Question

In: Operations Management

Scenario Mega Manufacture, Inc. (MMI) decided to build a new factory. It hired AAI, an architectural...

Scenario

Mega Manufacture, Inc. (MMI) decided to build a new factory. It hired AAI, an architectural firm, to create the design. AAI retained a geotechnical firm, Geo-R-Us, Inc., to perform a soil report. AAI used that soil report to design the excavation and foundation specifications.

MMI used the completed design to solicit fixed-price bids from a variety of prime contractors. The design included the excavation requirements and foundation specifications. The advertisement advised that the geotechnical report was available for review at the office of Geo-R-Us and was provided “for information only.”

Prime Builder, Inc. decided to bid on the job. Its president, Mr. Prime, visited the site, which was an empty lot. Mr. Prime was mostly concerned with the logistics of working in the remote location. He examined the foundation design and saw no obvious conflict with the subsurface indications (he saw no boulders or swampy areas), but he did not go to the office of Geo-R-Us to examine the original geotechnical report.

MMI entered into a fixed-price contract with Prime Builder, using American Institute of Architect (AIA) General Conditions of the Contract for Construction, A201-2007. Prime Builder began the excavation work and discovered far more boulders than anticipated. MMI refused to grant Prime Builder additional compensation or time, stating that the construction was Prime Builder’s responsibility.

Within a couple of years, the completed factory developed cracks and sticking doors. When contractor refused to make repairs, MMI sued it for breach of contract and negligence. Prime Builder then brought a third -party complaint against Geo-R-Us. Prime Builder introduced expert testimony as to the causes of the failures.

A geotechnical expert testified that the Geo-R-Us report was defective because too few boring logs were drilled. Specifically, Geo-R-Us failed to take borings from one corner of the lot which contained expansive soil. The foundation designed by AIA was inadequate to deal with this type of soil.

(Chapter 19)

Provide your legal analysis of the following questions.

1) (25%) MMI (owner) used a disclaimer system by an approach that gives the information but states that it is “for information only.” Answer the following two questions.

a) Which party does the disclaimer system put the risk on? owners or the contractors?

b) What are the three drawbacks of the disclaimer system?

2) (25%) The Geo-R-Us report was defective. Can Prime Builder (the contractor) bring a misrepresentation claim?

First, answer Yes or No. Then, briefly explain why.

3) (25%) MMI and Prime Builder used AIA A201-2007, which contains a differing site condition (DSC) clause. Here, Prime builder encountered an unusual number of boulders when it began excavation. Assuming the contractor provided prompt notice, may it bring a Type I DSC claim against MMI? Suppose the geotechnical report warned of boulders in the area.

First, answer Yes or No. Then, briefly explain why.

4) (25%) MMI and Prime Builder used AIA A201-2007, which contains a differing site condition (DSC) clause. Here, Prime builder encountered an unusual number of boulders when it began excavation. Assuming the contractor provided prompt notice, may it bring a Type II DSC claim against MMI? Suppose the geotechnical report warned of boulders in the area.

First, answer Yes or No. Then, briefly explain why.

Solutions

Expert Solution

Answer 1:

a) The risk is on the contractor because through the disclaimer system the owner (MMI) has restricted any claims or any responsibility for any future legal actions or of any other kind of actions against themself or the construction.

b) The three drawbacks of the disclaimer system are as follows:

1. Restricting the risk of the disclaiming party.

2. The information disclaimed must be true, else it will be treated as a misrepresentation.

3. Strong legal consequences will be over the other parties involved in the construction, in case of any default.

Answer 2: Yes, the Prime Builder the contractor can claim misrepresentation against MMI because a disclaimer is the source of information and is treated as a validation from the side of the disclaiming party.

Answer 3: Yes. Supposing if the geotechnical report warned of boulders in the area and still Prime Builder encounters an unusual number of boulders when it began excavation. He can claim against MMI under a Type I DSC. Because according to the Type I DSC claim the aggrieved party can raise the claim in case if the site surface condition deviates substantially from the condition which was represented at the time of bidding.

Answer 4: Yes, because under Type I DSC claim if the contractor encounters any condition which materially differs from the condition mentioned at the time of contract. The contractor has the right to claim damages or any other applicable relief.

"If you liked the answer please give an Up-vote, this will be quite encouraging for me, thank you!"


Related Solutions

MagTech Inc. requires funding to build a new factory and has decided to raise the additional...
MagTech Inc. requires funding to build a new factory and has decided to raise the additional capital by issuing $850,000 face value of bonds with a coupon rate of 10%. In discussions with investment bankers, it was determined that to help the sale of the bonds, detachable stock warrants should be issued at the rate of 5 warrants for each $1,000 bond sold. The value of the bonds without the warrants is considered to be $775,000, and the value of...
A company wants to build a new factory. They know the cost to build the factory...
A company wants to build a new factory. They know the cost to build the factory and have forecasted the future cash flows from the plant. They want to do an NPV analysis but are not sure what rate to use. They come to you as a consultant to figure out their cost of capital. The information they have given you is: They just paid a dividend of $2.75. Their dividend growth rate is 4.8%. Their current stock price is...
Mutton Motors wants to build a new factory. They know the cost to build the factory...
Mutton Motors wants to build a new factory. They know the cost to build the factory and have forecasted the future cash flows from the plant. They want to do an NPV analysis but are not sure what rate to use. They come to you as a consultant to figure out their cost of capital. The information they have given you is: They just paid a dividend of $2.75. Their dividend growth rate is 4.8%. Their current stock price is...
Task 2 Scenario Mega construction Plc, are contractors for replacement of a high technology factory for...
Task 2 Scenario Mega construction Plc, are contractors for replacement of a high technology factory for a multinational company. The total value of the contract is £ 3,500,000 over a three year period. The contract commenced on 1st March 2011, & the following details are available as at 28th February 2012 Material purchases 65,000 Material transfers in from other site 28,000 Material transfer out to another site. 5,000 Material on site, not yet used 28,000 Direct labour 29,000 Direct labour...
E16-7B (L02) (Issuance of Bonds with Warrants) MagTech Inc. requires funding to build a new factory...
E16-7B (L02) (Issuance of Bonds with Warrants) MagTech Inc. requires funding to build a new factory and has decided to raise the additional capital by issuing $850,000 face value of bonds with a coupon rate of 10%. In discussions with investment bankers, it was determined that to help the sale of the bonds, detachable stock warrants should be issued at the rate of 5 warrants for each $1,000 bond sold. The value of the bonds without the warrants is considered...
A company has just built a new factory to manufacture their widgets with a method they...
A company has just built a new factory to manufacture their widgets with a method they believe should be more efficient than their old method on a daily basis. To compare they recorded the number of widgets produced by the old factory for the last 9 days before it was shutdown and the first 8 days of the new factory's production. The company has reason to believe that daily production of widgets does not follow the normal distribution and have...
A company has just built a new factory to manufacture their widgets with a method they...
A company has just built a new factory to manufacture their widgets with a method they believe should be more efficient than their old method on a daily basis. To compare they recorded the number of widgets produced by the old factory for the last 8 days before it was shutdown and the first 9 days of the new factory's production. The company has reason to believe that daily production of widgets does not follow the normal distribution and have...
Management is trying to decide whether or not to build a new factory. They have estimated...
Management is trying to decide whether or not to build a new factory. They have estimated revenues of $90,000 in year one and $70,000 in years two through ten. In 10 years the factory is obsolete. They estimate expenses annually to operate the factory in years 2 through 10 would be $40,000. The cost of the new factory is $310,000 The payments required are $80,000 immediately with the remainder due in one year. The company uses an interest rate of...
A firm is evaluating whether to build a new factory. The proposed investment will cost the...
A firm is evaluating whether to build a new factory. The proposed investment will cost the firm $1 million to construct and provide cash savings of $200,000 per year over the next 10 years. (1) What rate of return does the investment offer? (2) What is the maximum risk-free rate under which the firm is willing to make this investment? (3) If the firm were to invest another $500,000 in the facility at the end of 5 years, it would...
A firm is evaluating whether to build a new factory. The proposed investment will cost the...
A firm is evaluating whether to build a new factory. The proposed investment will cost the firm $1 million to construct and provide cash savings of $200,000 per year over the next 10 years. (1) What rate of return does the investment offer? (2) What is the maximum risk-free rate under which the firm is willing to make this investment? (3) If the firm were to invest another $500,000 in the facility at the end of 5 years, it would...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT