Question

In: Finance

•Calculate the variance analysis for the information provided below using this problem and the formula provided...

•Calculate the variance analysis for the information provided below using this problem and the formula provided to you.

Data:

Budget Actual Variance
Total Payroll Cost $65,600.00 $78,627.50 $13,027.50
Total Nursing Hours 1600 1850 250
Composite Hourly Pay Rate $30.00 $33.00 $3.00
Patient Days 350 375 25

Formulas to use in calculations for variance analysis:

Step #1: Compute the Efficiency Variance.

Budgeted nursing hours   / Budgeted patient days = HPPD Budgeted

Actual nursing hours / Actual patient days = HPPD Actual

HPPD Actual - HPPD Budgeted

Actual patient days X extra nursing care hours = Total extra

Total extra X Budgeted hourly wage = Efficiency (in dollars)

Step #2: Compute the volume variance.

Actual patient days - Budgeted patient days = A

A X Budgeted HPPD = B

B X Budgeted pay = V (dollars)

Step #3: Compute the cost variance.

Actual $ paid - Budgeted $ paid = D

D X Actual hours worked = C (dollars)

Step #4: Calculate the Budget Variance.

Efficiency + Volume + Cost = Budget Variance

Solutions

Expert Solution

Step #1: Compute the Efficiency Variance.
Budgeted nursing hours   / Budgeted patient days = HPPD Budgeted                          4.57
Actual nursing hours / Actual patient days = HPPD Actual                          4.93
HPPD Actual - HPPD Budgeted                          0.36
Actual patient days X extra nursing care hours = Total extra                      135.71
Total extra X Budgeted hourly wage = Efficiency (in dollars) $              4,071.43
Budgeted nursing hours                  1,600.00
Budgeted patient days                      350.00
Actual nursing hours                  1,850.00
Actual patient days                      375.00
extra nursing care hours                          0.36
Budgeted hourly wage                        30.00
Actual hourly wage                        33.00
Step #2: Compute the volume variance.
Actual patient days - Budgeted patient days = A                        25.00
A X Budgeted HPPD = B                      114.29
B X Budgeted pay = V (dollars) $              3,428.57
Step #3: Compute the cost variance.
Actual $ paid - Budgeted $ paid = D                          3.00
D X Actual hours worked = C (dollars) $              5,550.00
Step #4: Calculate the Budget Variance.
Efficiency + Volume + Cost = Budget Variance $           13,050.00


Related Solutions

Using the partially completed analysis of variance and table of means provided below, answer the following...
Using the partially completed analysis of variance and table of means provided below, answer the following questions. Use the .05 significance level. All three groups have the same sample size. Source SS df MS F Treatment 4.3669 Error 9.03 Total 29 Group A B C sample mean 278.3 275.4 274.5 10. Find the value of LSD for comparing Groups A and B. 11. Is the difference between groups A and B significant? yes no maybe? Antidisestablishmentarianism 12. What's the value...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION : Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION: Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per hour...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3)...
1.2 REQUIRED: Use the information provided below to calculate the following: 1.2.1 Idle time variance (3) 1.2.2 Labour mix variance (7) 1.2.3 Labour yield variance (3) Indicate whether each variance is favourable or unfavourable. INFORMATION: Standard labour costs for Electro Manufacturers to manufacture 2 000 units: 400 hours at R70 per hour 200 hours at R35 per hour Actual labour costs incurred to produce 1 900 units: 290 hours at R R65 per hour 170 hours at R32 per hour...
Using the information provided below, calculate the closing stock valuations and the profit figures for Product...
Using the information provided below, calculate the closing stock valuations and the profit figures for Product Z under both Absorption Costing principles and Variable Costing principles. Product Z: Annual production (units) 31,000 Units sold during the period 25,000 Costs: Direct materials per unit €10 Direct labour per unit €21 Administration expenses for period €15,000 Overheads incurred: Power and maintenance (variable) €24,000 Other factory overheads (fixed) €36,000 Other information: Selling price per unit €40 Total machine hours per annum 12,000 hours...
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
What are the formula of Standard costs for variance Analysis (Effieciency Variance and Price Variance) ?
Using the table below, calculate the variance of X, variance of Y, standard deviation of X,...
Using the table below, calculate the variance of X, variance of Y, standard deviation of X, standard deviation of Y,   the covariance between X and Y, the correlation coefficient between X and Y, and find the regression line assuming X is the independent variable (find the slope and the intercept). Show your work Fill in the Blanks: X Y X-Xbar Y-Ybar (X-Xbar)^2 (Y-Ybar)^2 (X-Xbar)*(Y-Ybar) 5 3 9 6 12 15 17 20 21 23 Sum Calculate the following and show...
Using the below data calculate the quadratic formula. Then calculate the following: i) Fixed cost ii)...
Using the below data calculate the quadratic formula. Then calculate the following: i) Fixed cost ii) Average total cost iii) Marginal cost d) Using your answers from part c) calculate fixed cost, average total cost, and marginal cost if 25 units Coefficient Std. Error t-ratio p-value const 2.22486 2.29906 0.9677 0.3347 q 0.00434763 0.000230941 18.83 <0.0001 sq_q 1.63160e-08 2.79915e-09 5.829 <0.0001
Everywhere there is a "?", I need a formula and the answer. Variance Analysis Insert a...
Everywhere there is a "?", I need a formula and the answer. Variance Analysis Insert a formula into each cell marked with a "?". For the variances indicate whether they are favorable or unfavorable Bradley Company produces a garden statue which requires the following variable manufacturing costs: Std Qty Std Price/Rate Direct material (mix) 6 lbs 0.06 per lb Direct labor 1 hours $16 per hour Variable O/H (based on direct labor hours) 1 hours $8.30 per hour Standard Cost...
Variance Analysis Insert a formula into each cell marked with a "?". For the variances indicate...
Variance Analysis Insert a formula into each cell marked with a "?". For the variances indicate whether they are favorable or unfavorable Bradley Company produces a garden statue which requires the following variable manufacturing costs: Std Qty Std Price/Rate Direct material (mix) 6 lbs 0.06 per lb Direct labor 1 hours $16 per hour Variable O/H (based on direct labor hours) 1 hours $8.30 per hour Standard Cost per Unit: Standard Cost Direct Material ? Direct Labor ? Variable O/H...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT