Question

In: Finance

Project Y has following cash flows:  C 0 = -800,  C 1 = +5,000, and  C 2 = -5,000....

Project Y has following cash flows:  C 0 = -800,  C 1 = +5,000, and  C 2 = -5,000. Calculate the IRRs for the project.

25 percent and 400 percent.

125 percent and 500 percent.

-44 percent and 11.6 percent.

No IRRs exist for this project.

Solutions

Expert Solution

Year Cash flow × factor@ 25.00% Present value
0 $            (800.00) 1.0000 $                 (800.00)
1 $          5,000.00 0.8000 $                4,000.00
2 $        (5,000.00) 0.6400 $              (3,200.00)
$                            -  
$                            -  
NPV 1.4400 $                            -  
Year Cash flow × factor@ 400.00% Present value
0 $            (800.00) 1.0000 $                 (800.00)
1 $          5,000.00 0.2000 $                1,000.00
2 $        (5,000.00) 0.0400 $                 (200.00)
$                            -  
$                            -  
NPV 0.2400 $                            -  

Answer is:

25 percent and 400 percent.

please rate.

Related Solutions

A hospital’s project has the following expected cash flows Year Cash flow 0 ($5,000) 1 $1,000...
A hospital’s project has the following expected cash flows Year Cash flow 0 ($5,000) 1 $1,000 2 $2,000 3 $3,000 If the cost of capital is 12%, should the project be undertaken? Show your calculations
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2...
A project has the following cash flows : Year Cash Flows 0 −$12,000 1 5,290 2 7,630 3 5,040 4 −1,580 Assuming the appropriate interest rate is 10 percent, what is the MIRR for this project using the discounting approach? 19.21% 15.23% 13.96% 11.63% 17.77%
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2...
A project has the following cash flows : Year Cash Flows 0 −$11,700 1 5,110 2 7,360 3 4,800 4 −1,640 Assuming the appropriate interest rate is 7 percent, what is the MIRR for this project using the discounting approach?
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800...
A project has the following cash flows: Year Cash Flows 0 −$127,800 1 47,000 2 63,800 3 51,600 4 28,100 The required return is 8.3 percent. What is the profitability index for this project?
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2...
A project has the following cash flows: Year Cash Flow 0 –$ 16,100 1 6,800 2 8,100 3 6,600 What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.) NPV $ What is the NPV at a discount rate of 11 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ What is the NPV...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2...
A project has the following cash flows: Year Cash Flow 0 $ 73,000 1 –54,000 2 –27,600 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2...
A project has the following cash flows:    Year Cash Flow 0 $64,100 1 –30,100 2 –48,100    a. What is the IRR for this project?    b. What is the NPV of this project, if the required return is 11.5 percent?    c. NPV at 0 percent?    d. NPV at 23 percent?
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2...
A project has the following cash flows: Year Cash Flow 0 –$ 15,600 1 6,300 2 7,600 3 6,100     What is the NPV at a discount rate of zero percent? (Do not round intermediate calculations and round your answer to the nearest whole number, e.g., 32.)      NPV $       What is the NPV at a discount rate of 9 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)      NPV $   ...
Project Y Time    Cash Flow 0    -5,000 1 500 2 2000 3    3000...
Project Y Time    Cash Flow 0    -5,000 1 500 2 2000 3    3000 4 1500 5    500 Compute the discounted payback statistic for Project Y and recommend whether the firm should accept or reject the project with the cash flows shown in the table if the appropriate cost of capital is 12 percent and the maximum allowable discounted payback is 3.5 years. A. 3.00 years, accept B. 3.45 years, accept C. 3.86 years, accept D. 3.45...
A project has the following cash flows. What is the payback period? Year 0 1 2...
A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 cash flow -$14500 $2200 $4800   $6500 $7500 A project has the following cash flows. What is the internal rate of return? Year 0 1 2 3 Cash flows -$89300 $32900 $64200 $5800 A project has the following cash flows. What is the payback period? Year 0 1 2 3 4 Cash flow -$28000 $11600 $11600 $6500 $6500 And how to solve this...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT