Question

In: Economics

Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost...

Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost is $150,000 and the O&M costs are $5000 per year. There is no salvage value after 20 years. Time savings to users are worth $35,000 per year, and neighborhood disruption is a disbenefit of $10,000 per year. Is this project attractive?

Solutions

Expert Solution

Question

First cost = $150,000

Annual O&M cost = $5,000

Calculate the PW of annual O&M cost -

PW = Annual O&M cost(P/A, i, n)

PW = $5,000(P/A, 5%, 20)

PW = $5,000 * 12.4622

PW = $62,311

The PW of annual O&M cost is $62,311

Annual benefits = $35,000

Calculate the PW of annual benefits -

PW = Annual benefits(P/A, i, n)

PW = $35,000(P/A, 5%, 20)

PW = $35,000 * 12.4622

PW = $436,177

The PW of annual benefits is $436,177

Annual disbenefits = $10,000

Calculate the PW of annual disbenefits -

PW = annual disbenefit (P/A, i, n)

PW = $10,000(P/A, 5%, 20)

PW = $10,000 * 12.4622

PW = $124,622

The PW of annual disbenefit is $124,622

calculate the benefit/cost ratio -

B/C ratio = [PW of benefit - PW of disbenefits]/[First cost + PW of O&M costs]

B/C ratio = [436,177 - 124,622]/[150,000 + 62,311]

B/C ratio = 311,555/212,311

B/C ratio = 1.47

The B/C ratio is 1.47

When B/C ratio is equal to or greater than 1, project can be selected.

So,

This project is attractive and should be executed.


Related Solutions

Considering discount rate of 14%, calculate NPV, Benefit Cost Ratio, and Present Value Ratio for the...
Considering discount rate of 14%, calculate NPV, Benefit Cost Ratio, and Present Value Ratio for the following investment and explain if it is a good investment. C=10,000 C=8,000 C=6,000 I=7,500 I=7,500 ... I=7,500 L=10,000 0 1 2 3 4 ... 10 C: Cost, I:Income, L: Salvage value
Benefit-Cost Analysis Given Parameters: Scenario One Benefit-Cost Ratio: 1.11 Scenario Two Benefit-Cost Ratio: 0.52 Did your...
Benefit-Cost Analysis Given Parameters: Scenario One Benefit-Cost Ratio: 1.11 Scenario Two Benefit-Cost Ratio: 0.52 Did your benefit-cost analysis reach the same or different conclusions in the two scenarios analyzed? If different conclusions, why? Assume that the proposal in fact “passed” the analysis with a benefit-cost ratio greater than 1. Does this imply that the proposed project is the optimal or best use for the $8.55 million to be invested in resource conservation? Explain. In conducting benefit-cost analyses, do you think...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...
The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV? Parameter Pessimistic Most Likely Optimistic Fist cost 150000 100000 80000 Annual benefit 25000 45000 50000 Project life 5 7 9
Use the following table solve the Benefit Cost Ratio , NPV benefits ( Please show excel...
Use the following table solve the Benefit Cost Ratio , NPV benefits ( Please show excel formulas) Discount rate 0.08 0 1 2 3 System A Costs Hardware 14000 3000 3000 3000 Software 12000 2000 2000 1000 Services 2500 2500 2500 2500 Benefits Increased productivity 15000 10000 5000 Lower Error rates 18000 5000 6000 System B Costs Hardware 15000 3000 3000 3000 Software 12000 4000 2000 5000 Services 7000 3000 3000 1000 Benefits Increased productivity 7000 10000 10000 Reduced Work...
There are two ways for finding the benefit to cost ratio (B/C Ratio) B/C Ratio =...
There are two ways for finding the benefit to cost ratio (B/C Ratio) B/C Ratio = [ Annual Benefits-Annual Disbenefits] / [Annual Cost of Implementing Project] B/C Ratio = [NPV of Benefits-NPV of Disbenefits] / [NPV of Implementing Project] If the B/C Ratio is greater than one, we can infer that the project is worth undertaking. Note that there can only be one B/C ratio for a project (unlike IRR which can at times have multiple values) Problem: The City...
explain project cost-benefit analysis?
explain project cost-benefit analysis?
A project manager decided to use critical ratio (C/Rij for WP j of project i) to...
A project manager decided to use critical ratio (C/Rij for WP j of project i) to prioritize and schedule the remaining work packages to be done for three concurrent projects with the data in the table below. The technical sequence (precedence) are WP1>WP2>WP4>WP4, for each of the three projects. For an illustration, the first project is due by day 4. Its first work package requires 2 days at workstation 1. Project ID Due Date Processing time for WP1 Processing time...
A DOT is performing a benefit-cost analysis of a new highway using an analysis period of...
A DOT is performing a benefit-cost analysis of a new highway using an analysis period of 40 years as part the required environmental impact assessment of the project. The section of highway is estimated to have a construction cost $220 million dollars. The public benefit in reduced travel time and economic development around the highway is estimated to be $17 million per year for the first 5 years, then decrease by 3% per year for the remainder of the 40...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i =...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i = 12% and n = infinity, then the net present worth of this project is most nearly: a) 20.84 b) 41.67 c) 30.25 d) 50.00 e) 22.40 f) No correct answer above
Use the following table solve the Benefit Cost Ratio , NPV benefits (Please show excel formulas...
Use the following table solve the Benefit Cost Ratio , NPV benefits (Please show excel formulas as well) Discount rate 0.08 0 1 2 3 System A Costs Hardware 14000 3000 3000 3000 Software 12000 2000 2000 1000 Services 2500 2500 2500 2500 Benefits Increased productivity 15000 10000 5000 Lower Error rates 18000 5000 6000 System B Costs Hardware 15000 3000 3000 3000 Software 12000 4000 2000 5000 Services 7000 3000 3000 1000 Benefits Increased productivity 7000 10000 10000 Reduced...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT