In: Operations Management
The product design group of Iyengar Electric Supplies, Inc., has determined that it needs to design a new series of switches. It must decide on one of three design strategies. The market forecast is for
200,000
units. The better and more sophisticated the design strategy and the more time spent on value engineering, the less will be the variable cost. The chief of engineering design, Dr. W. L. Berry, has decided that the following costs are a good estimate of the initial and variable costs connected with each of the three strategies explained below.
Low-tech:
a low-technology, low-cost process consisting of hiring several new junior engineers. This option has a fixed cost of
40,000
and variable-cost probabilities of
0.5
for
$0.54
0.1
for
$0.49
and
0.4
for
$0.47
Subcontract:
a medium-cost approach using a good outside design staff. This approach would have a fixed cost of
60,000
and variable-cost probabilities of
0.70.7
of
$0.52
0.2
of
$0.47
and
0.1
of
$0.37
High-tech:
a high-technology approach using the very best of the inside staff and the latest computer-aided design technology. This approach has a fixed cost of
85,000
and variable-cost probabilities of
0.90
of
$0.39
and
0.1
of
$0.38
What is the best decision based on an expected monetary value (EMV) criterion?
(Note:
We want the lowest EMV, as we are dealing with costs in this problem.)
High-tech
Subcontract
Low-tech
We find EMV of each decision as shown below:
Low-tech option:
Fixed Cost = 40,000
Based on probability, expected variable cost = (0.5 * $0.54) + (0.1 * $0.49) + (0.4 * $0.47) = $0.507
Total Cost = Fixed cost + Total Variable cost = 40,000 + 0.507 * 200,000 units = $141,400
Subcontract option:
Fixed Cost = 60,000
Based on probability, expected variable cost = (0.7 * $0.52) + (0.2 * $0.47) + (0.1 * $0.37) = $0.495
Total Cost = Fixed cost + Total Variable cost = 60,000 + 0.495 * 200,000 units = $159,000
High-tech option:
Fixed Cost = 85,000
Based on probability, expected variable cost = (0.9 * $0.39) + (0.1 * $0.38) = $0.389
Total Cost = Fixed cost + Total Variable cost = 85,000 + 0.389 * 200,000 units = $162,800
As seen from above, low-tech has the lowest expected cost.
Hence, the best decision based on an expected monetary value (EMV) criterion is Low-tech
----------------------------------------------------------------------------------------------------------------------------------------------------
In case of any doubt, please ask through the comment section before Upvote/downvote.