In: Accounting
Airbus has found an 80% learning curve applies to direct labor for new production items. The first set of a new wing designed for a plane required 6,000 direct labor hours. How many total direct labor hours should be required to complete 16 sets of wings?
· Learning Curve = 80%
· Working
No of sets |
No of DLHs per set |
Total Direct Labor hours |
1 |
6,000.00 |
6,000 |
2 |
4,800.00 |
9,600 |
4 |
3,840.00 |
15,360 |
8 |
3,072.00 |
24,576 |
16 |
2,457.60 |
39,322 |
· Calculation
No of sets |
No of DLHs per set |
Total Direct Labor hours |
1 |
6000 |
=6000*1 |
=1+1 |
=6000*80% |
=4800*2 |
=2+2 |
=4800*80% |
=3840*4 |
=4+4 |
=3840*80% |
=3072*8 |
=8+8 |
=3072*80% |
=2457.6*16 |
· Total Direct Labor hours required for 16 sets = 39,322 hours Answer