In: Accounting
Task 2 Scenario Mega construction Plc, are contractors for replacement of a high technology factory for a multinational company. The total value of the contract is £ 3,500,000 over a three year period. The contract commenced on 1st March 2011, & the following details are available as at 28th February 2012
Material purchases | 65,000 | |
Material transfers in from other site | 28,000 | |
Material transfer out to another site. | 5,000 | |
Material on site, not yet used | 28,000 | |
Direct labour | 29,000 | |
Direct labour accrued | 3,500 | |
Indirect labour | 5,000 | |
Indirect labour accrued | 1,800 | |
Plant delivered to site | 60,000 | |
Hire of equipment’s | 27,000 | |
Hire charges owing | 8,400 | |
Head office charges | 58,000 | |
Cost of work yet not certified | 27,000 |
Mega Construction Plc, have received payment of £ 540,000 which
represent work certified as
completed by architects as at 28 February 2011, less a 15%
retention.
The company takes credits for three fourth of the profits on
work certified (less retention). The
plant is estimated to last the life of the contract, & no
residual value is expected.
2.1 Explain the principle of contract costing in construction
industry.
2.2 Calculate the attributable profit/ loss & value of work
certified.
2.3 Prepare contract cost statement for Mega Construction Plc. (40
marks
Answer: | |||
2.1 Principle of contract costing: Contract costing is a type of job costing in which contract constitutes a unit of cost. | |||
When contract costing is applied a separate no is given to each contract.costs are accumulated for each contract. | |||
This costing is used by companies engaged in building construction, civil engineering works and related works. | |||
The nature of expenses of contract costing is mainly consists of direct costs. The indirect costs mainly related to office and | |||
administrative costs. All direct costs like cost of material, direct labour etc are debited to contract account. | |||
If a plant is used for the contract approriate depreciation value should be debited to the contract account. | |||
If a contract extends to more than one year the outstanding expenses relating to the accounting year debited to the contract account. | |||
The Contract account is credited with work certified and uncertified but completed. | |||
The difference between the debit and credit siteresults in notional profit or loss. In case of loss the entire amount of loss is transferred to the | |||
profit and loss account but in case of profit only a part is transferred to profit and loss account. | |||
2.2 | |||
Value of Work Cerified | |||
Amount | |||
Payment received at the end of the first year which is 15% less than the value certified. | 540,000.00 | ||
Hence, The value of work certified ( 540000/85*100) | 635,294.12 | ||
2.3 : Contract Cost Statement | |||
Statement of Contract Account No…. | |||
Particulars | amount | Particulars | amount |
To Material Purchased | 65000.00 | By Material at site | 28000.00 |
To Material from other site | 28000.00 | By material transferred to another site | 5000.00 |
To Direct Labour | 29000.00 | By Work certified | 635294.12 |
To Direct labour accrued | 3500.00 | By Cost of Work not certified | 27000.00 |
To Hire of equipments | 27000.00 | ||
To Hire charges owing | 8400.00 | ||
To depreciation (60000/3) | 20000.00 | ||
To Balance C/d ( Notional Profit) | 514394.12 | ||
695294.12 | 695294.12 | ||
Note : As the life of the plant is 3 years with no residual value, | |||
the depreciation is 1/3rd of plant value of 60000. | |||
2.2 | |||
Attributable Profit & Loss | Amount | ||
Value of Notional Profit | 514394.12 | ||
Less : Cost of work not certified | 27000.00 | ||
value of Notional Profit on Work Certified | 487394.12 | ||
Less: Value of retention ( 635294.12-540000) | 95294.12 | ||
value of Notional Profit on Work Certified ( less retention) | 392100.00 | ||
As the company takes credits for 3/4 of the profits on work certified ( less retention), the value of attributable profit will be 3/4 of 412100 | 294075 | ||