In: Finance
1)A bond is currently priced at 10% of the face value. If it pays a coupon of $50 annually and mature in 5 years. What is the yield to maturity?
2) The clean Lake Investment Group wants to build a golf course with a clubhouse. It is estimated that the project will provide a net cash inflow of $94000 for the first year of operation and the cash flows are projected to grow at a rate of 3% per year forver. The golf course project requires an initial investment of $1470000. Calculate the NPV of the project assuming an opportunity cost of 12%
Part a:
YTM is the rate at which PV of Cash inflows are equal to Bond price when the bond is held till maturity.
YTM = Rate at which least +ve NPV + [ NPV at that Rate / Change
in NPV due to 1% inc in disc rate ] * 1%
Assuming Face Value of Bond is $ 1000
Year | Cash Flow | PVF/[email protected] | PV of Cash Flows | PVF/[email protected] | PV of Cash Flows |
1-5 | $ 50.00 | 1.1106 | $ 55.53 | 1.0992 | $ 54.96 |
5 | $ 1,000.00 | 0.0449 | $ 44.92 | 0.0437 | $ 43.73 |
PV of Cash Inflows | $ 100.45 | $ 98.69 | |||
PV of Cash Oiutflows | $ 100.00 | $ 100.00 | |||
NPV | $ 0.45 | $ -1.31 |
YTM = Rate at which least +ve NPV + [ NPV at that rate / Change in NPV due to Inc of 1% in Int Rate ] * 1% |
= 0.86 + [0.45 / 1.76 ] * 1% |
= 0.86 + [0.25 ] * 1% |
= 0.86 + [0.0025] |
= 0.8625 |
YTM is 0.8625 i,e 86.25%
Part B:
NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/
Rejected.
NPV < 0 , Project will be rejected.
PV of Cash inflows = CF1 / [ Ke - g ]
= $ 94000 / [ 12% - 3% ]
= $ 94000 / 9%
= $ 1044444.44
NPV = 1044444.44 - 1470000
= - $ 425,555.56
Pls do rate, if the answer is correct and comment, if any
further assistance is required.