In: Finance
The treasurer of Amaro Canned Fruits, Inc., has projected the cash flows of Projects A, B, and C as follows: |
Year | Project A | Project B | Project C | ||||||
0 | −$ | 190,000 | −$ | 355,000 | −$ | 190,000 | |||
1 | 123,000 | 222,000 | 133,000 | ||||||
2 | 123,000 | 222,000 | 103,000 | ||||||
Suppose the relevant discount rate is 9 percent per year. |
a. |
Compute the profitability index for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.) |
b. |
Compute the NPV for each of the three projects. (Do not round intermediate calculations. Round your answers to 2 decimal places, e.g., 32.16.) |
c. |
Suppose these three projects are independent. Which project(s) should Amaro accept based on the profitability index rule? |
|
d. |
Suppose these three projects are mutually exclusive. Which project(s) should Amaro accept based on the profitability index rule? |
|
e. |
Suppose Amaro’s budget for these projects is $545,000. The projects are not divisible. Which project(s) should Amaro accept? |
|
a.
Computation of Profitability index:
Profitability index = Present value of future cash flows/Initial investment
Project A:
Profitability index = [($ 123,000/ (1+0.09) + ($ 123,000/ (1+0.09)2] /$ 190,000
= [($ 123,000/ (1.09) + ($ 123,000/ (1.09)2] /$ 190,000
= [($ 123,000/ (1.09) + ($ 123,000/1.1881)]/$ 190,000
= ($ 112,844.036697248 + $ 103,526.639171787)/ $ 190,000
= $ 216,370.675869035/$ 190,000 = 1.13879303088966 or 1.14
Project B:
Profitability index = [($ 222,000/ (1+0.09) + ($ 222,000/ (1+0.09)2] /$ 355,000
= [($ 222,000/ (1.09) + ($ 222,000/ (1.09)2] /$ 355,000
= [($ 222,000/ (1.09) + ($ 222,000/1.1881)]/$ 355,000
= ($ 203669.724770642 + $ 186852.958505176)/ $ 355,000
= $ 390,522.683275818/$ 355,000 = 1.1000638965516 or 1.10
Project C:
Profitability index = [($ 133,000/ (1+0.09) + ($ 103,000/ (1+0.09)2] /$ 190,000
= [($ 133,000/ (1.09) + ($ 103,000/ (1.09)2] /$ 190,000
= [($ 133,000/ (1.09) + ($ 103,000/1.1881)]/$ 190,000
= ($122,018.348623853 + $ 86,693.039306456)/ $ 190,000
= $ 208,711.387930309/$ 190,000 = 1.09848098910689 or 1.10
b.
Computation of NPV:
NPV = PV of future cash flows – Initial investment
Project A:
NPV = $ 216,370.675869035 - $ 190,000 = $ 26,370.675869035 or $ 26,370.68
Project B:
NPV = $ 390,522.683275818 - $ 355,000 = $ 35,522.683275819 or $ 35,522.68
Project C:
NPV = $ 208,711.387930309 - $ 190,000 = $ 18,711.387930309 or $ 18,711.39
c.
If the projects are independent, all three projects Project A, Project B, Project C are acceptable based on Profitability Index as all these projects have PI of more than 1.
d.
If projects are mutually exclusive, Project A should be accepted based on Profitability Index as Project A has highest PI.
e.
If Amaro’s budget for these projects is $ 545,000, Project B and Project A should be accepted.