Question

In: Operations Management

5. You are preparing a project to lay fiber optic cable. The first task is to...

5. You are preparing a project to lay fiber optic cable. The first task is to mobilize the team. You estimate this will take one week and cost $4000. The second task is to lay the cable. This will take three weeks and will cost $30,000. The total length of the cable is 15 miles. The last task, which will take one week, is to terminate and test the cable. You budget $6000 for this. At the end of the first week, you have completed mobilization, but it cost a total of $4500. At the end of the third week, you have completed five miles of cable at a total cost of $28,000 (installation only). It takes you a total of 10 weeks to complete the entire project, for a total cost of $75,000.

a. At the end of week 1: i. What is your SPI? ii. What is your CPI? iii. What is your EAC?

b. At the end of week 3: i. What is your SPI? ii. What is your CPI? iii. What is your EAC?

c. At the end of the project: i. What is your SPI? ii. What is your CPI? iii. What is your EAC?

Can someone show me how to do this on Excel?

Thanks

Solutions

Expert Solution

Total Budget = Budget for mobilization + Budget for laying cable + Budget for termination and testing = 4000 + 30000 + 6000 = $40,000. Similarly planned time for completion = 1 + 3 + 1 = 5 weeks.

(a) After week 1 mobilization is complete as planned. Hence Planned Value = Earned Value = 4000 => SPI = 1. Actual Cost = 4500. CPI = Earned Value/Actual Cost = 4000/4500 = 0.88. EAC = Estimate at completion = Cost incurred till date + Budget for the rest of the project = 4500 + 30,000 + 6000 = $40,500

(b) After 3 weeks 5 miles are completed in addition to mobilization. Plan was to complete 2/3rd of laying in 2 weeks after mobilization . This should have cost 2/3 of 30,000 = 20,000. Hence total planned value for 3 weeks was 20,000 + 4000 = $24,000. Earned value is only Mobilization and 5 miles of cable laying = 4000 + 5/15 * 30,000 = $14,000. Hence SPI = Earned Value / Planned Value = 14,000/24,000 = 0.58.

Cost incurred = 4500 + 28,000 = $32,500. CPI = EV / Actual Cost = 14,000/32,500 = 0.43. To calculate estimate at completion we need to recalculate budget needed for completion of current task. 5 miles has cost 28,000. Hence balance 10 miles will cost 56,000 at current rates. Hence estimate at completion after week 3= 4500 + 28000 + 56,000 + 6000 = $94,500

(c) AT the end of the project Planned Value = Earned Value again = 40,000 Hence SPI = 1. Actual Cost = 75000. Hence CPI = EV/Actual Cost = 70/ 75=0.93. Eastimate at completion is the actual cost since project is complete = 75,000


Related Solutions

Write a program that will calculate the cost of installing fiber optic cable at a cost...
Write a program that will calculate the cost of installing fiber optic cable at a cost of .87 per ft for a company. Your program should display the company name and the total cost. Display a welcome message for your program. Get the company name from the user Get the number of feet of fiber optic to be installed from the user Multiply the total cost as the number of feet times .87. Display the calculated information and company name.
Why, a fiber optic cable cannot be called as a transmission line? Also clarify what are...
Why, a fiber optic cable cannot be called as a transmission line? Also clarify what are the primary conditions required for a transmission line. (b)Why a structured cabling system is required? Describe the structure in a proper flow with a neat diagram.
Revised Problem 5-65 Fresno Fiber Optics, Inc. manufactures fiber optic cables for the computer and telecommunications...
Revised Problem 5-65 Fresno Fiber Optics, Inc. manufactures fiber optic cables for the computer and telecommunications industries. At the request of the company VP of marketing, the cost management staff has recently completed a customer profitability study. The following activity-based costing information was the basis for the analysis. Customer - Related Activities Cost Driver Base Cost Driver Rate Sales activity Sales visits $        860 Billing and Collection Invoices 160 Order taking Purchase orders 220 Special shipping Shipments 430 Customer -...
PREPARING YOUR FIRST SPEECH How are you feeling as you are preparing your first speech?   ...
PREPARING YOUR FIRST SPEECH How are you feeling as you are preparing your first speech?    What communication tips are helping you to reduce any anxiety? Are you allowing yourself plenty of time to prepare and practice? What will be your preparation process for this week's assignment?
Overview: For this task you will first compare the ACHE and AHIMA code of ethics and...
Overview: For this task you will first compare the ACHE and AHIMA code of ethics and then review a brief case from Healthcare Marketing: A Case Study that involves ethical decision-making. Then you will discuss the role of the healthcare marketer in relation to ethical behavior and conduct. ● Codes of Ethics: American College of Healthcare Executives (ACHE) Code of Ethics American Health Information Management Association (AHIMA) Code of Ethics 1. Compare the code of ethics from these two organizations....
You are hired as a financial manager and your first task is to establish the cash...
You are hired as a financial manager and your first task is to establish the cash budget of your firm. You gathered the following information. The firm receives all income from sales Sales estimates (in millions) Q1 = 1,000; Q2 = 1,250; Q3 = 1,500; Q4 = 2,000; Q1 next year = 1,200 Accounts receivable Beginning receivables = $3000 Average collection period = 45 days Accounts payable Purchases = 60% of next quarter’s sales Beginning payables = 1,200 Accounts payable...
you were just hired as a researcher in an in an immunology lab. Your first task...
you were just hired as a researcher in an in an immunology lab. Your first task in the lab is to inject mice with a sufficient dose of live pneumococcus bacteria so it dies from the infection within a few days. You also heat-up (but not boil) some of the Pneumococcal bacteria to kill the cells and inject the heat-killed bacteria into the mice. These mice do not succumb to the infection and it will survive a subsequent injection of...
You have been hired as Financial advisor by Texas Corporation and the first task that is...
You have been hired as Financial advisor by Texas Corporation and the first task that is assigned to you is to help the company determine its optimal capital structure. a) What factors will help you in determining the optimal structure for Texas Corporation. b) From the financial statements of the company you have discovered that company has a very high operating leverage. How is it effecting the firm's profitability? c) The company is in a higher tax bracket defined by...
You have just joined the design and development group at Panasonic, Inc. The first task you...
You have just joined the design and development group at Panasonic, Inc. The first task you are given is to work on the design of a thermal system to anneal TV glass screens. Each screen is made of semi-transparent glass and weighs 10 kg. You need to heat it from a room temperature of 25°C to 1100°C, maintain it at this temperature for 15 minutes, and then cool slowly to 500°C, after which it may be cooled more rapidly to...
Task 3: Research Project (5 marks) You’re investigating a case involving a 2 GB drive that...
Task 3: Research Project You’re investigating a case involving a 2 GB drive that you need to copy at the scene. Describe the three types of acquisitions – physical, logical, and sparse that you can use to copy the drive accurately. Be sure to include your software and media choices. Deliverable: Write a 300-500 word report that outlines standard investigation management and data validation methods.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT