In: Accounting
Use the information below to answer the following
question(s):
Cruise Company produces a part that is used in the manufacture of
one of its products. The unit manufacturing costs of this part,
assuming a production level of 6,000 units, are as follows:
Direct materials $4.00
Direct labour $4.00
Variable manufacturing overhead $3.00
Fixed manufacturing overhead $1.00
Total cost $12.00
The fixed overhead costs are unavoidable.
6. Assuming Cruise Company can purchase 6,000 units of the part
from Suri Company for $9 each, and the facilities currently used to
make the part could be rented out to another manufacturer for
$24,000 a year, what should Cruise Company do?
a. Make the part and save $6.00 per unit.
b. Make the part and save $2.00 per unit.
c. Buy the part and save $2.00 per unit.
d. Buy the part and save $6.00 per unit.
7. Assume Cruise Company can purchase 6,000 units of the part from
Suri Company for $14.00 each, and the facilities currently used to
make the part could be used to manufacture 6,000 units of another
product that would have an $8 per unit contribution margin. If no
additional fixed costs would be incurred, what should Cruise
Company do?
a. Make the new product and buy the part to earn an extra $5.00 per
unit contribution to profit.
b. Make the new product and buy the part to earn an extra $6.00 per
unit contribution to profit.
c. Continue to make the part to earn an extra $2.00 per unit
contribution to profit.
d. Continue to make the part to earn an extra $4.00 per unit
contribution to profit.
8. What does a favourable direct materials price variance
indicate?
a. The actual cost of materials purchased was greater than the
standard cost of materials purchased.
b. The standard cost of materials purchased was less than the
actual cost of materials purchased.
c. The standard cost of materials purchased was greater than the
actual cost of materials purchased.
d. The actual quantity of materials used was less than the standard
quantity of materials used for actual production.
9. In flexible budgets, costs that remain the same regardless of
the output levels within the relevant range are
a. allocated costs.
b. budgeted costs.
c. fixed costs.
d. variable costs.
e. estimated costs.
10. Actual overhead is $698,000, while budgeted overhead is
$598,000. What is the fixed overhead static-budget variance if
250,000 units are produced and 225,000 are budgeted?
a. $80,000 favourable
b. $100,000 unfavourable
c. $100,000 favourable
d. $101,000 unfavourable
e. $102,000 favourable
Answer 6. d. Buy the part and save $6.00 per unit
Explanation:
Relevant cost of making | Relevant cost of buying | |
Direct materials | $4 | |
Direct labor | $4 | |
Variable manufacturing overhead | $3 | |
Opportunity cost for renting ($24,000 / 6,000) | $4 | |
Purchase cost | $9 | |
Cost per unit | $15 | $9 |
Cost of buying saves $6.00 ($15 - $9) per unit.
Answer 7. a. Make the new product and buy the part to earn an extra $5.00 per unit contribution to profit
Explanation:
Relevant cost of making | Relevant cost of buying | |
Direct materials | $4 | |
Direct labor | $4 | |
Variable manufacturing overhead | $3 | |
Opportunity cost to make the new product | $8 | |
Purchase cost | $14 | |
Cost per unit | $19 | $14 |
Buying the part & making new product will save $5.00 ($19 - $14) per unit
Answer 8. c. The standard cost of materials purchased was greater than the actual cost of materials purchased.
Explanation:
Direct materials price variance = (Actual price - Standard price) * Actual quantity purchased.
Thus direct materials price variance is favorable when the actual price is less than the standard price.
Answer 9. c. fixed costs.
Explanation:
Fixed costs under flexible budgets remain constant for all output levels for a given range.
Answer 10. b. $100,000 unfavorable
Explanation:
Fixed overhead static-budget variance = Actual overhead - Budgeted overhead
= $698,000 - $598,000 = $100,000 unfavorable.
Since Actual overhead > Budgeted overhead, the resultant fixed overhead static-budget variance is unfavorable.