Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...

Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow: Direct Labor-Hours per unit Annual Production Rims 0.30 26,000 units Posts 0.50 70,000 units Additional information about the company follows: Rims require $15 in direct materials per unit, and Posts require $11. The direct labor wage rate is $15 per hour. Rims are more complex to manufacture than Posts and they require special equipment. The ABC system has the following activity cost pools: Estimated Activity Activity Cost Pool Activity Measure Estimated Overhead Cost Rims Posts Total Machine setups Number of setups $ 32,900 60 140 200 Special processing Machine-hours $ 114,800 4,000 0 4,000 General factory Direct labor-hours $ 1,404,000 6,000 72,000 78,000

. Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculations. Round your final answers to 2 decimal places.)

Solutions

Expert Solution

Solution- Unit production cost of rims: $ 28.45

Unit production cost of posts: $ 37.34

Workings:

Computation of unit product cost under ABC:

Rims Posts
$ $
Direct Material 390,000 ( 26,000 x $ 15) 770,000 ( 70,000 x $ 11)
Direct Labor 117,000 ( 0.30x $ 15 x 26,000) 525,000( 0.50 x $ 15 x 70,000)
Manufacturing Overhead
Machine Setup 9,780 ( $ 32,900 / 200 x 60) 23,030 ( $ 32,900 / 200 x 140)
Special Processing 114,800 0
General Factory 108,000( $ 1,404,000 / 78,000 x 6,000) 12,96,000 ( $ 1,404,000 / 78,000 x 72,000)
Total Production Cost 739,580 26,14,030
Number of units 26,000 70,000
Unit Production Cost 28.45 (739,580/26,000) 37.34 (26,14,030/70,000)

Related Solutions

Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production Rims 0.30 27,000 units Posts 0.50 75,000 units Additional information about the company follows: Rims require $12 in direct materials per unit, and Posts require $10. The direct labor wage rate is $20 per hour. Rims are more complex to manufacture than Posts and they require special equipment. The ABC system has the following activity cost pools:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:...
Performance Products Corporation makes two products, titanium Rims and Posts. Data regarding the two products follow:     Direct Labor-Hours per unit Annual Production   Rims 0.70         22,000 units      Posts 0.70         79,000 units        Additional information about the company follows: a. Rims require $17 in direct materials per unit, and Posts require $14. b. The direct labor wage rate is $19 per hour. c. Rims are more complex to manufacture than Posts and they require special equipment. d....
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow: Direct Labour- Hours per Unit Annual Production   Rims 0.50 21,000 units   Posts 0.25 85,000 units Additional information about the company follows: Rims require $18 in direct materials per unit, and posts require $11. The direct labour wage rate is $17 per hour. Rims are more complex to manufacture than posts, and they require special equipment. The ABC system has the following activity cost pools:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow:...
High-Calibre Products Corporation makes two products: titanium rims and posts. Data regarding the two products follow: Direct Labour- Hours per Unit Annual Production   Rims 0.70 31,000 units   Posts 0.35 135,000 units Additional information about the company follows: a. Rims require $17 in direct materials per unit, and posts require $10. b. The direct labour wage rate is $18 per hour. c. Rims are more complex to manufacture than posts, and they require special equipment. d. The ABC system has the...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:Additional information about the company follows:a. Hubs require $32 in direct materials per unit, and Sprockets require $13.b. The direct labor wage rate is $19 per hour.c. Hubs are more complex to manufacture than Sprockets and they require special equipment.d. The ABC system has the following activity cost pools:Determine the unit product cost of each cost using the ABC system.HubsSprocketsDirect MaterialsDirect LaborOverheadUnit costFogerty Company makes two...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:   ...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:    Direct Labor-Hours per Unit Annual Production   Hubs 0.80 12,000 units   Sprockets 0.40 53,000 units    Additional information about the company follows: a. Hubs require $38 in direct materials per unit, and Sprockets require $10. b. The direct labor wage rate is $15 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special equipment. d. The ABC system has the...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:   ...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:    Direct Labor-Hours per Unit Annual Production   Hubs 0.70 20,000 units   Sprockets 0.30 41,000 units    Additional information about the company follows: a. Hubs require $37 in direct materials per unit, and Sprockets require $12. b. The direct labor wage rate is $19 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special equipment. d. The ABC system has the...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:   ...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:    Direct Labor-Hours per Unit Annual Production Hubs 0.50 19,000 units Sprockets 0.10 47,000 units Additional information about the company follows: a. Hubs require $21 in direct materials per unit, and Sprockets require $12. b. The direct labor wage rate is $16 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special equipment. d. The ABC system has the following...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:   ...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:    Direct Labor-Hours per Unit Annual Production Hubs 0.80 12,000 units Sprockets 0.40 43,000 units Additional information about the company follows: a. Hubs require $21 in direct materials per unit, and Sprockets require $11. b. The direct labor wage rate is $17 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special equipment. d. The ABC system has the following...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:   ...
Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:    Direct Labor-Hours per Unit Annual Production Hubs 0.60 18,000 units Sprockets 0.20 51,000 units Additional information about the company follows: a. Hubs require $34 in direct materials per unit, and Sprockets require $18. b. The direct labor wage rate is $17 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special equipment. d. The ABC system has the following...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT