Question

In: Finance

Use the following information to answer the next two questions. Consider the after-tax cash flows below:...

Use the following information to answer the next two questions.

Consider the after-tax cash flows below:

Year 0 1 2 3 4
Cash Flow -$75,000 $5,100 -$1,100 $498,000 -$272,000

The required rate of return is 12 percent.

Find an internal rate of return (IRR) for these cash flows.

Should you use the IRR you calculated in the previous question to decide whether the project is acceptable? Explain

show work please

Solutions

Expert Solution

There are negative cash flows in the middle year as well as towards the end. It is apparent that the project will have 2 IRRs with wide range.

IRR is the rate at which the sum of PV of all cash flows (Inflows & Outflows) = 0, or the discounting rate at which NPV = 0

Lets use trial and error and interpolation to get the desired value.

If IRR = 20%,

NPV = -75000/ (1+20%)^0 + 5100/(1+20%)^1 -1100/(1+20%)^2 + 498000/(1+20%)^3 - 272000/(1+20%)^4

= -75000 + 4250 - 764 + 288194 - 131173

= 85,508

If IRR = 40%,

NPV = -75000/ (1+40%)^0 + 5100/(1+40%)^1 -1100/(1+40%)^2 + 498000/(1+40%)^3 - 272000/(1+40%)^4

= -75000 + 3643 - 561 + 181487 - 70804

= 38765

If IRR = 60%,

NPV = -75000/ (1+60%)^0 + 5100/(1+60%)^1 -1100/(1+60%)^2 + 498000/(1+60%)^3 - 272000/(1+60%)^4

= -75000 + 3188 - 430 + 121,582 - 41504

= 7836

We are nearing to NPV = 0

If IRR = 70%,

NPV = -75000/ (1+70%)^0 + 5100/(1+70%)^1 -1100/(1+70%)^2 + 498000/(1+70%)^3 - 272000/(1+70%)^4

= -75000 + 3000 - 381 + 101364 - 32567

= -3584

Now IRR lies between 60% & 70%

If IRR = 65%,

NPV = -75000/ (1+65%)^0 + 5100/(1+65%)^1 -1100/(1+65%)^2 + 498000/(1+65%)^3 - 272000/(1+65%)^4

= -75000 + 3091 - 404 + 110861 - 36697

= 1850

Now IRR lies between 65% & 70%

We will now use interpolation to get the value

The interpolation formula looks like this:

y- y1 = ((y2-y1) / (x2-x1))* (x-x1)

IRR - 65 = ((70-65) /(-3850 - 1850)) *( 0-1850)

= 65 + (5/ -5700)*(-1850)

= 65 + 1.702

= 66.70%

For the other IRR, if we start with 0%

IRR = 0%

NPV = -75000/ (1+0%)^0 + 5100/(1+0%)^1 -1100/(1+0%)^2 + 498000/(1+0%)^3 - 272000/(1+0%)^4

= -75000 + 5100 - 1100 + 49800 - 272000

= 155000

We need to now move further towards negative value,

If IRR = -40%

NPV = -75000/ (1-40%)^0 + 5100/(1-40%)^1 -1100/(1-40%)^2 + 498000/(1-40%)^3 - 272000/(1-40%)^4

= -75000 + 8500 - 3056 + 2305556 - 2098765

= 13,725

If IRR = -50%

NPV = -75000/ (1-50%)^0 + 5100/(1-50%)^1 -1100/(1-50%)^2 + 498000/(1-50%)^3 - 272000/(1-50%)^4

= -75000 +10200 - 4400 + 3984000 - 4352000

= -437200

So IRR lies between - 40% & -50%

If IRR = -45%

NPV = -75000/ (1-45%)^0 + 5100/(1-45%)^1 -1100/(1-45%)^2 + 498000/(1-45%)^3 - 272000/(1-45%)^4

= -75000 +9273 - 3636 + 2993238 - 2972475

= - 48600

So IRR lies between - 40% & -45%

Lets now use interpolation to find the value

y- y1 = ((y2-y1) / (x2-x1))* (x-x1)

IRR - (-45) = ((-40-(-45)) /(13725- (-48600)) *( 0- (-13725)

= -45 + (5/185835) x 13725

= -45 + 1.307

= - 43.69% (This could be further approximated with few more iterations)

2. Clearly a negative IRR is what a business never looks at. And the positive IRR too looks unrealistic. A better way to find the value is to use MIRR method.

MIRR = (ΣFVCF / ΣPVCF) ^(1/n) -1

ΣFVCF = Sum of Future Value of all positive cash flows

FVCF = Cash Flow x ((1+ Investment Rate)^(Term of project - Year of CF))

ΣPVCF = Cash Flow / ((1+ Discount Rate)^(Year of CF))

ΣFVCF (Positive Cash flow)

= 5100 x (1+12%)^(4-1) + 498000 x (1+12%)^(4-3)

= 7165 + 557760

= 564925

ΣPVCF (Negative CF)

= 75000/ (1+12%)^0 + 1100/ (1+12%)^2 + 272000 / (1+12%)^4

= 75000 +877 +172861

= 248738

MIRR = (564925 / 248738)^(1/4) -1

= 2.2711^(1/4) - 1

= 1.2276 -1

= .2276

MIRR = 22.76%

In the above, discount rate and reinvestment rate are both taken at 12% (Required rate of return)

Since MIRR is greater than 12%, the project should be accepted


Related Solutions

Use the following information to answer the next three questions. Consider the cash flows from two...
Use the following information to answer the next three questions. Consider the cash flows from two mutually exclusive projects: Cash Flow Year Project A Project B 0 -$470,000 -$460,000 1 $120,000 $392,000 2 $210,000 $110,000 3 $375,000 $120,000 The appropriate discount rate is 11.7%. Calculate the net present value (NPV) for both projects, and determine which project should be accepted based on NPV. Round both NPVs to the nearest dollar. Calculate the internal rate of return (IRR) for both projects,...
Use the following information to answer the next three questions. Consider the following cash flows: Year...
Use the following information to answer the next three questions. Consider the following cash flows: Year Cash Flow 0 -$2,110,000 1 1,000,000 2 450,000 3 790,000 4 890,000 Assume a discount rate of 17.5 percent. What is the payback period? Round your answer to two decimal places. What is the net present value (NPV) rounded to the nearest dollar? What is the internal rate of return? please show work.
Use the following information to answer the next three questions. Consider the following cash flows: Year...
Use the following information to answer the next three questions. Consider the following cash flows: Year Cash Flow 0 -$2,110,000 1 1,000,000 2 450,000 3 790,000 4 890,000 Assume a discount rate of 17.5 percent. What is the payback period? Round your answer to two decimal places. What is the net present value (NPV) rounded to the nearest dollar? What is the internal rate of return? please show work
Use the following information to answer the next four questions. The cash flows for two mutually...
Use the following information to answer the next four questions. The cash flows for two mutually exclusive projects are shown in the following table. Investors require a 16% rate of return for each project. Year Cash Flows: Project S (in millions) Cash Flows: Project T (in millions) 0 -200 -200 1 -20 50 2 45 60 3 70 30 4 -10 -40 5 125 100 6 125 100 7 150 100 Find the profitability index for project S. Round intermediate...
Use the cash flows from the following two projects to answer the questions below. The firms...
Use the cash flows from the following two projects to answer the questions below. The firms required rate of return is 11%. Make sure to show all your computations. Year Project A Project B 0 -$200,000 -$200,000 1 $80,000 $100,000 2 $80,000 $100,000 3 $80,000 $100,000 4 $80,000 Assuming the firm’s required rate of return increases to 16% and that your firm only has $200,000 available to invest, which project of the two above would you chose if you used:...
Use the following information to answer the next four questions: Consider two municipalities, A and B,...
Use the following information to answer the next four questions: Consider two municipalities, A and B, in the same province. Residents in municipality A enjoy attending outdoor music concerts (a public good) held in their public park. Each resident in municipality A has a marginal benefit curve for these concerts given by MB=10-2Q, where Q is the number of outdoor concerts. There are 100 residents in this municipality. Residents in municipality B do not enjoy outdoor music concerts (they are...
Use the following information to answer the next Two questions : 2018 2017 Cash 15,000 14,000...
Use the following information to answer the next Two questions : 2018 2017 Cash 15,000 14,000 A/R 24,000 25,000 Inventory 79,000 78,000 Prepaid Insurance 5,000 4,000 Preoperty plant, & Equipment 35,000 30,000 Accumlated Depreciation (7,000) (5,000) Total Assets 151,000 146,000 Account Payable 6,000 9,000 Bonds Payable (mature in yr 2022 45,000 60,000 Common Stock 70,000 60,000 Retaind Earnings 30,000 17,000 Total Liabilities & Equity 151,000 146,000 Sunny Company had the following comparative balance sheet information for 2018, 2017: Sunny reported...
Use the following information to answer the next two questions: Stock                  Amount            &nb
Use the following information to answer the next two questions: Stock                  Amount                       Beta A                         25,000                         0.2 B                         20,000                         1.0 C                         30,000                         1.8 D                         25,000                         1.6 Risk-free rate is 3% and the market risk premium is 8% What is the required return for this portfolio?
Please use the following information to answer the next question: For BB Incorporated: Cash Flows from...
Please use the following information to answer the next question: For BB Incorporated: Cash Flows from Assets -------------------------------------------------------------------- 100 dollars EBIT (from 1999 INCOME STATEMENT) -------------------------------------------0 dollars Depreciation Expense (from 1999 INCOME STATEMENT) ---------------------- 0 dollars Taxes (from 1999 INCOME STATEMENT) ------------------------------------------ 0 Net Fixed Assets from BALANCE SHEET dated December 31, 1998-------------1400 dollars Net Fixed Assets from BALANCE SHEET dated December 31, 1999------------ 1300 dollars Additions to (Changes in) NWC for 1999 ---------------------------------------------- 0 dollars For KK Incorporated: Cash...
Use the information below to answer the next 3 questions: At the beginning of the year,...
Use the information below to answer the next 3 questions: At the beginning of the year, JJB Inc. estimated that overhead would be $880,000 and direct labor hours would be 220,000 hours. At the end of the year actual overhead was $920,600 and there were actual direct labor hours of 230,000. Year ended unadjusted COGS is $2,000,000. What is the Rredetermined Overhead Rate? $2.63 $4 $4.18 None of the above QUESTION 8 What is the overhead variance? $200 overapplied $400...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT