Question

In: Operations Management

Mini case study – Scottish Parliament: the £431m question Scotland’s new parliament building cost more than...

Mini case study – Scottish Parliament: the £431m question

Scotland’s new parliament building cost more than 10 times the original estimate and opened three years behind schedule.

Official cost estimates changed 10 times and ballooned from the initial £40 million estimate to a final £431 million.

The procurement model chosen for Holyrood in early 1998 has emerged as the root of the problem. A fast-track contracting method known as construction management was used to build the parliament. It works by splitting a large building job into numerous smaller packages that are designed, tendered and let independently of one another.

Its main advantage is to speed up construction, because the overall design does not have to be complete before basic building work can begin.

It does not allow a client to know the total cost of a project until well after work has begun. It is considered risky for the client, which is responsible for running each individual package – in this case more than 60.

The project cost escalated from about £40 million in 1997 to £109 million in 1999, £241 million in 2001 and £294 million in 2002, and finally £431 million in February 2004. There were 18,000 design change orders over the five years of construction, combining

to form a three-year delay. Requests for design freezes on three occasions were ignored. The reality is that construction management was the only contract option for a client

wanting to make an early start on a project that was still at the design concept stage.
It is also clear that this was a classic case of procurement expertise being bypassed. The procurement department at the Scottish Office was not involved in the project. It was

not consulted over the procurement model.
There is nothing wrong with construction management as a procurement route. It is

best suited to high-quality, potentially high-cost projects, where the client is fully engaged, has a clear goal and works closely with the supply side team.

Some estimates put the money lost to delays and backtracking over design changes at as much as £100 million. If one trade contractor has a problem, it tends to ripple through all the others and cause delay and changes. The contracts are with the client, so the client picks up the cost of that.

However, between the extremes of fixed speedy construction management, a host of options exist under the heading of ‘conventional’ procurement. Their structures affect the risk and control over the final design that falls to the client.

The ‘design and build’ route would have seen the project management team drawing up a detailed design brief, which the main contractor then builds. It leaves the contractor footing the bill for cost overruns, but freezes the design as well.

A middle-of-the-road option, prime contracting, keeps design more open, but cuts the risk of costs going up if things go wrong. This is because a contractor joins the client’s project management team, and brings its entire supply chain of proven builders and suppliers along.

Then there is management contracting, where the client retains the design brief fully and splits up the project into small packages to be individually let, as in construction management. However, a professional intermediary runs all of the contractors on a daily basis, although they are still contracted to the client, which pays for design alterations.

Management contracting may, it seems, have given a more stable framework to the project by introducing an industry expert to run the many contractors.

Construction management was not the most suitable procurement vehicle. Sir Michael Latham, whose influential 1994 report, ‘Constructing the Team’, called on the construction industry to move towards partnering in the supply chain, says that full partnering should have been used to share the risk between client and contractor.

Discussion Question:

1. What was the nature of the procurement including the organization that conducted it and Who was involved in the procurement?

2. What was the process followed (briefly)?

3. Critique the procedure indicating what went wrong and how costly it was.

4. Suggest necessary improvements.

Solutions

Expert Solution

1) In the given case the procurement model used was construction management. This involved breaking up of the overall project into smaller projects which were all treated independent of each other as separate units. However the decisions were taken by the individual project teams and central procurement was not a part of the decsion making process.

2) The broad process followed was the break-up of the building project into several small individual packages which were dealt with independently. Significantly the structure also meant that as part of the process a central procurement team was not consulted in deciding trade contracts.

3) The procurement team not being consulted on trade decisions means that their expertise in terms of negotiating better costs was not utilized at all. This resulted in project costs ballooning from 40 MM to almost 11x of that at 431 MM in 2004 by the time project was complete. Also the use of construction management technique implied that design changes were too frequent and this resulted in inordinate delays of over 3 years.

4) Improvements to look at would be in the way contracting is carried out. The essence of it is to have greater control over the project even while splitting up independent tasks. The approaches to be used could be a mix of prime contracting which leverages the contractor's supply team by making the contractor a part of the project management team; and management contracting, where a professional intermediary coordinates with the contractors of the independent units - much like a CEO functions with a leadership team.


Related Solutions

Mini-Case Study: Team Building at Global Green Books Publishing Global Green Books Publishing is continuing to...
Mini-Case Study: Team Building at Global Green Books Publishing Global Green Books Publishing is continuing to grow. As their eBook business continues to drive that growth, they now are continuing to add staff to be able to keep up with customer demand. Most all of the new people and many of the eBook staff have not worked together in the original print-based business area of the company, and indeed are new to the company and its culture. These new employees...
Question: Building a new refinery The construction and installation of a new refinery will cost $22...
Question: Building a new refinery The construction and installation of a new refinery will cost $22 million. In addition, a processing plant will also need to be constructed at a cost $6 million. This plant will need to be supplied with grinding machines, DMS flotation machines and other equipment at a total cost of $16 million. Kidman Resources' current fleet of Haul trucks, water carts and dump trucks will meet the needs for this project, however until recently, the fleet...
We will be using the Saxonville Sausage Case Study more than once. For this week, you...
We will be using the Saxonville Sausage Case Study more than once. For this week, you need to develop and submit the answers to the following questions related to the 'Saxonville Sausage Company' Case Study. What was Anne Banks main research objective? Could you identify the Marketing Research Process steps in what she designed? What type of research did she use: qualitative (focus groups) or quantitative (questionnaries)? Do you consider that she used a good marketing research approach?
Question-Case Study:                                        
Question-Case Study:                                                                                Read the following case study carefully and answer the questions given at the END. . Playing Monopoly: Microsoft The success of Bill Gates together with his company Microsoft and the most favors Windows computer operating systems that are still dominating the PC operating system market has always been an excellent example stimulating the youths in the It industry to follow. But the business success and seemingly amazing technology innovation should not be very strong reasons why the...
Case Study- I surveyed more than 500 hospitals. At one point I asked not to be...
Case Study- I surveyed more than 500 hospitals. At one point I asked not to be placed on Veterans hospital accreditation surveys. Not all but some of the Veterans Administration (VA) hospitals were very argumentative fearing the possibility of written citations. So much so that on a ride from one VA hospital in Pennsylvania to a Pittsburgh VA the referring VA hospital sent 3 staff members to chauffeur me to the Pittsburgh VA. They all argued my concerns that a...
Case Study- I surveyed more than 500 hospitals. At one point I asked not to be...
Case Study- I surveyed more than 500 hospitals. At one point I asked not to be placed on Veterans hospital accreditation surveys. Not all but some of the Veterans Administration (VA) hospitals were very argumentative fearing the possibility of written citations. So much so that on a ride from one VA hospital in Pennsylvania to a Pittsburgh VA the referring VA hospital sent 3 staff members to chauffeur me to the Pittsburgh VA. They all argued my concerns that a...
Tesco-Case Study Tesco is the UK’s largest food retailer, with a sales turnover of more than...
Tesco-Case Study Tesco is the UK’s largest food retailer, with a sales turnover of more than 67.5 billion. While it has some 638 stores in central Europe, and some 636 in the Far East, most are in the United Kingdom and Northern Ireland, where it has nearly 1,800. This number has increased rapidly as Tesco entered the convenience store market with deals such as the Tesco Express alliance with Esso to run grocery shops at petrol stations. The product range...
Please only provide short answers for the discussion topic and the case study question. No more...
Please only provide short answers for the discussion topic and the case study question. No more than 3 sentence response. Discussion Topic: What are the three major causes of brain damage in childhood? Discussion Topic: Why would you use distraction versus traction? Case Study: Adam is a 6-year-old boy who dove headfirst in the shallow end of a swimming pool. Unable to move, he sank to the bottom of the pool and was rescued by his mother. His father called...
Case Study – Does a Turtle Have More Rights Than a Human? Resolving Controversial Environmental Issues...
Case Study – Does a Turtle Have More Rights Than a Human? Resolving Controversial Environmental Issues As you have learned in the first chapter, you need to identify the issue, conclusion, and reasons when reading an article. Identifying the argument in the following essay will help you better understand and evaluate it. Ethical norms are ideas that guide our behavior. Everyone generally agrees that ethical norms are positive ways of behaving. Some examples of ethical norms are honest, cooperation, and...
For the case study section only: Only provide short answers for the case study No more...
For the case study section only: Only provide short answers for the case study No more than 2 sentence response. Answer all the questions in all case study scenarios. Michael is a 7-week-old breastfed infant with a 2-day history of irritability and poor feeding. Subjective Data Mom states that her infant has been “fussy” for the last 2 days. He feeds for only a “few” minutes at a time. He is breathing heavily and fast for 2 days. Objective Data...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT