In: Accounting
Weighted Average Method, Equivalent Units, Unit Cost, Multiple Departments
Fordman Company has a product that passes through two processes: Grinding and Polishing. During December, the Grinding Department transferred 20,000 units to the Polishing Department. The cost of the units transferred into the second department was $40,000. Direct materials are added uniformly in the second process. Units are measured the same way in both departments.
The second department (Polishing) had the following physical flow schedule for December:
Units to account for: | ||
Units, beginning work in process | 4,000 | (40% complete) |
Units started | ? | |
Total units to account for | ? | |
Units accounted for: | ||
Units, ending work in process | 8,000 | (50% complete) |
Units completed | ? | |
Units accounted for | ? |
Costs in beginning work in process for the Polishing Department were direct materials, $5,000; conversion costs, $6,000; and transferred in, $9,000. Costs added during the month: direct materials, $32,000; conversion costs, $48,000; and transferred in, $39,000.
Required:
1. Assuming the use of the weighted average method, prepare a schedule of equivalent units. Enter percentages as whole numbers.
Direct Materials | Conversion Costs | Transferred In | |
Ending WIP: | |||
x % |
|||
x % |
|||
2. Compute the unit cost for the month. If
required, round your answer to the nearest cent.
$ per equivalent unit
The second department (Polishing) had the following physical flow schedule for December:
Units to account for: | ||
Units, beginning work in process | 4,000 | (40% complete) |
Units started | 24000 | |
Total units to account for | 28000 | |
Units accounted for: | ||
Units, ending work in process | 8,000 | (50% complete) |
Units completed | 20000 | |
Units accounted for | 28000 |
. Assuming the use of the weighted average method, prepare a schedule of equivalent units. Enter percentages as whole numbers.
Direct Materials | Conversion Costs | Transferred In | |
Unit Transferred out | 20000 | 20000 | 20000 |
Ending WIP: | |||
x 100% |
8000 | 8000 | |
x 50% |
4000 | ||
Equivalent unit | 28000 | 24000 | 28000 |
2. Compute the unit cost for the month. If required, round your answer to the nearest cent.
Transferred in Cost per equivalent unit = (9000+39000)/28000 = 1.71
Direct material cost per equivalent unit = (5000+32000)/28000 = 1.32
Conversion Cost per equivalent unit = (6000+48000)/24000 =
2.25
$5.28 per equivalent unit