To complete a contract for fitting out a new shop in time for its opening, a refurbishment company has employed three temporary painters for 10 days at £45 per day and moved two carpenters who are paid £70 per day from another job for three days. The penalty for late completion of the shop is £300 but the delay to the carpenters’ current job will only cost £150. What are the relevant costs?
a) | £1,770 |
b) | £1,500 |
c) | £1,650 |
d) | £1,800 |
CALCULATION OF THE RELEVANT COST FOR CONTRACT | ||
Amount | Remarks | |
Temporary Painters (10 Days X 3 X 45) = | £ 1,350 | Furture Cash Outflow |
Two carpenters are move from another site to this Job | £ - | These carpenters are already our employee , Sono addittional cash outflow |
Delay in Current Job | £ 150 | Furture Cash Outflow |
Total Relevant Cost | £ 1,500 | |
Answer = Option B = | £ 1,500 | |