Question

In: Finance

For independent projects, is it true that if PI>1.0, then NPV>0 and IRR>K? prove

For independent projects, is it true that if PI>1.0, then NPV>0 and IRR>K? prove

Solutions

Expert Solution

Assume that XYZ corporation is considering an investment of $50 million in a capital projcet that will return after tax cash flows of $16,000,000 per year for the next 4 years and anoth $20 million in year 5. the required rate of return in is 10%.

NPV = Present value of cash inflows - present value of cash outflows

NPV = 16 / ( 1.1)1 + 16 / ( 1.1)2 + 16 / ( 1.1)3 + 16 / ( 1.1)4 + 20 / ( 1.1)5 - 50

NPV = 14.545 + 13.223 + 12.021 + 10.928 + 12.418 - 50

NPV = $13.36 million

IRR is the rate of return that makes NPV equal to 0

NPV = 16 / ( 1 + R)1 + 16 / ( 1 + R)2 + 16 / ( 1 + R)3 + 16 / ( 1 + R)4 + 20 / ( 1 + R)5 - 50

Using trial and error method, let's try R as 19.52%

NPV = 16 / ( 1 + 0.1952)1 + 16 / ( 1 + 0.1952)2 + 16 / ( 1 + 0.1952)3 + 16 / ( 1 + 0.1952)4 + 20 / ( 1 + 0.1952)5 - 50

NPV = 0

Therefore, IRR is 19.52%

PI = present value of cash inflows / initial investment

PI = ( 14.545 + 13.223 + 12.021 + 10.928 + 12.418 ) / 50

PI = 1.26

Since PI of 1.26 is more than 1, IRR of 19.52% is more than K of 10% and NPV of 13.36 is greater than 0

it is true that if PI>1.0, then NPV>0 and IRR>K


Related Solutions

​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
​(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000​ and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 9 percent. The expected annual free cash inflows from each project are in the popup​ window: Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted.   ...
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B....
(​NPV, ​PI, and IRR calculations​) You are considering two independent​ projects, project A and project B. The initial cash outlay associated with project A is ​$50,000 and the initial cash outlay associated with project B is ​$70,000 The required rate of return on both projects is 12 percent. The expected annual free cash inflows from each project are in the popup​ window: .Calculate the NPV​, PI​, and IRR for each project and indicate if the project should be accepted. a....
Build a case on any company’s new projects calculate the NPV , IRR , and PI...
Build a case on any company’s new projects calculate the NPV , IRR , and PI and say if it’s a good project or not
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required...
Compute the IRR, NPV, PI, and payback period for the following two projects. Assume the required return is 12%. Cashflow for each year Project A : Year 0= -2500 Year 1=900 Yaer 2=800 Year 3=1600 Year 4=100 Yaer 5=50 Year 6= 300 Project B Year 0 =-2500 Year 1=50 Year2= 600 Year 3=150 Year 4=900 Year 5= 500 Year 6=2500
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the...
What is NPV, IRR, PI, MIRR of a project with the following cash flows if the discount rate is 14 percent? Year CF 0 -18,000    1 5000 2 7500 3 8400 4 2100 Also upload your excel files showing your work.
In capital budgeting, the NPV method is preffered to other alternativessuch as PI or IRR. What...
In capital budgeting, the NPV method is preffered to other alternativessuch as PI or IRR. What is the justification? A. Financial management seeks to maximize firm's profit margin. B. Financial management seeks to maximize firm's market value. c. Financial management seeks to maximize firm's price earning ratio D. Financial management seeks to maximize firm's ROE
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For...
. For each project, calculate the NPV, IRR, profitability index (PI) and the payback period. For each capital budgeting decision tool, indicate if the project should be accepted or rejected, assuming that each project is independent of the others. Important Note: The venture capital folks have a firm maximum payback period of four years.          Project A= Required rate of Return= 16.30% Project B= R= 12.50% Project C= R= 15.35% Project D= R= 17.25%      Expected cash flows for the four...
NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of...
NPV,​ PI, and IRR calculations​) You are considering a project with an initial cash outlay of ​$70,000 and expected free cash flows of ​$28,000 at the end of each year for 6 years. The required rate of return for this project is 7 percent. a. What is the​ project's payback​ period? b. What is the​ project's NPV​? c. What is the​ project's PI​? d. What is the​ project's IRR​?
1(a). When NPV=0, then: Select one: a. IRR less than 0 b. IRR=required return c. IRR...
1(a). When NPV=0, then: Select one: a. IRR less than 0 b. IRR=required return c. IRR greater than 0 d. IRR greater than required return e. IRR=0 1(b). The relationship between NPV of a project and the required rate of return is: Select one: a. positive b. random c. negative d. determined by the relationship of NPV to IRR e. none of the answers is correct
a) Is it possible for conflicts to exist between the NPV and the IRR when independent...
a) Is it possible for conflicts to exist between the NPV and the IRR when independent projects are being evaluated? Explain your answer. (150 words) b) If the payback was the only method a firm used to accept or reject projects, what payback should it choose as the cutoff point, that is, reject projects if their paybacks are not below the chosen cutoff? Is your selected cutoff based on some economic criteria, or is it more or less arbitrary? Are...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT