Question

In: Economics

Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost...

Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost is $150,000 and the O&M costs are $5000 per year. There is no salvage value after 20 years. Time savings to users are worth $35,000 per year, and neighborhood disruption is a disbenefit of $10,000 per year. Is this project attractive?

Solutions

Expert Solution

Question

First cost = $150,000

Annual O&M cost = $5,000

Calculate the PW of annual O&M cost -

PW = Annual O&M cost(P/A, i, n)

PW = $5,000(P/A, 5%, 20)

PW = $5,000 * 12.4622

PW = $62,311

The PW of annual O&M cost is $62,311

Annual benefits = $35,000

Calculate the PW of annual benefits -

PW = Annual benefits(P/A, i, n)

PW = $35,000(P/A, 5%, 20)

PW = $35,000 * 12.4622

PW = $436,177

The PW of annual benefits is $436,177

Annual disbenefits = $10,000

Calculate the PW of annual disbenefits -

PW = annual disbenefit (P/A, i, n)

PW = $10,000(P/A, 5%, 20)

PW = $10,000 * 12.4622

PW = $124,622

The PW of annual disbenefit is $124,622

calculate the benefit/cost ratio -

B/C ratio = [PW of benefit - PW of disbenefits]/[First cost + PW of O&M costs]

B/C ratio = [436,177 - 124,622]/[150,000 + 62,311]

B/C ratio = 311,555/212,311

B/C ratio = 1.47

The B/C ratio is 1.47

When B/C ratio is equal to or greater than 1, project can be selected.

So,

This project is attractive and should be executed.


Related Solutions

Considering discount rate of 14%, calculate NPV, Benefit Cost Ratio, and Present Value Ratio for the...
Considering discount rate of 14%, calculate NPV, Benefit Cost Ratio, and Present Value Ratio for the following investment and explain if it is a good investment. C=10,000 C=8,000 C=6,000 I=7,500 I=7,500 ... I=7,500 L=10,000 0 1 2 3 4 ... 10 C: Cost, I:Income, L: Salvage value
Benefit-Cost Analysis Given Parameters: Scenario One Benefit-Cost Ratio: 1.11 Scenario Two Benefit-Cost Ratio: 0.52 Did your...
Benefit-Cost Analysis Given Parameters: Scenario One Benefit-Cost Ratio: 1.11 Scenario Two Benefit-Cost Ratio: 0.52 Did your benefit-cost analysis reach the same or different conclusions in the two scenarios analyzed? If different conclusions, why? Assume that the proposal in fact “passed” the analysis with a benefit-cost ratio greater than 1. Does this imply that the proposed project is the optimal or best use for the $8.55 million to be invested in resource conservation? Explain. In conducting benefit-cost analyses, do you think...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV? Parameter Pessimistic Most Likely Optimistic Fist cost 150000 100000 80000 Annual benefit 25000 45000 50000 Project life 5 7 9
Use the following table solve the Benefit Cost Ratio , NPV benefits ( Please show excel...
Use the following table solve the Benefit Cost Ratio , NPV benefits ( Please show excel formulas) Discount rate 0.08 0 1 2 3 System A Costs Hardware 14000 3000 3000 3000 Software 12000 2000 2000 1000 Services 2500 2500 2500 2500 Benefits Increased productivity 15000 10000 5000 Lower Error rates 18000 5000 6000 System B Costs Hardware 15000 3000 3000 3000 Software 12000 4000 2000 5000 Services 7000 3000 3000 1000 Benefits Increased productivity 7000 10000 10000 Reduced Work...
A project manager decided to use critical ratio (C/Rij for WP j of project i) to...
A project manager decided to use critical ratio (C/Rij for WP j of project i) to prioritize and schedule the remaining work packages to be done for three concurrent projects with the data in the table below. The technical sequence (precedence) are WP1>WP2>WP4>WP4, for each of the three projects. For an illustration, the first project is due by day 4. Its first work package requires 2 days at workstation 1. Project ID Due Date Processing time for WP1 Processing time...
explain project cost-benefit analysis?
explain project cost-benefit analysis?
There are two ways for finding the benefit to cost ratio (B/C Ratio) B/C Ratio =...
There are two ways for finding the benefit to cost ratio (B/C Ratio) B/C Ratio = [ Annual Benefits-Annual Disbenefits] / [Annual Cost of Implementing Project] B/C Ratio = [NPV of Benefits-NPV of Disbenefits] / [NPV of Implementing Project] If the B/C Ratio is greater than one, we can infer that the project is worth undertaking. Note that there can only be one B/C ratio for a project (unlike IRR which can at times have multiple values) Problem: The City...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i =...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i = 12% and n = infinity, then the net present worth of this project is most nearly: a) 20.84 b) 41.67 c) 30.25 d) 50.00 e) 22.40 f) No correct answer above
A DOT is performing a benefit-cost analysis of a new highway using an analysis period of...
A DOT is performing a benefit-cost analysis of a new highway using an analysis period of 40 years as part the required environmental impact assessment of the project. The section of highway is estimated to have a construction cost $220 million dollars. The public benefit in reduced travel time and economic development around the highway is estimated to be $17 million per year for the first 5 years, then decrease by 3% per year for the remainder of the 40...
Use the following table solve the Benefit Cost Ratio , NPV benefits (Please show excel formulas...
Use the following table solve the Benefit Cost Ratio , NPV benefits (Please show excel formulas as well) Discount rate 0.08 0 1 2 3 System A Costs Hardware 14000 3000 3000 3000 Software 12000 2000 2000 1000 Services 2500 2500 2500 2500 Benefits Increased productivity 15000 10000 5000 Lower Error rates 18000 5000 6000 System B Costs Hardware 15000 3000 3000 3000 Software 12000 4000 2000 5000 Services 7000 3000 3000 1000 Benefits Increased productivity 7000 10000 10000 Reduced...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT