Question

In: Finance

You are considering constructing a new plant in a remote wilderness area to process the ore...

You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the plant will take a year to build and cost

$ 100

million upfront. Once? built, it will generate cash flows of

$ 16

million at the end of every year over the life of the plant. The plant will be useless

20

years after its completion once the mine runs out of ore. At that point you expect to pay

$ 220$220

million to shut the plant down and restore the area to its pristine state. Using a cost of capital of

13 %

a. What is the NPV of the? project?

b. Is using the IRR rule reliable for this? project? Explain.

c. What are the IRRs of this? project?

Solutions

Expert Solution

Year Amount PV Factor PV
0 -100 1 -100
1 16 0.885 14.16
2 16 0.783 12.53
3 16 0.693 11.088
4 16 0.613 9.81
5 16 0.543 8.69
6 16 0.480 7.68
7 16 0.425 6.8
8 16 0.376 6.02
9 16 0.333 5.33
10 16    0.295 4.72
11 16 0.261 4.18
12 16 0.231 3.7
13 16 0.204 3.26
14 16 0.181 2.9
15 16 0.160 2.56
16 16 0.141 2.26
17 16 0.125 2
18 16 0.111 1.78
19 16 0.098 1.57
20 -204 0.087 -17.75
TOTAL -6.712

The NPV of the project is -$6.712 millions. As the NPV is negative the project should not be accepted.

b. No, the IRR is not reliable for this project as the outflows are not only at the beginning of the year. When the cashflows change sign more than once than the IRR is not the correct way of assessing the project.

c. IRR is the rate at which outflows and inflows are equal. In this case the total outflow is 320 and also the total inflow is 320 (16*20). At the rate of 0% inflows and outflows would be equal. Therefore, IRR is 0%.


Related Solutions

You are considering constructing a new plant in a remote wilderness area to process the ore...
You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the plant will take a year to build and cost $100 million upfront. Once built, it will generate cash flows of $15 million at the end of every year over the life of the plant. The plant will be useless 20 years after its completion once the mine runs out of ore. At that point you...
You are considering constructing a new plant in a remote wilderness area to process the ore...
You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the plant will take a year to build and cost $120 million upfront. Starting in t=1, it will generate cash flows of $19 million at the end of every year over the life of the plant. The plant will be useless 20 years later, once the mine runs out of ore. In t=21 you expect to...
You are considering constructing a new plant in a remote wilderness area to process the ore...
You are considering constructing a new plant in a remote wilderness area to process the ore from a planned mining operation. You anticipate that the plant will take a year to build and cost $ 96 million upfront. Once​ built, it will generate cash flows of $ 16 million at the end of every year over the life of the plant. The plant will be useless 20 years after its completion once the mine runs out of ore. At that...
1. There is a small pool of oil in a remote wilderness area in a northern...
1. There is a small pool of oil in a remote wilderness area in a northern state. Geologists expect it to yield a net profit of $50 million at today’s prices for five years, and then fizzle out. Assume that $50 million can be taken immediately. Economists think the relative price of oil (and net profits) will rise at 4%, and the government has agreed to use a real discount rate of 3% for the oil project calculations. Environmentalists argue...
A company is in the process of constructing a new plant at a cost of $16...
A company is in the process of constructing a new plant at a cost of $16 million. It expects the project to generate cash flows of $9 million, $6 million, and $11 million over the next three years. The cost of capital is 18.9 percent p.a. What is the net present value of this project? (in millions to three decimals)
A company is considering constructing a plant to manufacture a proposed new product. The land costs...
A company is considering constructing a plant to manufacture a proposed new product. The land costs $350,000​, the building costs $500,000​, the equipment costs $250,000​, and $80,000 additional working capital is required. It is expected that the product will result in sales of $750,000 per year for 8 ​years, at which time the land can be sold for $350,000​, the building for $350,000​, and the equipment for $40,000.All of the working capital would be recovered at the EOY 8.The annual...
A company is considering constructing a plant to manufacture a proposed new product. The land costs...
A company is considering constructing a plant to manufacture a proposed new product. The land costs $300,000 the building costs $600,000 the equipment costs $250,000 and $100,000 additional working capital is required. It is expected that the product will result in sales of $750,000 per year for 10 years, at which time the land can be sold for $400,000, the building for $350,000, and the equipment for $50,000. All of the working capital would be recovered at the end of...
A company is considering constructing a new factory and is considering funding it by issuing a...
A company is considering constructing a new factory and is considering funding it by issuing a corporate bond to the value of $9m. The bond would have a term to maturity of 12 years, a coupon rate of 3.0% and the bond would be sold into the market at expected yield of 2.8%. Show how an immunisation portfolio could be constructed from the bonds below if the CB cut interest rates by 0.50% over the next year. Show how this...
You are considering opening a new plant. The plant will cost $103.9 million up front and...
You are considering opening a new plant. The plant will cost $103.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.5%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
You are considering opening a new plant. The plant will cost $97.9 million up front and...
You are considering opening a new plant. The plant will cost $97.9 million up front and will take one year to build. After that it is expected to produce profits of $30.4 million at the end of every year of production. The cash flows are expected to last forever. Calculate the NPV of this investment opportunity if your cost of capital is 7.8%. Should you make the​ investment? Calculate the IRR and use it to determine the maximum deviation allowable...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT