Question

In: Math

An engineering group needs to set up an assembly line to produce a new product. The...

An engineering group needs to set up an assembly line to produce a new product. The following table describes the relationships between the activities, their predecessors, and the estimated activity times (in weeks) for this project. (10 points)

Activity

Immediate

Predecessors)

Optimistic

(Weeks)

Most Likely

(Weeks)

Pessimistic

(Weeks)

A

---

4

7

10

B

A

2

8

20

C

A

8

12

16

D

B

1

2

3

E

D, C

6

8

22

F

C

2

3

4

G

F

2

2

2

H

F

6

8

10

I

E, G, H

4

8

12

J

I

1

2

3

  1. Using this data, develop a network for this project.
  2. Identify the critical path and determine the expected time of completion of the project.
  3. Prepare the detailed activity schedule for this project (i.e., provide a table showing EST, EFT, LST, LFT, Slack, critical path?).
  4. Determine the probability that the project will be completed in:
  1. Less than 42 weeks
  2. Greater than 35 weeks
  3. Between 42 to 44 weeks
  4. Greater than 40 weeks

Solutions

Expert Solution


Related Solutions

The Laurenster Corporation needs to set up an assembly line to produce a new product. The...
The Laurenster Corporation needs to set up an assembly line to produce a new product. The fol- lowing table describes the relationships among the activities that need to be completed for this product to be manufactured.    DAYS    IMMEDIATE ACTIVITY    a m                     b                      PREDECESSORS A 3                      6                      6                                  —                               B                     5                      8                      11                                A                                 C                     5                      6                      10                                A                                             D                     1                      2                      6                                  B,...
Layout Part A A facility is setting up an assembly line to produce 75 units per...
Layout Part A A facility is setting up an assembly line to produce 75 units per day, working 24 hours per day. Calculate the desired cycle time in minutes per unit. (Round up to a whole number) Part B Task Time (Min) Predecessors A 4 - B 3 - C 5 A D 5 A,B E 3 C,D Assume a facility is setting us an assembly line and the tasks and times are listed above. Assume the desired cycle time...
Digital Eye must design an assembly line to produce a new line of slim digital cameras....
Digital Eye must design an assembly line to produce a new line of slim digital cameras. Assembling a single camera requires the completion of nine distinct tasks, and information about each of these tasks is provided below: Task Immediate Predecessors Task Duration (Seconds) A None 20 B A 15 C A 20 D B 12 E B 8 F B 15 G D,E 30 H C,F 25 I G,H 9 This assembly line will operate 8 hours a day to...
Tisla Motors needs to select an assembly line for producing their new SUV. They have two...
Tisla Motors needs to select an assembly line for producing their new SUV. They have two options: Option A is a highly automated assembly line that has a large up-front cost but low maintenance cost over the years. This option will cost $9 million today with a yearly operating cost of $2 million. The assembly line will last for 5 years and be sold for $5 million in 5 years. Option B is a cheaper alternative with less technology, a...
Ruff Motors needs to select an assembly line for producing their new SUV. They have two...
Ruff Motors needs to select an assembly line for producing their new SUV. They have two options: Option A is a highly automated assembly line that has a large up-front cost but low maintenance cost over the years. This option will cost $9 million today with a yearly operating cost of $2 million. The assembly line will last for 5 years and be sold for $5 million in 5 years. Option B is a cheaper alternative with less technology, a...
A projection for a new product line was prepared by a task force from Engineering and...
A projection for a new product line was prepared by a task force from Engineering and Sales. The plan presented to management calls for an initial investment of $13,000,000 which is projected to generate annual revenue which increases at $750,000 per year, with a first year revenue of $5,000,000. Annual costs which are estimated at $2,750,000 for the first year, are expected to increase in direct proportion to the annual revenue. The task force has made a case for a...
The Ashton Group is developing a new product line. Initial costs for the line are $83191....
The Ashton Group is developing a new product line. Initial costs for the line are $83191. Annual utilities will be $29917. The company plans to concentrate on marketing for the first 3 years at a cost of $11746 per year. Profits are anticipated to be zero for the first few years. It is estimated the product line will finally have a profit of $453436 at the end of year 6 and profits will continue to increase by 18% each subsequent...
The Ashton Group is developing a new product line. Initial costs for the line are $94693....
The Ashton Group is developing a new product line. Initial costs for the line are $94693. Annual utilities will be $34518. The company plans to concentrate on marketing for the first 2 years at a cost of $11430 per year. Profits are anticipated to be zero for the first few years. It is estimated the product line will finally have a profit of $469315 at the end of year 6 and profits will continue to increase by 20% each subsequent...
The Ashton Group is developing a new product line. Initial costs for the line are $87985....
The Ashton Group is developing a new product line. Initial costs for the line are $87985. Annual utilities will be $34193. The company plans to concentrate on marketing for the first 4 years at a cost of $13812 per year. Profits are anticipated to be zero for the first few years. It is estimated the product line will finally have a profit of $466925 at the end of year 5 and profits will continue to increase by 19% each subsequent...
Trademark Inc. is planning to set up a new manufacturing plant in New York to produce...
Trademark Inc. is planning to set up a new manufacturing plant in New York to produce safety tools. The company bought some land six years ago for $4.3 million in anticipation of using it as a warehouse and distribution site, but the company has since decided to rent these facilities from a competitor instead. If the land were sold today, the company would sell for $4.6 million on an after-tax basis. In four years, the land could be sold for...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT