In: Accounting
Cost Information and the Weighted Average Method
Morrison Company had the equivalent units schedule and cost information for its Sewing Department for the month of December, as shown below.
Direct Materials | Conversion Costs | ||||||
Units completed | 48,000 | 48,000 | |||||
Add: Units in ending work in process × | |||||||
Percentage complete: | |||||||
17,000 × 100% direct materials | 17,000 | — | |||||
17,000 × 40% conversion materials | — | 6,800 | |||||
Eqivalent units of output | 65,000 | 54,800 | |||||
Costs: | |||||||
Work in process, December 1: | |||||||
Direct materials | $60,000 | ||||||
Conversion costs | 12,000 | ||||||
Total work in process | $72,000 | ||||||
Current costs: | |||||||
Direct materials | $500,000 | ||||||
Conversion costs | 186,000 | ||||||
Total current costs | $686,000 |
Required:
1. Calculate the unit cost for December, using
the weighted average method. Do NOT round interim calculations and,
if required, round your answer to the nearest cent.
$ per equivalent unit
2. Calculate the cost of goods transferred out, calculate the cost of EWIP, and reconcile the costs assigned with the costs to account for.
Cost of goods transferred out:
Units completed | $ |
Cost of EWIP | |
Total costs assigned (accounted for) | $ |
Reconciliation
Cost to account for:
BWIP | $ |
Current (December) | |
Total | $ |
3. What if you were
asked to show that the weighted average unit cost for materials is
the blend of the November unit materials cost and the December unit
materials cost? The November unit materials cost is $3.53
($60,000/17,000), and the December unit materials cost is $10.42
($500,000/48,000). The equivalent units in BWIP are 17,000, and the
FIFO equivalent units are 48,000. Calculate the weighted average
unit materials cost using weights defined as the proportion of
total units completed from each source (BWIP output and current
output). Do NOT round interim calculations and, if required, round
your answer to the nearest cent.
$ per unit
Answer 1:
Answer 2:
Working:
Answer 3:
Units completed = 48000
Which will consists of:
BWIP of 17,000 units completed plus
31,000 units of completed out of units started in December.
Hence:
Weighted average cost of material = (3.53 * 17000 + 10.42 * 31000) / (17000 + 31000) = $7.98