Question

In: Finance

Project A has a 10 percent cost of capital and the followingcash flows: (3) Project...

Project A has a 10 percent cost of capital and the following cash flows: (3) Project A Year Cash Flow 0 -$300 1 100 2 150 3 200 4 50 What is Project A’s discounted payback? a. 2.25 years b. 2.36 years c. 2.43 years d. 2.50 years e. 2.57 years

Solutions

Expert Solution

Option e = 2.57 years

Calculation of Discounted Payback Period:

Here, Discount rate = 10%


Related Solutions

Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project U Time: 0 1 2 3 4 5 Cash flow: –$1,000 $350 $1,480 –$520 $300 –$100 show how to do this in excel and the excel formulas You have to show what the excel formulas are pls
Compute the MIRR statistic for Project J if the appropriate cost of capital is 10 percent....
Compute the MIRR statistic for Project J if the appropriate cost of capital is 10 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.) Project J Time: 0 1 2 3 4 5 Cash flow: −$1,000 $350 $1,480 −$520 $300 −$100 MIRR ______ % Should the project be accepted or rejected?
10-10. Project A has a cost of $22,000 and is expected to produce benefits (cash flows)...
10-10. Project A has a cost of $22,000 and is expected to produce benefits (cash flows) of $7,000 per year for 5 years. Project B costs $70,000 and is expected to produce cash flows of $20,000 per year for 5 years. Calculate the two projects' NPVs, IRRs, MIRRs, and PIs, assuming a cost of capital of 10%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?
Consider a project that has a 10% cost of capital that requires an initial investment of...
Consider a project that has a 10% cost of capital that requires an initial investment of $10,000. The year 1 net cash inflow is $2,450; the year 2 net cash inflow is $2,850; the year 3 net cash inflow is $3,350; the year 4 net cash inflow is $3,750; and the year 5 net cash inflow is $5,250. What is the project's discounted payback? NPV? AND IRR?
The project has the following cash flows and salvage values and cost of capital 8%: Year...
The project has the following cash flows and salvage values and cost of capital 8%: Year Cash flows Salvage 0 -5000 4000 1 2500 3500 2 3200 1800 3 1600 900 4 1000 0 What are the physical life and the economic life for this project? A. Physical life of this project is 3 years with economic life of 4 years. B. Physical life of this project is 4 years with economic life of 1 year. C. Physical life of...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $11,000 and is expected to...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $11,000 and is expected to produce benefits (cash flows) of $3,400 per year for 5 years. Project L costs $23,000 and is expected to produce cash flows of $6,900 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 14%. Round your answers to the nearest cent. Project S $       Project L $       Which project would be selected, assuming they are mutually exclusive?...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $11,000 and is expected to...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $11,000 and is expected to produce benefits (cash flows) of $3,400 per year for 5 years. Project L costs $23,000 and is expected to produce cash flows of $6,900 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 14%. Round your answers to the nearest cent. Project S $       Project L $       Which project would be selected, assuming they are mutually exclusive?...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $9,000 and is expected to...
Problem 10-10 Capital Budgeting Methods Project S has a cost of $9,000 and is expected to produce benefits (cash flows) of $2,700 per year for 5 years. Project L costs $26,000 and is expected to produce cash flows of $7,100 per year for 5 years. Calculate the two projects' NPVs, assuming a cost of capital of 10%. Round your answers to the nearest cent. Project S $     Project L $     Which project would be selected, assuming they are mutually exclusive?...
A firm with a cost of capital of 10% considers the following capital investment: Cash Flows:...
A firm with a cost of capital of 10% considers the following capital investment: Cash Flows: Year 0 -4 million Year 1 26.5 Million Year 2 -24.2 Million (A) According to the IRR given by your financial calculator, should the firm accept this project? (B) Up to how many IRRs could this project have? (C) According to the MIRR, should the firm accept this project? (D) Should the firm accept this project? Justify your answer using the NPV. (Please show...
What is the NPV for a project if its cost of capital is 0 percent and...
What is the NPV for a project if its cost of capital is 0 percent and its initial after-tax cost is $5,000,000 and it is expected to provide after-tax operating cash inflows of $1,800,000 in year 1, $1,900,000 in year 2, $1,700,000 in year 3, and $1,300,000 in year 4? Select one: a. $6,700,000 b. $137,053 c. $1,700,000 d. $371,764 Which of the following is TRUE? Select one: a. The Gordon model assumes that the value of a share of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT