Question

In: Accounting

Bachmann Products, Inc., has found that new products follow a learning curve. The first two units...

Bachmann Products, Inc., has found that new products follow a learning curve. The first two units have been completed with the following results:

Units Produced Marginal Labor Time
1 80.00
2 56.00


How much time will be needed to complete the 8th unit?

62.00 hours.

39.20 hours.

32.00 hours.

27.44 hours.

Solutions

Expert Solution

The Answer of this question can be simply given through formula but I have explained knowingly it much lengthy to get conceptual clarity...

The learning curve is based on doubling of production

The first unit takes time of 80 hours. i.e when production doubles decrease in time per unit affect the rate of learning curve.

Time required for (N)th unit = T × L​​​​​​n

where T= Unit time of 1st unit. L = Learning curve rate. n = No of times T is doubled.

​​​​since, 1st unit takes 80 hours

It's double is second unit takes 56 hours

Applying the formula , Time required for 2nd unit = 1st unit time × L​​​​​n.

  i.e. 56 = 80 × L​​​​​​1

Therefore, Learning rate (L) = 70% i.e. 0.7

Since we know each time when the production doubles, labor per unit declines by a constant factor, known as the learning rate.

Accordingly as the unit doubles to 4 units then 8 units the time taken in hours to complete the product to be declined or reduced to 70% of earlier time taken.

Hence the time taken for 4th unit will be 70% of 56 hours ( i.e time taken for 2nd unit.)

So time taken for 4th unit will be = 56× 70% = 39.2 hours.

Further time taken for 8th unit will be 70% of 39.2 hours ( i.e. time taken for 4th unit.)

So time taken for 8th unit will be = 39.2 × 70% = 27.44 hours.

Answer: Time taken to complete 8th unit = 27.44 hours.


Related Solutions

Airbus has found an 80% learning curve applies to direct labor for new production items. The...
Airbus has found an 80% learning curve applies to direct labor for new production items. The first set of a new wing designed for a plane required 1,000 direct labor hours. How many total direct labor hours should be required to complete 16 sets of wings?
Airbus has found an 80% learning curve applies to direct labor for new production items. The...
Airbus has found an 80% learning curve applies to direct labor for new production items. The first set of a new wing designed for a plane required 6,000 direct labor hours. How many total direct labor hours should be required to complete 16 sets of wings?
An analyst has estimated that there will be an 84% learning curve for an assembly operation....
An analyst has estimated that there will be an 84% learning curve for an assembly operation. The first assembly takes 48 minutes and the standard time is set at 6 minutes. a. How long will it take the operator to reach the standard time? b. Unfortunately, the operator falls ill after the first week on the new assembly operation and returns after one week. What will be the estimated time for the operator to reach standard time now?
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production Rims 0.30 27,000 units Posts 0.50 75,000 units Additional information about the company follows: Rims require $12 in direct materials per unit, and Posts require $10. The direct labor wage rate is $20 per hour. Rims are more complex to manufacture than Posts and they require special equipment. The ABC system has the following activity cost pools:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow: Direct Labor-Hours per unit Annual Production Rims 0.30 26,000 units Posts 0.50 70,000 units Additional information about the company follows: Rims require $15 in direct materials per unit, and Posts require $11. The direct labor wage rate is $15 per hour. Rims are more complex to manufacture than Posts and they require special equipment. The ABC system has the following activity cost pools: Estimated...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production   Rims 0.70         22,000 units      Posts 0.70         79,000 units        Additional information about the company follows: a. Rims require $17 in direct materials per unit, and Posts require $14. b. The direct labor wage rate is $19 per hour. c. Rims are more complex to manufacture than Posts and they require special equipment. d....
first unit of a product took 900 hour to build and learning curve 90%. how long...
first unit of a product took 900 hour to build and learning curve 90%. how long will it take to make the first 3 units
Data regarding the two products follow: Direct Labor-Hours Per Unit Annual Production Hubs 0.70 10,000 Units...
Data regarding the two products follow: Direct Labor-Hours Per Unit Annual Production Hubs 0.70 10,000 Units Sprockets 0.50 40,000 Units Additional information about the company follows: Hubs require $28 in direct materials per unit, and Sprockets require $16. The direct labor wage rate is $20 per hour. Hubs are more complex to manufacture than Sprockets and they require special equipment. The ABC System has the following activity cost pools: Activity Cost Pool (Activity Measure) Estimated Overhead Cost Activity        Hubs             ...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow: Direct Labour- Hours per Unit Annual Production   Rims 0.50 21,000 units   Posts 0.25 85,000 units Additional information about the company follows: Rims require $18 in direct materials per unit, and posts require $11. The direct labour wage rate is $17 per hour. Rims are more complex to manufacture than posts, and they require special equipment. The ABC system has the following activity cost pools:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow: Direct Labour- Hours per Unit Annual Production   Rims 0.70 31,000 units   Posts 0.35 135,000 units Additional information about the company follows: a. Rims require $17 in direct materials per unit, and posts require $10. b. The direct labour wage rate is $18 per hour. c. Rims are more complex to manufacture than posts, and they require special equipment. d. The ABC system has the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT