Fogerty Company makes two products, titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours per Unit |
Annual Production |
||
Hubs | 0.60 | 18,000 | units |
Sprockets | 0.20 | 51,000 | units |
Additional information about the company follows:
a. Hubs require $34 in direct materials per unit, and Sprockets require $18.
b. The direct labor wage rate is $17 per hour.
c. Hubs are more complex to manufacture than Sprockets and they require special equipment.
d. The ABC system has the following activity cost pools:
Estimated | Activity | ||||
Activity Cost Pool (Activity Measure) | Overhead Cost | Hubs | Sprockets | Total | |
Machine setups (number of setups) | $ | 15,300 | 85 | 68 | 153 |
Special processing (machine-hours) | $ | 184,500 | 4,100 | 0 | 4,100 |
General factory (organization-sustaining) | $ | 174,000 | NA | NA | NA |
Required
2. Determine the unit product cost of each product according to the ABC system. (Round intermediate calculations and final answers to 2 decimal places.)
For hubs and sprockets
Direct materials:
Direct Labor:
Overhead:
Requirement 2, along with workings
Hubs | Sprockets | |||
Answer | Working | Answer | Working | |
Direct materials | $ 34.00 | [given] | $ 18.00 | [given] |
Direct labor | $ 10.20 | 0.60 DLHs x $ 17 | $ 3.40 | 0.20 DLHs x $ 17 |
Overhead | $ 10.72 | [ (85 x 100) + (4100 x 45)]/18000 units | $ 0.13 | [ (68 x 100) + (0 x 45)]/51000 units |
Unit cost | $ 54.92 | $ 21.53 |
--ABC workings
Activity Cost Pool | Overhead cost | Total Activity | Activity Rate | |
[A] | [B] | [C = A/B] | ||
Machine setups | $15,300 | 153 | $100.000 | per setup |
Special processing | $184,500 | 4100 | $45.00 | per MH |