In: Accounting
Case 2-22 Plantwide versus Departmental Overhead Rates; Pricing [LO2-1, LO2-2, LO2-3, LO2-4]
“Blast it!” said David Wilson, president of Teledex Company. “We’ve just lost the bid on the Koopers job by $2,000. It seems we’re either too high to get the job or too low to make any money on half the jobs we bid.”
Teledex Company manufactures products to customers’ specifications and uses a job-order costing system. The company uses a plantwide predetermined overhead rate based on direct labor cost to apply its manufacturing overhead (assumed to be all fixed) to jobs. The following estimates were made at the beginning of the year:
Department | ||||||||
Fabricating | Machining | Assembly | Total Plant | |||||
Manufacturing overhead | $ | 350,000 | $ | 400,000 | $ | 90,000 | $ | 840,000 |
Direct labor | $ | 200,000 | $ | 100,000 | $ | 300,000 | $ | 600,000 |
Jobs require varying amounts of work in the three departments.
The Koopers job, for example,
would have required manufacturing costs in the three departments as
follows:
Department | ||||||||||||
Fabricating | Machining | Assembly | Total Plant | |||||||||
Direct materials | $ | 3,000 | $ | 200 | $ | 1,400 | $ | 4,600 | ||||
Direct labor | $ | 2,800 | $ | 500 | $ | 6,200 | $ | 9,500 | ||||
Manufacturing overhead | ? | ? | ? | ? | ||||||||
Required:
1. Using the company's plantwide approach:
a.Compute the plantwide predetermined rate for the current year.
b.Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
2. Suppose that instead of using a plantwide predetermined overhead rate, the company had used departmental predetermined overhead rates based on direct labor cost. Under these conditions:
a.Compute the predetermined overhead rate for each department for the current year.
b.Determine the amount of manufacturing overhead cost that would have been applied to the Koopers job.
4. Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead).
a.What was the company’s bid price on the Koopers job using a plantwide predetermined overhead rate?
b.What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost?
Garrison 16e Rechecks 2017-08-08, 2018-08-21, 2018-08-31, 2018-09-04, 2018-09-27
This is the last question in the assignment. To submit, use Alt + S. To access other questions, proceed to the question map button.Next Visit question map
Question8of8Total8 of 8
Prev
Solution 1-a:
Plantwide Predetermined Overhead Rate = Total Plant Overhead / Total Plant Direct labor = $840000 / $600000 * 100 = 140%
Solution 1-b:
Manufacturing overhead applied to Koopers Job = Total Direct labor cost *140% = $9500*140% = $13300
Solution 2-a:
Computation of overhead rate for Each department | |||
Particulars | Fabricating | Machining | Assembly |
Overhead cost of department | $350,000 | $400,000 | $90,000 |
/Total direct labor Cost | $200,000 | $100,000 | $300,000 |
Overhead rate of department | 175% | 400% | 30% |
Solution 2-b:
Computation of Manufacturing Overhead applied to Koopers Job | |||
Particulars | Fabricating | Machining | Assembly |
Direct Labor | $2800 | $500 | $6200 |
Overhead rate of department | 175% | 400% | 30% |
Manufacturing overhead applied | $4900 | $2000 | $1860 |
Total Manufacturing overehad applied = $4900 + $2000 + $1860 = $8760
Solution 4-a:
Computation of Bid price on Koopers Job (Using Plantwide Overhead rate) | |
Particulars | Amount |
Total Direct material | $4600 |
Total Direct Labor | $9500 |
Total manufacturing Overhead applied | $13300 |
Total manufacturing cost | $27400 |
Bid Price ($27400*150%) | $41100 |
Solution 4-b:
Computation of Bid price on Koopers Job (Using Departmental Overhead rate) | |
Particulars | Amount |
Total Direct material | $4600 |
Total Direct Labor | $9500 |
Total manufacturing Overhead applied | $8760 |
Total manufacturing cost | $22860 |
Bid Price ($22860*150%) | $34290 |
Leave comment in case of any doubt or if answers don't match.