​ projects? c. Why...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A -$48 $27 $ 21 $ 19 $ 12 B −$98 $20 $ 41 $ 51 $ 59 a. What are the IRRs of the two​ projects? (Round to one decimal​ place.) b. If your discount rate is 4.7%​ what are the NPVs of the two​ projects? c. Why...
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$51 $24 $18 $21 $17 B −$102 $21 $38 $49 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently?
You are choosing between two projects. The cash flows for the projects are given in the...
You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$51 $26 $20 $18 $13 B −$101 $22 $39 $49 $58 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.4%​, what are the NPVs of the two​ projects? c. Why do IRR and NPV rank the two projects​ differently? a. What...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT