In: Accounting
Managers at Wager Fabricating Company are reviewing the economic
feasibility of manufacturing a part that the currently purchases
from a supplier. Forecasted annual demand for the part is 3200
units. Wagner operates 250 days per year.
Wagner's financial analysts have established a cost of capital of
14% for the use of funds for investments within the company. In
addition, over the past year $600,000 was the average investment in
the company's inventory. Accounting information shows that a total
of $24,000 was spent on taxes and insurance related to the
company's inventory. In addition, an estimated $9000 was lost due
to inventory shrinkage, which included damaged goods as well as
pilferage. A remaining $15,000 was spent on warehouse overhead,
including utility expenses for heating and lighting.
An analysis of the purchasing operation shows that approximately
two hours are required to process and coordinate an order for the
part regardless of the quantity ordered. Purchasing salaries
average $28 per hour, including employee benefits. In addition, a
detailed analysis of 125 orders showed that $2375 was spent on
telephone, paper, and postage directly related to the ordering
process.
A one-week lead time is required to obtain the part from the
supplier. An analysis of demand during the lead time shows it is
approximately normally distributed with a mean of 64 units and a
standard deviation of 10 units. Service-level guidelines indicate
that one stock-out per year is acceptable.
Currently, the company has a contract to purchase the part from a
supplier at a cost of $18 per unit. However, over the past few
months, the company's production capacity has been expanded. As a
result, excess capacity is now available in certain production
departments, and the company is considering the alternative of
producing the parts itself.
Forecasted utilization of equipment shows that production capacity
will be available for the part being considered. The production
capacity is available at the rate of 1000 units per month, with up
to five months of production time available. Management believes
that with a two-week lead time, schedules can be arranged so that
the part can be produced whenever needed. The demand during the
two-week lead time is approximately normally distributed, with a
mean of 128 units and a standard deviation of 20 units. Product
costs are expected to be $17 per part.
A concern of management is that setup costs will be substantial.
The total cost of labor and lost production time is estimated to be
$50 per hour, and a full eight-hour shift will be needed to set up
the equipment for producing the part.
Managerial Report
Develop a report for management of Wagner Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself. Include the following factors in your report:
1. An analysis of the holding costs, including the appropriate annual holding cost rate
2. An analysis of ordering costs, including the appropriate cost per order from the supplier
3. An analysis of setup costs for the production operation
4. A development of the inventory policy for the following two alternatives:
a. Ordering a fixed quantity Q from the supplier
b. Ordering a fixed quantity Q from in-plant production
5. Include the following in the policies of parts 4(a) and 4(b):
a. Optimal quantity Q*
b. Number of order or production runs per year
c. Cycle time
d. Reorder point
e. Amount of safety stock
f. Expected maximum inventory
g. Average inventory
h. Annual holding cost
i. Annual ordering cost
j. Annual cost of units purchased or manufactured
k. Total annual cost of the purchase policy and the total annual cost of the production policy
6. Make a recommendation as to whether the company should purchase or manufacture the part. What savings are associated with your recommendation as compared with the other alternative?
ANSWER
_____________________________________________
If you have any query or any Explanation please ask me in the comment box, i am here to helps you.please give me positive rating.
*****************THANK YOU**************