Question

In: Finance

Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for...

Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for 5 years. The required return is 9%, and payback cutoff is 4 years.

A. What is the payback period?

B. What is the discounted payback period?

C. What is the NPV? D. What is the IRR?

E. Should we accept the project?

What method should be the primary decision rule?

When is the IRR rule unreliable?

Please include steps on how to solve and all parts to question. Thank you.

Solutions

Expert Solution

Answer:

Initial Outlay = $1,00,000

Annual Cash In-Flow = $ 25,000, Time Period = 5 Years

A) Payback Period: Initial Outlay/Cash Flow per year

Payback Period = 1,00,000/25,000 = 4 Years

B) Discounted Payback Period:

Year 0 Year 1 Year 2 Year 3 Year 4 Year 5
CashFlows -1,00,000 25,000 25,000 25,000 25,000 25,000
Present Value (Discounted at 9%) -1,00,000 22936 21042 19305 17711 16248
Cumulative PV of Cashflows (Discounted) 0 22936 43978 63282 80993 97241

Discounted Pay Back Period = Cumulative Value of PV of Cashflows (Discounted) upto 1 Lac (Initial Outlay)

So adding up Cash Flows we get: Cumulative Value of PV of Cashflows (Discounted) upto year 5 us 97,241 which is less than Initial outlay so discounted payback period is more than 5 year.

3) NPV = Present value of Cash Inflows - Present Value of Cash Outflows(Initial Investment)

NPV = 25,000/(1.09) + 25,000/(1.09)^2 + 25,000/(1.09)^3 + 25,000/(1.09)^4 + 25,000/(1.09)^5 - 1,00,000

NPV = 97241 - 100000

NPV = - $2759

IRR: Discount rate at which NPV is 0. or discount rate at which present value of cash inflows totals to initial investments (1,00,000)

at 9% discount rate: PV of Cash inflows = 97241

at 8% discount rate: PV of Cash inflows = 99,818

at 7.9% discount rate: PV of Cash inflows = 1,00,081

Using interpolation we get

IRR = 7.93%

D) No, we should not accept the project as IRR is less than cost of capital and NPV is negative

For primary decision NPV is preferred over other methods because of following points:

1) NPV assumes that cash flows are reinvested at cost of capital where as IRR assumes that cash flows are reinvested at IRR rate which is not a fair assumption

2) For unconventional cashflows there are multiple IRR possible, but there will only be one NPV

3) NPV helps to know the real creation of wealth for any project


Related Solutions

Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for...
Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for 5 years. The required return is 9%, and the required payback is 4 years. What is the payback period? What is the discounted payback period? What is the NPV? What is the AAR? What is the IRR? What is the MIRR? What is the PI? Should we accept the project? What decision rule should be the primary decision method? When is the IRR rule...
Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for...
Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for 5 years. The required return is 9%. What is the net present value of this investment? A) $ -2,758.72 B) $ -857.65 C) $1217.70 D) $10,525 E) $25,000
Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for...
Consider an investment that costs $100,000 and has a cash inflow of $25,000 every year for 5 years. The required return is 9% and required payback is 4 years. • What is the payback period? • What is the NPV? • What is the IRR? • Should we accept the project? What decision rule should be the primary decision method? When is the IRR rule unreliable? • •
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $27,300 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 21% and can claim 100% bonus depreciation on the investment. Suppose the opportunity cost of capital is 10%. Ignore inflation. a. Calculate project NPV for each company. (Do not...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $27,800 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 21% and can claim 100% bonus depreciation on the investment. Suppose the opportunity cost of capital is 11%. Ignore inflation. A.Calculate project NPV for each company. (Do not round...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $26,200 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 30% and can depreciate the investment for tax purposes using the five-year MACRS tax depreciation schedule. Suppose the opportunity cost of capital is 8%. Ignore inflation. a. Calculate project...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $26,600 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 21% and can claim 100% bonus depreciation on the investment. Suppose the opportunity cost of capital is 9%. Ignore inflation. Calculate the NPV for each company. What is the...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $27,700 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 21% and can claim 100% bonus depreciation on the investment. Suppose the opportunity cost of capital is 11%. Ignore inflation. a. Calculate project NPV for each company. (Do not...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $27,300 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 40% and can depreciate the investment for tax purposes using the five-year MACRS tax depreciation schedule. Suppose the opportunity cost of capital is 10%. Ignore inflation. a. Calculate project...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow...
A project requires an initial investment of $100,000 and is expected to produce a cash inflow before tax of $27,300 per year for five years. Company A has substantial accumulated tax losses and is unlikely to pay taxes in the foreseeable future. Company B pays corporate taxes at a rate of 40% and can depreciate the investment for tax purposes using the five-year MACRS tax depreciation schedule. Suppose the opportunity cost of capital is 10%. Ignore inflation. a. Calculate project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT