Case 2-22 Plantwide versus Departmental Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3, LO2-4] “Blast it!” said David...

Case 2-22 Plantwide versus Departmental Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3, LO2-4]

“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”

Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:

Department
Fabricating Machining Assembly Total Plant
Manufacturing overhead $ 350,000 $ 400,000 $ 90,000 $ 840,000
Direct labor $ 200,000 $ 100,000 $ 300,000 $ 600,000

Jobs require varying amounts of work in the three departments. The Koopers job, for example,
would have required manufacturing costs in the three departments as follows:

Department
Fabricating Machining Assembly Total Plant
Direct materials $ 3,000 $ 200 $ 1,400 $ 4,600
Direct labor $ 2,800 $ 500 $ 6,200 $ 9,500
Manufacturing overhead ? ? ? ?

Required:

1. Using the company's plantwide approach:

a.Compute the plantwide predetermined rate for the current year.

b.Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:

a.Compute the predetermined overhead rate for each department for the current year.

b.Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.

4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).

a.What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate?

b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?

Garrison 16e Rechecks 2017-08-08, 2018-08-21, 2018-08-31, 2018-09-04, 2018-09-27

This is the last question in the assignment. To submit, use Alt + S. To access other questions, proceed to the question map button.Next Visit question map

Question8of8Total8 of 8

Prev

Solutions

Expert Solution

Solution 1-a:

Plantwide Predetermined Overhead Rate = Total Plant Overhead / Total Plant Direct labor = $840000 / $600000 * 100 = 140%

Solution 1-b:

Manufacturing overhead applied to Koopers Job = Total Direct labor cost *140% = $9500*140% = $13300

Solution 2-a:

Computation of overhead rate for Each department
Particulars Fabricating Machining Assembly
Overhead cost of department $350,000 $400,000 $90,000
/Total direct labor Cost $200,000 $100,000 $300,000
Overhead rate of department 175% 400% 30%

Solution 2-b:

Computation of Manufacturing Overhead applied to Koopers Job
Particulars Fabricating Machining Assembly
Direct Labor $2800 $500 $6200
Overhead rate of department 175% 400% 30%
Manufacturing overhead applied $4900 $2000 $1860

Total Manufacturing overehad applied = $4900 + $2000 + $1860 = $8760

Solution 4-a:

Computation of Bid price on Koopers Job (Using Plantwide Overhead rate)
Particulars Amount
Total Direct material $4600
Total Direct Labor $9500
Total manufacturing Overhead applied $13300
Total manufacturing cost $27400
Bid Price ($27400*150%) $41100

Solution 4-b:

Computation of Bid price on Koopers Job (Using Departmental Overhead rate)
Particulars Amount
Total Direct material $4600
Total Direct Labor $9500
Total manufacturing Overhead applied $8760
Total manufacturing cost $22860
Bid Price ($22860*150%) $34290

Leave comment in case of any doubt or if answers don't match.


Related Solutions

Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3, LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 31,000 41,000 72,000 Fixed manufacturing overhead costs $ 740,000 $ 210,000 $ 950,000 Variable manufacturing overhead cost per machine-hour $ 5.50 $ 5.50    During the...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4] [The following information...
Exercise 2-15 Plantwide and Departmental Predetermined Overhead Rates; Job Costs [LO2-1, LO2-2, LO2-3,LO2-4] [The following information applies to the questions displayed below.] Delph Company uses a job-order costing system and has two manufacturing departments—Molding and Fabrication. The company provided the following estimates at the beginning of the year:    Molding Fabrication Total Machine-hours 20,000 30,000 50,000 Fixed manufacturing overhead cost $ 700,000 $ 210,000 $ 910,000 Variable manufacturing overhead cost per machine-hour $ 3.00 $ 1.00 During the year, the...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 90,000 Machine-hours required to support estimated production 45,000 Fixed manufacturing overhead cost $ 252,000 Variable manufacturing overhead cost per direct labor-hour $ 2.40 Variable manufacturing overhead cost per machine-hour $ 4.80 During the year, Job 550 was started and completed. The following information is...
Problem 2-16 (Algo) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order...
Problem 2-16 (Algo) Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 160,000 Machine-hours required to support estimated production 80,000 Fixed manufacturing overhead cost $ 480,000 Variable manufacturing overhead cost per direct labor-hour $ 5.00 Variable manufacturing overhead cost per machine-hour $ 10.00 During the year, Job 550 was started and completed. The following information...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing...
Problem 2-16 Plantwide Predetermined Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3] Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 155,000 Machine-hours required to support estimated production 77,500 Fixed manufacturing overhead cost $ 465,000 Variable manufacturing overhead cost per direct labor-hour $ 4.80 Variable manufacturing overhead cost per machine-hour $ 9.60 During the year, Job 550 was started and completed. The following information is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT