Talk about and explain what types of procedures can be implemented to improve project management for watershed investigations when using Computer software technology such as GIS/Remote Sensing.
In: Civil Engineering
The operator of a rock quarry is invited to bid on furnishing 42,000 cy of crushed aggregate for a job. The aggregate will be delivered to the job, which is 27 miles from the quarry. The aggregate will be loaded into trucks by a loader that can load at a rate of 75 cy/hr. The trucks will haul 18 cy/load at an average speed of 50 mi./hr loaded and 55 mi./hr empty. The estimated time to dump a load is 5 min. Assume a 45 min. effective hour for the loading and hauling operation.
The cost information for the job is: Royalty paid for aggregate
= $1.35/cy Overhead = $0.75/cy Profit = $1.20/cy Loader = $85.00/hr
Operator = $32.00/hr Trucks, each = $55.00/hr Truck driver, each =
$28.00/hr Foremen = $35.00/hr
a) How many trucks are required? b) What resource dictates project duration. c) What should be the bid price per cubic yard using the economic way to conduct the project?
In: Civil Engineering
1- Sketch a typical atmospheric pressure steam curing cycle identifying the main steps and
requirements for each step.
2- What is meant by the characteristic strength of concrete?
3- Compressive strength specimens could be cured by standard curing method or on site
beside the concrete elements. What is meant by standard curing? Explain when each curing
4- Discuss the effect of curing, time and temperature, on compressive strength of concrete.
State the minimum moist curing period according to ACI 308.
method is used.
In: Civil Engineering
In: Civil Engineering
do a comparative essay between Casa Mila and Casa Batllo of the architect Antoni Gaudi. In this essay you are to look at the similarities and differences of architectural design principles applied. You are to identify at least four principles and to justify their application by the architect through the two buildings.
In: Civil Engineering
Based on the microstructure of wood, explain the mechanisms responsible for retention of water within the structure of wood.
In: Civil Engineering
A product improvement project involves an existing product (M), with minor complexity (C), and is dependent for schedule on an existing system (D). (reference Risk Assessment Calculations document, Likelihood table).
Consider that criteria are weighted as follows:
M is (0.5), C is (0.3), D is (0.2)
Calculate the Composite Likelihood Factor (CLF).
W1= 0.5, W2=0.3, W3=0.2
(CLF) = W1 * M + W2 * C + W3 * D = 0.5 * 0.1 + 0.3 * 0.3 + 0.2 * 0.3 = 0.05 + 0.09 + 0.06 = 0.20
A product test failure is expected to have a minor impact on overall technical performance and be correctable within 2 months at a cost of 10 percent. (reference Risk Assessment Calculations document, Impact table).
Consider that criteria are weighted as follows:
TI is Moderate (0.5), CI is Minor (0.3), SI is Low (0.2)
Calculate the Composite Impact Factor (CIF).
Using the previous problems #1 Risk Likelihood (CLF) and #2 Risk Impact (CIF), calculate the Risk Consequence Rating (RCR).
In: Civil Engineering
(1) A simply supported steel beam is 30' long and subjected to a uniform distributed 1.3 kips per foot. What is the minimum required section modulus for this beam if we do not want its maximum stress to exceed 50 ksi?
(2) What is the minimum inertia of the beam in the previous question if we do not want it to deflect more than 1/2" ?
In: Civil Engineering
CONSTRUCTION PROJECT MANAGEMENT
From the late 1800s to the mid-1900s unions fought for and won improvements for labor which were later adopted by government laws and regulations for all workers. Which part of labor law and regulation was not originally won by unions:
Mandated overtime after a 40 hour work week |
||
Safety regulations |
||
Equal opportunity and affirmative action |
||
Pension regulations |
In: Civil Engineering
The results of torsion test on two shafts are shown in the figure. The top shaft shows the torsion failure in the cast iron which is a brittle material and the bottom figure is the test result in a shaft made of ductile steel. Considering the fact that brittle material are controlled by tension (fail in tension) and ductile materials are controlled by shear stress (fail in shear), explain why the brittle cast iron has a 45 degree fracture surface, while the ductile steel shaft has a flat fracture surface. Provide detailed logic based on stress transformation.
In: Civil Engineering
Question:
In: Civil Engineering
A six lane urban freeway (three lanes in each direction) in mountainous terrain has 10-ft lanes and obstructions 5 ft from the right edge. For every mile of freeway, there is one interchange. The traffic stream consists of mostly commuters with a peak hour factor of 0.84, peak hour volume of 2500 vehicles, and 4% recreational vehicles. What is the LOS? Assume base free flow speed of 70 mph
In: Civil Engineering
Problem 3 A column supports a roof and a second floor. The loads that act on the column are shown below. Using the ASCE 7 load combinations determine the factored design load in the column just above the second floor and the factored design load in the column just above the foundation. Show all load combination calculations and identify the controlling load combination and resulting load values at each design location. ( “ - “ load : indicates it is going away from the diaphragm surface)
Service Loads:
Roof Live Load 5.5 kip
Snow Load 6 kip
Roof Vertical Wind Load - 2.5 kip
Roof Horizontal Wind Load 9.2 kip
Roof Vertical Earthquake Load ±1.5 kip
Roof Horizontal Earthquake Load 9 kip
Roof Dead Load Maximum 3.5 kip
Roof Dead Load Minimum 2.75 kip
Live Load 9 kip
2 nd Floor Vertical Earthquake Load ±3.5 kip
2 nd Floor Horizontal Earthquake Load 20 kip
2 nd Floor Horizontal Wind Load 8 kip
2 nd Floor Dead Load Maximum 7 kip
2 nd Floor Dead Load Minimum 7 kip
In: Civil Engineering
Problem 2: A simple roof beam with a span 30 ft has a tributary width of 5 ft. The nominal loads that act on the roof system are shown below. Using the ASCE 7 Strength Design load combinations determine the factored design load in the beam (plf). Show all load combination calculations and identify the controlling load combination and resulting design values for positive and negative moment (±Mu) and shear (Vu).
Nominal Loads
Roof Live Load 20 psf
Snow Load 26 psf
Roof Vertical Wind Load -16psf
+5 psf
Roof Rain Load 12 psf
Roof Vertical Earthquake Load ±8 psf
Roof Dead Load Maximum 25 psf
Roof Dead Load Minimum 18 psf
In: Civil Engineering
Which of the following are stormwater management principles?
Select one:
a. Maintain water cycle balance
b. Disconnect. Decentralize. Distribute.
c. Integrate early into site design process
d. Protect/utilize natural systems
e. All of the other answers are correct.
In: Civil Engineering