In: Finance
Project Y has following cash flows: C 0 = -800, C 1 = +5,000, and C 2 = -5,000. Calculate the IRRs for the project.
|
25 percent and 400 percent. |
||
|
125 percent and 500 percent. |
||
|
-44 percent and 11.6 percent. |
||
|
No IRRs exist for this project. |
| Year | Cash flow | × factor@ 25.00% | Present value |
| 0 | $ (800.00) | 1.0000 | $ (800.00) |
| 1 | $ 5,000.00 | 0.8000 | $ 4,000.00 |
| 2 | $ (5,000.00) | 0.6400 | $ (3,200.00) |
| $ - | |||
| $ - | |||
| NPV | 1.4400 | $ - |
| Year | Cash flow | × factor@ 400.00% | Present value |
| 0 | $ (800.00) | 1.0000 | $ (800.00) |
| 1 | $ 5,000.00 | 0.2000 | $ 1,000.00 |
| 2 | $ (5,000.00) | 0.0400 | $ (200.00) |
| $ - | |||
| $ - | |||
| NPV | 0.2400 | $ - |
Answer is:
|
25 percent and 400 percent. |
| please rate. |