Question

In: Accounting

Everywhere there is a "?", I need a formula and the answer. Variance Analysis Insert a...

Everywhere there is a "?", I need a formula and the answer.

Variance Analysis
Insert a formula into each cell marked with a "?". For the variances indicate whether they are favorable or unfavorable
Bradley Company produces a garden statue which requires the following variable manufacturing costs:
Std Qty Std Price/Rate
Direct material (mix) 6 lbs 0.06 per lb
Direct labor 1 hours $16 per hour
Variable O/H (based on direct labor hours) 1 hours $8.30 per hour
Standard Cost per Unit:
Standard Cost
Direct Material ?
Direct Labor ?
Variable O/H ?
Total Std Cost per Unit ?
Bradley incurred the following variable production costs in February:
Units produced 500
Actual Qty Actual Price/Rate Actual Cost
Direct materials 2880 lbs $0.07 per lb ?
Direct labor 475 hours $15.00 per hour ?
Variable O/H 475 hours $8.00 per hour ?
Total Actual cost ?
Variance Calculations
Total Variance
Standard - Actual = Variance
? ? ?
Direct Material Variances
Total
Standard - Actual = Variance
? ? ?
Price
Difference in price x Actual Qty = Variance   
? ? ?
Quantity
Difference in quantity x Standard Price = Variance
? ? ?
Direct Labor Variances
Total
Standard - Actual = Variance
? ? ?
Rate
Difference in price x Actual Qty = Variance
? ? ?
Efficiency
Difference in quantity x Standard Price = Variance
? ? ?
Variable O/H Variances
Total
Standard - Actual = Variance
? ? ?
Rate
Difference in price x Actual Qty = Variance
? ? ?
Efficiency
Difference in quantity x Standard Price = Variance
? ? ?

Solutions

Expert Solution

Standerd cost per unit :
Direct meterial (6* .06) 0.36
Direct labour (1 *16) 16
Variable OH (1*8.3) 8.3
Total standeed cost per unit $24.66
Actual cost
Direct meterial 2880*.07 201.6
Direct labour 475*15 7125
Variable OH 475*8 3800
Total standeed cost per unit $11126.6
Material price variance
AP (a) SP (b) Variance (c=b-a) AQ (d) Total variance (e=c*d) F/U
Material price variance = (AP-SP)*AQ
AP = Actual price per unit = $0.07
SP = Standard price per unit = $0.06
AQ = Actual quantity consumed= 2880
F= Favourable
U = Unfavourable
Material price variance
AP (a) SP (b) Variance (c=b-a) AQ (d) Total variance (e=c*d) F/U
0.07 0.06 -0.01 2880 -28.8 U
Material quantity variance
AQ (a) SQ (b) Variance (c=b-a) SP (d) Total variance (e=c*d) F/U
Material quantity variance = (AQ-SQ)*SP
AQ = Actual quantity consumed= 2880
SQ = Standard quantity = 500*6 = 3000
SP = Standard price per unit = $0.06
F= Favourable
U = Unfavourable
Material quantity variance
AQ (a) SQ (b) Variance (c=b-a) SP (d) Total variance (e=c*d) F/U
2880 3000 120 0.06 7.2 F
Total Material variance
Total Actual Total Std Total variance F/U
201.6 180 -21.6 U
(2880*.07) (3000*0.06)
Labor Rate variance
AR (a) SR (b) Variance (c=b-a) AH (d) Total variance (e=c*d) F/U
Labor Rate variance = (AR-SR)*AH
AR = Actual Rate per hour = $15
SR = Standard Rate per hour = $16
AH = Actual hours = 475
F= Favourable
U = Unfavourable
Labor Rate variance
AR (a) SR (b) Variance (c=b-a) AH (d) Total variance (e=c*d) F/U
15 16 1 475 475 F
Labor Efficiency variance
AH (a) SH (b) Variance (c=b-a) AR (d) Total variance (e=c*d) F/U
Labor Efficiency variance = (AH-SH)*AR
AH = Actual hours = 475
SH = Standard Hours = 500
SR = Standard Rate per hour =16
F= Favourable
U = Unfavourable
Labor Efficiency variance
AH (a) SH (b) Variance (c=b-a) SR (d) Total variance (e=c*d) F/U
475 500 25 16 400 F
Total Labor variance
Total Actual Total Std Total variance F/U
7125 8000 875 F
(475*15) (500*16)
VOH spending variance
AR (a) SR (b) Variance (c=b-a) AH (d) Total variance (e=c*d) F/U
VOH spending variance = (AR-SR)*AH
AR = Actual Rate per hour = $8
SR = Standard Rate per hour = $8.3
AH = Actual hours = 475
F= Favourable
U = Unfavourable
VOH spending variance
AR (a) SR (b) Variance (c=b-a) AH (d) Total variance (e=c*d) F/U
8 8.3 0.3 475 142.5 F
VOH efficiency variance
AH (a) SH (b) Variance (c=b-a) SR (d) Total variance (e=c*d) F/U
VOH efficiency variance = (AH-SH)*SR
AH = Actual hours = 475
SH = Standard Hours = 500
SR = Standard Rate per hour =8.3
F= Favourable
U = Unfavourable
VOH efficiency variance
AH (a) SH (b) Variance (c=b-a) Price (d) Total variance (e=c*d) F/U
475 500 25 8.3 207.5 F
Total VOH variance
Total Actual Total Std Total variance F/U
3800 4150 350 F
(475*8) (500*8.3)

Related Solutions

Variance Analysis Insert a formula into each cell marked with a "?". For the variances indicate...
Variance Analysis Insert a formula into each cell marked with a "?". For the variances indicate whether they are favorable or unfavorable Bradley Company produces a garden statue which requires the following variable manufacturing costs: Std Qty Std Price/Rate Direct material (mix) 6 lbs 0.06 per lb Direct labor 1 hours $16 per hour Variable O/H (based on direct labor hours) 1 hours $8.30 per hour Standard Cost per Unit: Standard Cost Direct Material ? Direct Labor ? Variable O/H...
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
I need solution and formula as clear.Otherwise , I will have to report the answer. Assume...
I need solution and formula as clear.Otherwise , I will have to report the answer. Assume that X and Y has a continuous joint p.d.f. as 28x2y3 in 0<y<x<1 interval. Otherwise the joint p.d.f. is equal to 0. a.Calculate Var(X) b.Calculate P(X< 0.1) c.Calculate P(X> 0.1) d.Calculate P(X>2) e.Calculate P(-2<X<0.1)
I need step wise hand written solution with formula as I have answer of following question:-...
I need step wise hand written solution with formula as I have answer of following question:- The Provincial Bank lent $20 000 to the owner of the Purple Pelican on April 1, 2012, for commercial improvements. The loan was secured by a demand note subject to a variable rate of interest. This rate was 7% on April 1. The rate of interest was raised to 9% effective August 1 and reduced to 8% effective November 1. Partial payments, applied to the...
DBMS Create/Insert/Update SQL I need the create, insert, and update SQL statement for this table as...
DBMS Create/Insert/Update SQL I need the create, insert, and update SQL statement for this table as if it were being added to MySQL (please give explanations for each line of SQL code and a copy of the code as it would be entered into the query by itself: Customer PK Customer ID Text Phone Number int name text address ID int email text FK vendor ID int Vendor is the name of the table the FK comes from.
DBMS Create/Insert/Update SQL I need the create, insert, and update SQL statement for this table: Customer...
DBMS Create/Insert/Update SQL I need the create, insert, and update SQL statement for this table: Customer PK Customer ID Text Phone Number int name text address ID int email text FK vendor ID int Vendor is the name of the table the FK comes from.
•Calculate the variance analysis for the information provided below using this problem and the formula provided...
•Calculate the variance analysis for the information provided below using this problem and the formula provided to you. Data: Budget Actual Variance Total Payroll Cost $65,600.00 $78,627.50 $13,027.50 Total Nursing Hours 1600 1850 250 Composite Hourly Pay Rate $30.00 $33.00 $3.00 Patient Days 350 375 25 Formulas to use in calculations for variance analysis: Step #1: Compute the Efficiency Variance. Budgeted nursing hours   / Budgeted patient days = HPPD Budgeted Actual nursing hours / Actual patient days = HPPD Actual...
What order would I need to insert the numbers 1 to 7 into a new AVL...
What order would I need to insert the numbers 1 to 7 into a new AVL tree in order to ensure that there was no need to perform a rotation.
Marketing department I need long answer /short answer is not working I need unique answer please...
Marketing department I need long answer /short answer is not working I need unique answer please don't copy I need references, use APA style If answer without references I will hit you dislike Question: Which strategies in Huawei company should make regarding its portfolio of current and future products. What are the dimensions upon which a company manages its product portfolio? Instructions: Good and clear explanation of the various dimensions upon which a company manages its product portfolio (product mix...
(i just need an answer for question 4) (i just need an answer for just question...
(i just need an answer for question 4) (i just need an answer for just question 4) you have two facilities, one in Malaysia and one in Indonesia. The variable cost curve in the Malaysian plant is described as follows: VCM = q­ + .0005*q2 , where q is quantity produced in that plant per month. The variable cost curve in the Indonesian plant is described by VCI = .5q + .00075q2, where q is the quantity produced in that...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT