Question

In: Economics

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most...

The first cost, life, and annual benefit for a prospective project are uncertain. Optimistic (OP), most likely (ML), and pessimistic(PS) estimates are given. If the interest rate is 20%, what is the expected NPV?

Parameter Pessimistic Most Likely Optimistic
Fist cost 150000 100000 80000
Annual benefit 25000 45000 50000
Project life 5 7 9

Solutions

Expert Solution

Interest rate = 20%

Pessimistic:

First cost = 150,000

Annual benefit = 25,000

Life = 5 years

Net present value is calculated as: [First Cost - Present value of annual benefit]

Year Annual Benefit Present value of annual benefit
1 25000 20833.33
2 25000 17361.11
3 25000 14467.59
4 25000 12056.33
5 25000 10046.94
74,765.30

Net present value = -150,000 + 74,765.3 = 75,234.70

Most Likely:

First cost = 100,000

Annual benefit = 45,000

Life = 7 years

Net present value is calculated as: [First Cost - Present value of annual benefit]

Year Annual Benefit Present value of annual benefit
1 45000 37500.00
2 45000 31250.00
3 45000 26041.67
4 45000 21701.39
5 45000 18084.49
6 45000 15070.41
7 45000 12558.67
162,206.63

Net present value = -100,000 + 162,206.63 = 62,206.63

Optimistic:

First cost = 80,000

Annual benefit = 50,000

Life = 9 years

Net present value is calculated as: [First Cost - Present value of annual benefit]

Year Annual Benefit Present value of annual benefit
1 50000 41666.67
2 50000 34722.22
3 50000 28935.19
4 50000 24112.65
5 50000 20093.88
6 50000 16744.90
7 50000 13954.08
8 50000 11628.40
9 50000 9690.33
201,548.33

Net present value = -80,000 + 201,548.33 = 121,548.33


Related Solutions

Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost...
Use PWs to calculate the benefit/cost ratio of i=5% for a highway project. The first cost is $150,000 and the O&M costs are $5000 per year. There is no salvage value after 20 years. Time savings to users are worth $35,000 per year, and neighborhood disruption is a disbenefit of $10,000 per year. Is this project attractive?
A tractor has a first cost of $40,000, a monthly op- erating cost of $1500, and...
A tractor has a first cost of $40,000, a monthly op- erating cost of $1500, and a salvage value of $12,000 in 10 years. The MARR is 12% per year. An identical tractor can be rented for $3200 per month (operating cost not included). If n is the minimum number of months per year the tractor must be used in order to justify its purchase, the relation to find n is represented by: Determine the number of month for breakeven...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i =...
A government project has $500 of initial cost and 62.5 uniform annual benefit. If i = 12% and n = infinity, then the net present worth of this project is most nearly: a) 20.84 b) 41.67 c) 30.25 d) 50.00 e) 22.40 f) No correct answer above
explain project cost-benefit analysis?
explain project cost-benefit analysis?
A project has a first cost P, annual savings A and a salvage value of $500...
A project has a first cost P, annual savings A and a salvage value of $500 at the end of its 10-year service life. It is also known that the IRR for this project is 11 %, and the payback period is 8 years. What is the project's first cost? (Don't use the $ sign and coma in your answer!)
A project has a cost of $10 million, a useful life of 30 years, annual operation...
A project has a cost of $10 million, a useful life of 30 years, annual operation and maintenance costs equal 2% of the capital cost, and annual benefit of $1.5 million.. 1. Find the simple payback period of the project. 2. Find out benefit-cost ratio if the discount rate is 10%
1. project initial cost (incurred at beginning of year 1) Project life Salvage value Positive annual...
1. project initial cost (incurred at beginning of year 1) Project life Salvage value Positive annual cash flow (received at the end of each year) A $200000 16 years $0 $28000 B $56000 14 years $0 $9783 B is higher than the Internal Rate of Return of project A. Required: A) Is the NPV for Project A higher than, equal to, or lower than, the NPV for Project B, assuming a 10% discount rate? B) Is the Payback Period for...
sparta corp. has a prospective project with an irr of 7.25%. its cost of preferred equity,...
sparta corp. has a prospective project with an irr of 7.25%. its cost of preferred equity, cost of common equity, and post-tax cost of debt are 7%, 9%, and 4%, respectively, and sparta raises equal amounts of funding from all these three sources. choose the best statement: A- the project’s required rate of return must be greater than 7.25%. B- the project’s net present value (npv) must be $0. C- the project’s npv must be negative. D- the project’s npv...
What is the NPV of the project? Project life: 3 years Equipment: Cost: $18,000 Economic life:...
What is the NPV of the project? Project life: 3 years Equipment: Cost: $18,000 Economic life: 3 years Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect.
Do we have to ignore value of human life in benefit cost analysis?
Do we have to ignore value of human life in benefit cost analysis?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT