In: Finance
Problem 10-10
Capital Budgeting Methods
Project S has a cost of $11,000 and is expected to produce benefits (cash flows) of $3,400 per year for 5 years. Project L costs $23,000 and is expected to produce cash flows of $6,900 per year for 5 years.
Calculate the two projects' NPVs, assuming a cost of capital of 14%. Round your answers to the nearest cent.
Project S | $ |
Project L | $ |
Which project would be selected, assuming they are mutually
exclusive?
-Select-Project SProject LItem 3
Project S | % |
Project L | % |
Which project would be selected, assuming they are mutually
exclusive?
-Select-Project SProject LItem 6
Calculate the two projects' MIRRs, assuming a cost of capital of 14%. Round your answers to two decimal places.
Project S | % |
Project L | % |
Which project would be selected, assuming they are mutually
exclusive?
-Select-Project SProject LItem 9
Project S | |
Project L |
Which project would be selected, assuming they are mutually
exclusive?
-Select-Project SProject LItem 12
Which project should actually be selected?
-Select-Project SProject LItem 13
a )
Project S : - NPV
NPV = Cash flow / ( 1 +r )1 + Cash flow / ( 1 +r )2 +Cash flow / ( 1 +r )3 - Initial investment
= 3400 / ( 1.14)1 + 3400 / ( 1.14)2 +3400 / ( 1.14)3 +3400 / ( 1.14)4 +3400 / ( 1.14)5 - 11000
= 2982.45 +2616.18 +2294.90 +2013.07 +1765.85 - 11000
=11672.48 - 11000
= $ 672.48
Project L :
NPV = 6900 / ( 1.14)1 + 6900 / ( 1.14)2 +6900 / ( 1.14)3 +6900 / ( 1.14)4 +6900 / ( 1.14)5 - 23000
= 6052.63 + 5309.32 + 4657.30 +4085.35 +3583.64 - 23000
= 23688.26 - 23000
= $ 688.26
Project L have higher NPV . so it should be selected
b )
IRR Project S = 16.52%
IRR Project l = 15.24 %
Here Project S have higher IRR than Project L. so it should be selected
c )
MIRR Project S = 15.36 %
MIRR Project L = 14.67%
Project S have higher MIRR than Project L. so Project S should be select
d )
Profitability index = Present value of cash inflow / initial investment
Project S
Present value of cash inflow = 11672.48
Initial invetsment = 11000
Profitability index = 11672.48 / 11000
= 1.076
Project L
Present value of cash inflow = 23688.26
Initial invetsment = 23000
Profitability index = 23688.26 / 23000
= 1.02
When they are mutually exclusive Higher PI should be select. here Project S have higher profitability index.so it should be selected
in general rule any profitability index results more than 1 should be selected. here both projects PI values are higher than 1.so both projects are selected