Q3 (a) Figure Q3 (a) shows a cantilever beam which is carry a
load P at point C.
(i) Sketch the deflection curve of the beam.
(ii) Derive the bending moment deflection, slope deflection and
deflection equation at b-b using Double Integration Method.
(iii) Calculate the maximum deflection. Given: L= 10 m, a= 3m, P=
25 kN. EI is constant
(b) Figure Q3 (b) shows a solid steel spindle AB that has a diameter ??=38 mm. The allowable shearing stress of the spindle is 84 MPa, while sleeve CD is made of a brass with an allowable shearing stress of 50MPa. Determine the largest torque (T), that can be applied at A.
In: Civil Engineering
Explain why the stiffness of a discontinuous fiber composite is less than that of a continuous fiber composite with the same constituents and same proportion of reinforcement.
In: Civil Engineering
How to obtain peak deviator stress from the three triaxial tests plotted on a graph? HINT.
In: Civil Engineering
A monolithic reinforced concrete floor is to be composed of rectangular bays measuring 6 m x 7.5 m. The floor is to designed to carry a service live load of 5 KPa, floor finish of 1.5 KPa, and ceiling load of 1 KPa, in addition to its own weight.
Design the corner floor panel slab using fc’=21 MPa, fy = 400 MPa, and concrete unit weight of 23.54 KN/m3.
?? ?ℎ??? ???? ???????????, ?????? ?ℎ? ???? ????, ??? ??????? ?ℎ? ??????? ?????????y
In: Civil Engineering
A water treatment plant is designed for a constant flow rate of
3 MGD. The flocculation system consists of three tanks, each having
a water depth of 10 ft and an average hydraulic residence time
(HRT) of 30 min.
(a) Determine the dimension of each tank (i.e., width and
length).
(b) Determine whether the flow through velocity is acceptable.
(c) The plant is planning to take one tank out of service for
maintenance. Determine the increase in power requirement in the
remaining two units to maintain the average velocity gradient (G)
of 40 sec-1.
In: Civil Engineering
Summarise the cement production process.
In: Civil Engineering
arrive the cross section of a plate girders for railway bridge with effective span of 30m and dead load on the open floor 7.5 KN/m . equivalent total load for BM calculation per track is 2727KN and for shear is2927 kN
In: Civil Engineering
Compare the following risks: Preventable risks, Strategy risks, and External risks.
subject : risk management is construction
In: Civil Engineering
Based on the Engineering Case Study on Highland Towers Collapsed, answer the following questions;
a) Explain the factors contributing to the collapse of the building.
b) Explain Highland Properties engineer’s misconduct and relate it to the BEM Code of professional conduct.
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering
You have been asked to review the performance of a
combination
solution gas, gas-cap drive reservoir. Well test and log
information show
that the reservoir initially had a gas cap half the size of the
initial oil
volume. Initial reservoir pressure and solution gas-oil ratio were
2500 psia
and 721 SCF/STB, respectively. Using the volumetric approach,
initial oil in place was found to be 56 MM STB. As you proceed with
the
analysis, you discover that your boss has not given you all the
data you
need to make the analysis. The missing information is that at some
point
in the life of the project a pressure maintenance program was
initiated
using gas injection. The time of the gas injection and the total
amount of
gas injected are not known. There was no active water drive or
water
production. PVT and production data are in the following
table:
a) At what point (i.e., pressure) did the pressure
maintenance program
begin?
b) How much gas in SCF had been injected when the
reservoir pressure is
500 psia? Assume that the reservoir gas and the injected gas have
the
same compressibility factor.
In: Civil Engineering
In: Civil Engineering
In: Civil Engineering