In: Accounting
Constructing and Assessing Income Statements Using
Cost-to-Cost Method
Assume General Electric Company agreed in May 2016 to construct a
nuclear generator for NSTAR, a utility company serving the Boston
area. General Electric Company estimated that its construction
costs would be $360 million. The contract price of $450 million is
to be paid as follows: $150 million at the time of signing; $150
million on December 31, 2016; and $150 million at completion in May
2017. General Electric incurred the following costs in constructing
the generator: $144 million in 2016 and $216 million in 2017.
a. Compute the amount of General Electric's revenue, expense, and
income for both 2016 and 2017, and for both years combined, under
the cost-to-cost revenue recognition method.
Enter dollar amounts in millions.
Cost-to-Cost Method | ||||
---|---|---|---|---|
Year |
Costs incurred |
% of total excepted costs |
Revenue recognized |
Income |
2016 | Answer | Answer | Answer | Answer |
2017 | Answer | Answer | Answer | Answer |
Total | Answer | Answer | Answer |
a. Compute the amount of General Electric's revenue, expense, and income for both 2016 and 2017, and for both years combined, under the cost-to-cost revenue recognition method.
.
Cost-to-Cost Method |
||||
Year |
Costs incurred |
% of total excepted costs |
Revenue recognized |
Income |
2016 |
$144 |
40% |
$180 |
$36 |
2017 |
$216 |
60% |
$270 |
$54 |
Total |
$360 |
$450 |
$90 |
.
Working
The contract price of $450 million
Year |
Costs incurred |
% of total excepted costs |
Revenue recognized |
Income |
2016 |
$144 |
144 / 360 = 0.40 = 40% |
450 * 40% = 180 |
180 - 144 =36 |
2017 |
$216 |
216 / 360 = 0.60 =60% |
450 * 60% = 270 |
270-216 =54 |
Total |
$360 million |
450 million |
90 million |
.
* The formula for the cost to cost method is to divide all costs recorded up to date on a construction project by the total estimated amount of costs that will be incurred for that project.
The result is an overall percentage of completion that is then used for billing and revenue recognition purposes, the deduct previously recognized to calculate current period recognition .