In: Finance
Question 1 (6pts). For the cash flows shown below, answer the following questions. (Assume MARR = 12%) (1) (2pts) Provide the equation using PW to find the ROR of the cash flow given. (2) (2pts) Decide whether the project is acceptable or not using RATE function in MS Excel. Provide the screenshot (3) (2pts) Decide whether the project is acceptable or not using IRR function in MS Excel. Provide the screenshot
Year |
Factor |
Amounts |
0 |
Investment ($) |
1,200,000 |
1-10 |
Revenue ($ per year) |
300,000 |
1-10 |
M&O cost ($ per year) |
100,000 |
10 |
Salvage ($) |
400,000 |
Cash Flow for each year from 1 to 10 year = $ 200,000
(Revenue minus M & O Cost for every year)
Calculation of Net present value of the given project. Please refer the below table.
Year & Type of Cash flow |
Cashflow |
Discount Factor |
Discounted Cash Flow |
Initial Investment |
-$12,00,000 |
1.0000 |
-$12,00,000 |
1 |
$2,00,000 |
0.8800 |
$1,76,000 |
2 |
$2,00,000 |
0.7744 |
$1,54,880 |
3 |
$2,00,000 |
0.6815 |
$1,36,294 |
4 |
$2,00,000 |
0.5997 |
$1,19,939 |
5 |
$2,00,000 |
0.5277 |
$1,05,546 |
6 |
$2,00,000 |
0.4644 |
$92,881 |
7 |
$2,00,000 |
0.4087 |
$81,735 |
8 |
$2,00,000 |
0.3596 |
$71,927 |
9 |
$2,00,000 |
0.3165 |
$63,296 |
10 |
$2,00,000 |
0.2785 |
$55,700 |
Salvage realisation |
$4,00,000 |
0.2785 |
$1,11,400 |
Net Present Value |
-$30,401 |
Since net present value is negative (-$ 30401), the project should not be accepted.